Permanent Occupancy | | 5/26/2004 | 5/26/2004 | | DONE |
|
|
|
|
BLD-Final | 5/6/2004 | 5/7/2004 | 5/7/2004 | A | PASS |
Dave Hannah
|
|
|
Cathy has the card - David Southers, ###-#### ok for prem occ 5/7/2004 11:24:50 AM
|
BLD-Final | 4/2/2004 | 4/5/2004 | 4/5/2004 | A | FAIL |
Dave Hannah
|
|
|
darryl; Phone #: ###-#### Internet Inspection Request from: Barbara Moore doors closers ect 4/5/2004 12:43:36 PM
|
FIRE-Final Inspection | 4/2/2004 | 4/5/2004 | 4/5/2004 | A | PASS |
Rick Jackson
|
|
|
darryl; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Concrete | 8/25/2003 | 8/25/2003 | 8/25/2003 | P | PART |
Dave Hannah
|
|
|
DARRELL; Phone #: ###-#### Internet Inspection Request from: Darla Downspt deck srata on site looking at rebar and cables this is for the north half 8/25/2003 2:24:48 PM
|
BLD-Conference | 7/29/2003 | 7/29/2003 | 7/29/2003 | P | PASS |
Carl Dependahl
|
|
|
w/ Darrel re progress
|
BLD-Foundation | 6/25/2003 | 6/25/2003 | 6/25/2003 | P | PART |
Carl Dependahl
|
|
|
titan construction; Phone #: ###-#### Internet Inspection Request from: Barbara Moorewall at south ok pend SI reports 6/25/2003 10:47:31 AM
|
BLD-Foundation | 6/24/2003 | 6/24/2003 | 6/24/2003 | P | PART |
Dave Hannah
|
|
|
darryl; Phone #: ###-#### Internet Inspection Request from: Barbara Moore on site talked with supper strata is doing the spec inspection and they have been out several times and will final rebar placement befor placing concrete 6/25/2003 7:48:11 AM
|
BLD-Conference | 6/18/2003 | 6/18/2003 | 6/19/2003 | P | PASS |
Carl Dependahl
|
|
|
Darrel ###-#### ....re foundation issues... add'l insulation not req'd. 6/19/2003 2:32:50 PM
|
BLD-Footing | 6/9/2003 | 6/9/2003 | 6/9/2003 | P | FAIL |
Tony Young
|
|
|
titan construction; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
pending s. i. report,,, also need to have rebar lap per plans or letter from engineer stating lap is ok as built,,,,, 18" .vs 27" laps in tension rebar, as in footings 6/9/2003 2:38:54 PM
|