Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD03-00653
StatusFinaled
Name IDAHO ELKS REHAB HOSPITAL INC
Site Address 510 N 2ND ST
Project NameIDAHO ELKS REHAB
Customer Number 
ePlanReviewNo
Description
Idaho Elks Rehabilitation Medical Office Building (Shell & Core) -To Construct a new 13,000 s.f., two story, medical office building shell & core and related site improvements. This building is constructed of concrete slab floors, steel structural frame, metal exterior studs and metal roof deck. This building is fully fire sprinklered. All construction per the apporoved plans and attached comment list. This is a shell and core permit only. No occupancy is allowed under this permit. Separate tenant improvemetn permits are required to finish this building for occupancy. PC#155-03/DRH02-00017/CZC97-26/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/22/200312/23/200312/23/2003APASS
DetailsRuss Owen
ok perm. 12/23/2003 1:09:33 PM
BLD-Final12/19/200312/22/200312/22/2003PCANC
DetailsDave Hannah
Nick; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes out of time reschedule for tomorrow am 12/22/2003 4:51:38 PM
FIRE-Final Inspection12/19/200312/22/200312/22/2003PPASS
DetailsRick Jackson
Nick; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
FIRE-Final Inspection12/19/200312/19/200312/19/2003PFAIL
DetailsRick Jackson
need door hardware; complete fire alarms 12/19/2003 4:59:26 PM
Code Occupancy Approval12/18/200312/18/200312/18/2003APASS
DetailsWm. Michael Meloy
Compliance met. 12/18/2003 11:11:41 AM
BLD-Framing/Rough-in12/15/200312/15/200312/15/2003PPART
DetailsDave Hannah
Nick -- shaft wall in the elevator; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes pass 12/15/2003 5:02:57 PM
BLD-Framing/Rough-in12/12/200312/12/200312/12/2003PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/12/2003 at 8:33:51 AM. Contact: ###-####. ceiling in south stair tower 12/12/2003 2:19:24 PM
BLD-Framing/Rough-in12/11/200312/11/200312/11/2003PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/11/2003 at 8:58:54 AM. Contact: ###-####. one hr wall east stair tower ok to cover 12/11/2003 2:09:36 PM
BLD-Framing/Rough-in12/9/200312/9/200312/9/2003PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/9/2003 at 8:36:09 AM. Contact: ###-####. ceiling grid in lobbys ok to drop in panels 12/9/2003 2:44:48 PM
BLD-Framing/Rough-in10/16/200310/17/200310/17/2003APART
DetailsDave Hannah
nick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in10/17/200310/17/200310/17/2003PPART
DetailsDave Hannah
nick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie steel studs ok to cover ext 10/17/2003 12:07:46 PM
BLD-Framing/Rough-in9/15/20039/15/20039/15/2003PPART
DetailsDave Hannah
nick; Phone #: ###-#### Internet Inspection Request from: Annette Moore red iron bolting mti doing specal inspection on welding and bolting along with all concrete work 9/15/2003 2:23:04 PM
BLD-Footing7/25/20037/28/20037/28/2003APART
DetailsDave Hannah
nick ###-#### mti on site test concrete and did rebar inspection 7/28/2003 11:19:29 AM
BLD-Footing7/24/20037/24/20037/24/2003PDONE
DetailsSteven Webb
rebar//early afternoon please//###-#### nick 4 columns and appr. 20' of wall-by special inspection. 7/24/2003 3:33:22 PM
BLD-Foundation7/21/20037/22/20037/22/2003APART
DetailsCarl Dependahl
###-####...steel in place ok, N,E, & South side walls; MTI onsite testing...ok pend reports... High slump, low air at 1st batch today... 7/22/2003 11:03:42 AM
BLD-Footing7/15/20037/16/20037/16/2003APART
DetailsDave Hannah
###-#### nick mti on site to do spec inspection and test concrete 7/16/2003 10:01:19 AM