BLD-Final | 3/1/2004 | 3/3/2004 | 3/3/2004 | P | PASS |
Russ Owen
|
|
|
dan ; Phone #: ###-#### Internet Inspection Request from: Annette Moore Ok for a perm oc. 3/2/2004 10:08:04 PM
|
Permanent Occupancy | | 3/3/2004 | 3/3/2004 | | DONE |
|
|
|
|
BLD-Final | 2/18/2004 | 2/18/2004 | 2/18/2004 | P | FAIL |
Russ Owen
|
|
|
dan ; Phone #: ###-#### Internet Inspection Request from: Annette Moore. called and left a message with dan, bottom handrails ext do not comply in exit tower. 2/18/2004 12:37:36 AM
|
BLD-Final | 2/2/2004 | 2/2/2004 | 2/2/2004 | P | PART |
Jim Storey
|
|
|
Gary; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes c/n made ok arch letter in your box/ handraillins missing back west stair wall mounts. 2/2/2004 4:03:49 PM
|
FIRE-Final Inspection | 1/8/2004 | 1/9/2004 | 1/9/2004 | A | FAIL |
Troy Cobbley
|
|
|
need alarm reports and could not test elevators 1/9/2004 10:31:52 AM
|
FIRE-Final Inspection | 1/9/2004 | 1/9/2004 | 1/9/2004 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety, fire alarm and fire sprinkler are finaled 1/9/2004 2:18:15 PM
|
BLD-Final | 1/7/2004 | 1/8/2004 | 1/8/2004 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 1/7/2004 at 4:03:10 PM. Contact: ###-####. issued a c/n ok for temp oc . 1/8/2004 5:05:48 PM
|
FIRE-Final Inspection | 1/7/2004 | 1/8/2004 | 1/8/2004 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the elevator has been tested, knox box is provided, signage per review note #33, remove plumbing pipe from sprinkler line at riser, provide address and paint curbing for fire dept access. Need NFPA 72 forms and monitoring verification 1/8/2004 10:06:42 AM
|
BLD-Framing/Rough-in | 12/29/2003 | 12/30/2003 | 12/30/2003 | A | FAIL |
Russ Owen
|
|
|
cell ###-#### 12/29/2003 3:43:53 PM > this needs penetrations of 1 hr walls completed. also went over this with contractor. 12/30/2003 12:08:57 PM
|
BLD-Other | 12/29/2003 | 12/29/2003 | 12/29/2003 | P | NH |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/29/2003 at 9:13:49 AM. Contact: ###-####. Called contractor unable to locate at job , need to meet with cont for this insp. 12/29/2003 3:39:40 PM
|
BLD-Framing/Rough-in | 12/10/2003 | 12/11/2003 | 12/11/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/10/2003 at 10:24:25 AM. Contact: ###-####. Got letter from architect no 1 hr shaft needed at ducts through floor as long as they are sealed tight which they are. Need narchitect to clairify insulation at exterior walla some not contionous contractor notified and will address soon 2 days. 12/11/2003 11:45:38 AM
|
BLD-Framing/Rough-in | 12/3/2003 | 12/3/2003 | 12/3/2003 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/3/2003 at 8:08:10 AM. Contact: ###-####. need to complete the 1 hr walls and shafts at second floor also shafts will need to be addressedas to how they will be built as offsets exist contractor on site notified. 12/4/2003 1:54:00 PM
|
BLD-Framing/Rough-in | 11/18/2003 | 11/20/2003 | 11/20/2003 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/18/2003 at 4:24:29 PM. Contact: ###-####. 1st floor framing minus elevator shaft OK 11/20/2003 5:05:55 PM
|
BLD-Framing/Rough-in | 11/14/2003 | 11/19/2003 | 11/18/2003 | P | CANC |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 11/14/2003 at 4:56:44 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Nov 18 2003 4:27PM.
|
BLD-Footing | 9/15/2003 | 9/15/2003 | 9/15/2003 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 9/15/2003 at 8:47:51 AM. Contact: ###-####. subject to s-i. 9/15/2003 12:38:52 AM
|
BLD-Foundation | 9/4/2003 | 9/5/2003 | 9/5/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 9/4/2003 at 8:44:54 AM. Contact: ###-####. ok subject to s-i. 9/4/2003 7:58:39 PM 9/4/2003 7:58:43 PM
|
BLD-Foundation | 9/4/2003 | 9/4/2003 | 9/4/2003 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 9/4/2003 at 8:44:15 AM. Contact: ###-####. ok subject to s-i. 9/4/2003 12:28:49 AM
|
BLD-Foundation | 8/28/2003 | 8/29/2003 | 8/29/2003 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/28/2003 at 1:49:16 PM. Contact: ###-####.
|
BLD-Foundation | 8/26/2003 | 8/27/2003 | 8/27/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/26/2003 at 2:32:41 PM. Contact: ###-####.subject to special inspection. 8/28/2003 9:37:42 AM
|
BLD-Footing | 8/25/2003 | 8/26/2003 | 8/26/2003 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/25/2003 at 9:18:48 AM. Contact: ###-####. Subject to s-i. 8/28/2003 12:17:27 PM
|
BLD-Footing | 8/21/2003 | 8/21/2003 | 8/21/2003 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 8/21/2003 at 8:34:33 AM. Contact: ###-####.
|