Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD03-01450
StatusFinaled
Name CHRIS CONNER CONSTRUCTION LL
Site Address 4636 N TORRIDON WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 3179 sq. ft. two story single family dwelling with a 910 sq. ft. attached three car garage and a 310 sq. ft. 2nd level wood deck per approved plans, all engineering/red-lining and attached conditions list. This lot is within a hillside area and is subject to the hillside ordinances. Class "A" roof and 30 ft. defensible space will be maintained. (1st floor 2674 sq. ft.)(2nd floor 505 sq. ft.) PC #398 CFH #03-00009 DJO
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/4/200312/5/200312/5/2003PPASS
DetailsTony Young
Scheduled by a contractor via Hello! on 12/4/2003 at 3:23:59 PM. Contact: ###-####.
BLD-Final12/4/200312/4/200312/4/2003PFAIL
DetailsSteven Webb
Scheduled by a contractor via Hello! on 12/4/2003 at 11:22:31 AM. Contact: ###-####. C/N has been issued by Insp. 415 12/4/2003 1:47:29 PM
BLD-Grading Inspection12/4/200312/4/200312/4/2003 PASS
DetailsRita DeYoung
Final grading and drainage approved. Recommended to Chris Connor that downspouts reaplace chains that were installed so that runoff can be more effectively transported away from the foundation.
BLD-Final11/28/200312/1/200312/1/2003PFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 11/28/2003 at 8:09:20 AM. Contact: ###-####.
need hillside and f/p signoff before a final inspection can be made 12/2/2003 10:48:57 AM
BLD-Wall cover10/2/200310/3/200310/3/2003APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 10/2/2003 at 7:28:31 AM. Contact: ###-####.
int. shear ok 10/3/2003 12:26:43 PM
BLD-Wall cover9/26/20039/29/20039/29/2003ACANC
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/26/2003 at 4:35:22 PM. Contact: ###-####. 9/29/2003 11:18:54 AM out of time rescheduled for pm 9/29/2003 11:22:05 AM
BLD-Wall cover9/29/20039/29/20039/29/2003PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 9/26/2003 at 4:35:22 PM. Contact: ###-####.
still need to verify U value of windows, and interior shear 9/29/2003 12:33:44 PM
BLD-Framing/Rough-in9/23/20039/24/20039/24/2003AFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 9/23/2003 at 2:05:56 PM. Contact: ###-####.c/n posted 9/24/2003 2:41:03 PM
BLD-Framing/Rough-in9/24/20039/24/20039/24/2003PCANC
DetailsTony Young
BLD-Framing/Rough-in9/19/20039/23/20039/23/2003AFAIL
DetailsTony Young
Shear wall inspection please//Scheduled by a contractor via Hello! on 9/19/2003 at 7:26:00 AM. Contact: ###-####.
conf. only 9/23/2003 2:11:29 PM
BLD-Foundation7/22/20037/22/20037/22/2003PPART
DetailsDave Hannah
terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore work in progress forms up rebar in progress still needs to set hold downs 7/22/2003 2:48:22 PM
BLD-Footing7/15/20037/16/20037/16/2003APART
DetailsSteven Webb
TERRY; Phone #: ###-#### Internet Inspection Request from: Dixie Fellows wip--85% ready at time of inspection. 7/16/2003 11:53:12 AM
BLD-Grading Inspection7/16/20037/16/20037/16/2003 PASS
DetailsRita DeYoung
Footing subgrade has been approved by the geotechnical engineer.