Permit Information
Permit NumberBLD03-00923
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project NameMicron Building #3
Customer NumberPCS4527
ePlanReviewNo
Description
Micron Building #3 * To demolish two existing cleanroom walls, excavate to 48" depth, pour new 42" deep concrete subfloor and retaining walls. To install new access floor system, grating and two new cleanroom walls to create Plenum #133, Photo Bay "D" #101U and Plenum #134. This remodel also includes replace the cleanroom ceiling, relocate 3 existing doors, as well as, new facilities piping, power and minor HVAC and exhaust duct modifications. This work is at an approximate 760 square foot area of the first floor of building #03 between grid lines 10.5&12 and E&F. All construction per the approved plans and redlined notes. PC#228-03/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection1/16/20041/16/20041/16/2004 PASS
DetailsJim Storey
BLD-Final10/23/200310/24/200310/24/2003APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/23/2003 at 12:21:50 PM. Contact: ###-####.
FIRE-Final Inspection10/23/200310/24/200310/24/2003APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/23/2003 at 12:20:52 PM. Contact: ###-####.
FIRE-Final Inspection10/14/200310/14/200310/14/2003PNR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/14/2003 at 7:38:49 AM. Contact: ###-####. Wayne called and said the sprinkler bracing isn't complete 10/14/2003 3:23:49 PM
BLD-Conference9/30/200310/1/200310/1/2003ACANC
DetailsJim Storey
waiting for paul or joe to call back.
BLD-Final9/30/20039/30/20039/30/2003PCANC
DetailsJim Storey
rachelle; Phone #: ###-#### Internet Inspection Request from: Annette Moore rolled over waiting for call back. 9/30/2003 4:42:03 PM
BLD-Conference8/14/20038/15/20038/15/2003APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/14/2003 at 10:07:30 AM. Contact: ###-####. Scheduled by a check f/d at floor 2 at final. ok to cover upon all trades r/i aproval. contractor via Hello! on 8/14/2003 at 10:07:30 AM. Contact: ###-####. 8/15/2003 12:46:33 PM
BLD-Footing7/24/20037/29/20037/29/2003APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/24/2003 at 3:14:20 PM. Contact: ###-####.wall forms ok. 7/29/2003 10:31:54 AM
BLD-Footing7/24/20037/29/20037/29/2003PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/24/2003 at 3:15:00 PM. Contact: ###-####.
BLD-Footing7/24/20037/28/20037/28/2003APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/24/2003 at 3:12:49 PM. Contact: ###-####.wall steel in place form work in progess. 7/28/2003 11:03:26 AM
BLD-Footing7/24/20037/28/20037/28/2003PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/24/2003 at 3:13:34 PM. Contact: ###-####.wip trans to am. 7/28/2003 1:41:19 PM
BLD-Footing7/23/20037/25/20037/25/2003APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/23/2003 at 9:10:41 AM. Contact: ###-####.
BLD-Footing7/23/20037/25/20037/25/2003PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/23/2003 at 9:11:50 AM. Contact: ###-####.
BLD-Footing7/24/20037/24/20037/24/2003PPASS
DetailsJim Storey
rebar ok. 7/24/2003 3:19:49 PM
BLD-Footing7/23/20037/24/20037/24/2003ACANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/23/2003 at 9:09:53 AM. Contact: ###-####.