BLD-Final | 6/8/2004 | 6/9/2004 | 6/9/2004 | A | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 6/8/2004 at 9:37:16 AM. Contact: ###-####.
|
BLD-Energy code compliance | 2/12/2004 | 2/12/2004 | 2/12/2004 | A | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 2/3/2004 | 2/4/2004 | 2/4/2004 | A | PASS |
Jim Storey
|
|
|
mike ; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Framing/Rough-in | 2/2/2004 | 2/3/2004 | 2/3/2004 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 2/2/2004 at 12:33:32 PM. Contact: ###-####. framing ok need engery sealant plk. 2/3/2004 11:24:58 AM
|
BLD-Framing/Rough-in | 1/7/2004 | 1/8/2004 | 1/8/2004 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/7/2004 at 2:36:37 PM. Contact: ###-####.
|
BLD-Foundation | 11/14/2003 | 11/18/2003 | 11/18/2003 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/14/2003 at 10:08:42 AM. Contact: ###-####.
|
BLD-Footing | 11/14/2003 | 11/17/2003 | 11/17/2003 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/14/2003 at 10:07:53 AM. Contact: ###-####.
|
BLD-Foundation | 11/12/2003 | 11/14/2003 | 11/14/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/12/2003 at 2:48:12 PM. Contact: ###-####. ft for garage and walls of dewlling ok rebar in place. 11/14/2003 10:07:56 AM
|
BLD-Footing | 11/10/2003 | 11/12/2003 | 11/12/2003 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/10/2003 at 11:48:20 AM. Contact: ###-####. house ft ok rebar ok will phase ft on grage. setbacks ok. 11/12/2003 10:32:08 AM
|