Permanent Occupancy | | 3/16/2005 | 3/16/2005 | | DONE |
|
|
|
|
BLD-Final | 3/10/2005 | 3/11/2005 | 3/11/2005 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/10/2005 at 3:02:08 PM. Contact: ###-####.
|
BLD-Final | 3/11/2005 | 3/11/2005 | 3/11/2005 | P | PASS |
Tom Arcoraci
|
|
|
ok for perm 3/11/2005 1:31:12 PM
|
FIRE-Final Inspection | 3/11/2005 | 3/11/2005 | 3/11/2005 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until I get the NFPA record of completion forms and the map is placed.
|
FIRE-Final Inspection | 3/9/2005 | 3/9/2005 | 3/9/2005 | P | FAIL |
Troy Cobbley
|
|
|
Need to final the fire alarm permit. Add exit signs on east end of all floors as discussed and provide two additional fire extinguishers, one near the pool area and one near front desk 3/10/2005 3:49:09 PM
|
Code Occupancy Approval | 3/7/2005 | 3/7/2005 | 3/7/2005 | P | CANC |
Scott M.Brown
|
|
|
|
Code Occupancy Approval | 3/7/2005 | 3/7/2005 | 3/7/2005 | P | PASS |
Scott M.Brown
|
|
|
LOCATION LOOKS GOOD AND IN COMPLIANCE, I DID NOTE GRASS PAVERS FOR FIRE TRUCK TURN AROUND AREAS NEED TO BE IN PLACE FOR FIRE INSPECTION. 3/7/2005 4:25:35 PM
|
BLD-Other | 2/18/2005 | 2/18/2005 | 2/18/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/18/2005 at 11:11:10 AM. Contact: ###-####.
|
FIRE-Conference | 2/7/2005 | 2/7/2005 | 2/7/2005 | P | DONE |
Troy Cobbley
|
|
|
A stop work order has been issued and posted at the project for any fire alarm installation work after 2/7/05 at Mary's direction. Stop work order given to the superintendant at job site.
|
BLD-Other | 1/27/2005 | 1/27/2005 | 1/27/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/27/2005 at 11:10:06 AM. Contact: ###-####. 4 floor ok 1/27/2005 12:50:51 PM
|
BLD-Other | 1/13/2005 | 1/13/2005 | 1/13/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/13/2005 at 10:58:39 AM. Contact: ###-####. 3rd floor ok 1/13/2005 4:24:01 PM
|
BLD-Other | 1/3/2005 | 1/4/2005 | 1/4/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/3/2005 at 4:02:05 PM. Contact: ###-####. grid ok 2 floor 1/4/2005 10:51:06 AM
|
BLD-Energy code compliance | 12/22/2004 | 12/22/2004 | 12/22/2004 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/22/2004 at 10:05:34 AM. Contact: ###-####.
|
BLD-Wall cover | 12/7/2004 | 12/8/2004 | 12/8/2004 | P | PART |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 12/7/2004 at 11:45:53 AM. Contact: ###-####.ok to lay ceiling tile first floor corridor if all trades are approved for cover. 12/8/2004 3:44:46 PM
|
BLD-Energy code compliance | 11/29/2004 | 11/29/2004 | 11/29/2004 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/29/2004 at 9:39:37 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/16/2004 | 11/17/2004 | 11/17/2004 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/16/2004 at 3:39:36 PM. Contact: ###-####. 4 th floor ok to insulate 11/17/2004 10:20:05 AM
|
BLD-Conference | 11/2/2004 | 11/2/2004 | 11/2/2004 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Energy code compliance | 11/2/2004 | 11/2/2004 | 11/2/2004 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/2/2004 at 11:27:30 AM. Contact: ###-####.
|
BLD-Conference | 10/28/2004 | 10/29/2004 | 10/29/2004 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 10/26/2004 | 10/27/2004 | 10/27/2004 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/26/2004 at 2:57:57 PM. Contact: ###-####. 3rd floor ok 10/27/2004 11:04:44 AM
|
BLD-Conference | 10/20/2004 | 10/21/2004 | 10/21/2004 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Energy code compliance | 10/14/2004 | 10/14/2004 | 10/14/2004 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/14/2004 at 9:56:28 AM. Contact: ###-####. 3RD FLOOR 10/14/2004 4:17:51 PM
|
BLD-Framing/Rough-in | 10/8/2004 | 10/8/2004 | 10/8/2004 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/8/2004 at 11:27:02 AM. Contact: ###-####. 2nd floor ok 10/8/2004 3:56:38 PM
|
BLD-Conference | 10/6/2004 | 10/7/2004 | 10/7/2004 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 10/6/2004 | 10/6/2004 | 10/6/2004 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 10/5/2004 | 10/5/2004 | 10/5/2004 | P | PASS |
Tom Arcoraci
|
|
|
dry wall ok 1st floor 10/5/2004 1:41:43 PM
|
BLD-Energy code compliance | 9/30/2004 | 9/30/2004 | 9/30/2004 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/30/2004 at 10:07:50 AM. Contact: ###-####. 1st floor 9/30/2004 4:05:53 PM
|
BLD-Framing/Rough-in | 9/24/2004 | 9/24/2004 | 9/24/2004 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/24/2004 at 9:54:01 AM. Contact: ###-####. ok to insulate 1st floor 9/24/2004 3:21:14 PM
|
BLD-Framing/Rough-in | 9/23/2004 | 9/23/2004 | 9/23/2004 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/23/2004 at 10:08:21 AM. Contact: ###-####. wp ok 1st floor 9/23/2004 2:28:06 PM needs plumb pippes fire stopped 9/23/2004 2:28:25 PM
|
BLD-Framing/Rough-in | 9/2/2004 | 9/2/2004 | 9/2/2004 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/2/2004 at 9:17:42 AM. Contact: ###-####. wip ok 9/2/2004 4:48:55 PM
|
BLD-Framing/Rough-in | 8/18/2004 | 8/18/2004 | 8/18/2004 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/18/2004 at 8:42:42 AM. Contact: ###-####. wip ok 8/18/2004 2:51:00 PM
|
FIRE-Conference | 8/11/2004 | 8/11/2004 | 8/11/2004 | P | DONE |
Troy Cobbley
|
|
|
I stopped by the project to check on fire sprinkler system installaton progress and found backboxes for fire alarm devices installed. This includes boxes for audio/visual devices and smoke detectors. I spoke to Danny Robbins with Kendall Electric ###-####, who was the installer, about code requiring plans be submitted and approved prior to installation. I issued a stop work order which is placed on the north wall in the first floor electrical room. The fire alarm system is actually to be installed by Vanguard. I called Keith with Vanguard ###-####, and he stated that they had just gotten the contract the previous day and did not even have plans submitted yet. Mary Froemke verified this fact.
|
BLD-Conference | 8/2/2004 | 8/2/2004 | 8/2/2004 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 7/27/2004 | 7/28/2004 | 7/28/2004 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/27/2004 at 3:50:53 PM. Contact: ###-####. 4 floor shear ok 7/28/2004 9:11:31 AM
|
BLD-Framing/Rough-in | 7/19/2004 | 7/20/2004 | 7/20/2004 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/19/2004 at 2:34:18 PM. Contact: ###-####. shear ok as marked on plans 7/20/2004 9:56:52 AM
|
BLD-Conference | 6/22/2004 | 6/29/2004 | 6/29/2004 | A | PASS |
Tom Arcoraci
|
|
|
###-#### stan tom meeting at 9:00am
|
BLD-Framing/Rough-in | 6/28/2004 | 6/29/2004 | 6/29/2004 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 6/28/2004 at 3:12:18 PM. Contact: ###-####. shear wip ok 2 3 floor 6/29/2004 9:44:59 AM
|
BLD-Conference | 6/22/2004 | 6/28/2004 | 6/28/2004 | A | NR |
Tom Arcoraci
|
|
|
###-#### stan tom this conference should be with Dixie & Stan & you....thanks
|
BLD-Framing/Rough-in | 6/23/2004 | 6/23/2004 | 6/23/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/23/2004 at 9:52:07 AM. Contact: ###-####. Framing 1st floor corridor OK except for shear walls. 6/23/2004 2:09:49 PM
|
BLD-Framing/Rough-in | 6/21/2004 | 6/21/2004 | 6/21/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/21/2004 at 8:05:21 AM. Sch ed by a contractor via Hello! on 6/21/2004 at 8:05:21 AM. 6/21/2004 1:51:26 PM Inspection of (3) shear walls ...third floor. 10d 6 & 12...Ext OSB prior to covering with rock. Marked on plans. 6/21/2004 1:53:30 PM 6/21/2004 1:54:08 PM
|
BLD-Conference | 5/19/2004 | 5/19/2004 | 5/19/2004 | P | PASS |
Tom Arcoraci
|
|
|
meeting on fur outs and their construction also talked about 2 hr wall resub 5/19/2004 3:02:27 PM
|