Code Occupancy Approval | 1/8/2004 | 1/8/2004 | 1/8/2004 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance met. 1/8/2004 1:38:00 PM
|
Permanent Occupancy | | 1/8/2004 | 1/8/2004 | | DONE |
|
|
|
|
BLD-Final | 12/30/2003 | 12/31/2003 | 12/31/2003 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/30/2003 at 1:33:50 PM. Contact: ###-####. 12/31/2003 10:11:13 AM ok for perm occ 12/31/2003 10:12:07 AM
|
BLD-Final | 11/25/2003 | 11/26/2003 | 11/26/2003 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/25/2003 at 9:53:41 PM. Contact: ###-####. c/n on site 11/26/2003 3:26:44 PM
|
FIRE-Final Inspection | 11/25/2003 | 11/26/2003 | 11/26/2003 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/25/2003 at 9:53:02 PM. Contact: ###-####.
|
BLD-Final | 10/30/2003 | 10/31/2003 | 10/31/2003 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/30/2003 at 11:10:31 PM. Contact: ###-####. needs fire life safty 11/3/2003 7:54:06 AM
|
BLD-Final | 10/30/2003 | 10/31/2003 | 10/31/2003 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/30/2003 at 5:22:57 PM. Contact: ###-####.
|
FIRE-Final Inspection | 10/30/2003 | 10/31/2003 | 10/31/2003 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/30/2003 at 11:09:49 PM. Contact: ###-####. ADA ramp door hardware not lever; exit signs on 2nd floor to be relocated per plans; is basement lid to be enclosed?; door hardware on office doors; address 10/31/2003 4:26:41 PM
|
FIRE-Final Inspection | 10/30/2003 | 10/31/2003 | 10/31/2003 | A | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/30/2003 at 5:22:13 PM. Contact: ###-####.
|
BLD-Final | 10/29/2003 | 10/30/2003 | 10/30/2003 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/29/2003 at 8:08:56 PM. Contact: ###-####.needs other trades fanaled 10/30/2003 3:27:13 PM
|
FIRE-Final Inspection | 10/29/2003 | 10/30/2003 | 10/30/2003 | P | NR |
Troy Cobbley
|
|
|
Inspection was actually a conference. I went over the life safety notes with the contractor. Specifically the placement of fire extinguishers. 10/30/2003 2:37:57 PM
|
BLD-Framing/Rough-in | 8/13/2003 | 8/14/2003 | 8/14/2003 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/13/2003 at 7:54:01 PM. Contact: ###-####. shear ok to cover ext and int shear walls also ok to start covering int walls new office area first and sec floors foem seal is done contractor will cieling off on second floor hallway so mec can be checked after units are set 8/14/2003 4:02:10 PM
|
BLD-Framing/Rough-in | 8/12/2003 | 8/13/2003 | 8/13/2003 | A | NR |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 8/12/2003 at 4:02:41 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/13/2003 | 8/13/2003 | 8/13/2003 | P | FAIL |
Carl Dependahl
|
|
|
need plans... 8/13/2003 3:04:34 PM
|
BLD-Framing/Rough-in | 8/13/2003 | 8/13/2003 | 8/13/2003 | P | FAIL |
Carl Dependahl
|
|
|
complete air seal, provide plans 8/13/2003 3:01:06 PM
|
BLD-Framing/Rough-in | 8/10/2003 | 8/11/2003 | 8/11/2003 | P | CANC |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 8/10/2003 at 9:02:37 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/7/2003 | 8/8/2003 | 8/8/2003 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 8/7/2003 at 7:14:15 PM. Contact: ###-####....nail shear panels & sills per plan, obtain hvac ok; no further insp. 8/8/2003 11:51:16 AM
|
BLD-Foundation | 7/10/2003 | 7/11/2003 | 7/11/2003 | A | PART |
Carl Dependahl
|
|
|
jeremy stem wall; Phone #: ###-#### Internet Inspection Request from: Barbara Moore...pending strata's reports 7/11/2003 1:27:25 PM
|
BLD-Footing | 7/7/2003 | 7/8/2003 | 7/8/2003 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/7/2003 at 2:08:21 PM. Contact: ###-####.need compaction report from stradia special insp. for fill and rebar clearance from bottom of footing. ground in place. 7/8/2003 2:10:45 PM
|