BLD-Final | 6/21/2004 | 6/21/2004 | 6/21/2004 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/21/2004 at 8:25:38 AM. Contact: ###-####. ok for perm occ 6/21/2004 3:13:18 PM
|
Permanent Occupancy | | 6/21/2004 | 6/21/2004 | | DONE |
|
|
|
|
BLD-Final | 6/16/2004 | 6/18/2004 | 6/18/2004 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/16/2004 at 11:07:27 AM. Contact: ###-####.
|
FIRE-Final Inspection | 6/16/2004 | 6/17/2004 | 6/17/2004 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 6/16/2004 at 11:05:47 AM. Contact: ###-####.
|
BLD-Final | 6/11/2004 | 6/15/2004 | 6/15/2004 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/11/2004 at 2:47:00 PM. Contact: ###-####.
|
FIRE-Final Inspection | 6/11/2004 | 6/14/2004 | 6/14/2004 | A | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 6/11/2004 at 2:45:20 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 4/22/2004 | 4/22/2004 | 4/22/2004 | P | PASS |
Jim Storey
|
|
|
Brandon -- ceiling grid; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes ok ceilling. 4/22/2004 2:00:43 PM
|
BLD-Framing/Rough-in | 4/8/2004 | 4/9/2004 | 4/9/2004 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/8/2004 at 1:12:46 PM. Contact: ###-####. beams and post added to pick up load for removal of bearing wall ok to cover cieling grid c/n item completed and insulation added to cantilevered floor area 4/9/2004 9:18:52 AM
|
BLD-Framing/Rough-in | 4/7/2004 | 4/8/2004 | 4/8/2004 | A | FAIL |
Russ Owen
|
|
|
out of time rolled over.Scheduled by a contractor via Hello! on 4/7/2004 at 9:29:30 AM. Contact: ###-####. Gave a c/n to contractor on site, for a beam and posts added in break room , for support of bearing floor joist above. Need engineering for this, Note:I only looked at the north end lower floor, non- bearing wall office partitions. And break room,No approval for any other portion of this building or re-inspection of any portion, no other inspection requested by builder. 4/7/2004 6:34:18 PM 4/7/2004 6:35:04 PM
|
BLD-Framing/Rough-in | 4/7/2004 | 4/7/2004 | 4/7/2004 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/7/2004 at 9:29:30 AM. Contact: ###-####.
|
FIRE-Conference | 3/26/2004 | 3/29/2004 | 3/29/2004 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 3/26/2004 at 11:50:06 AM. Contact: ###-####. Met with GC about requirements for final - sprinklers overspaced at draft stop; extinguishers overdue; gauge on riser broken; exit door hardware; knox box to main entrance; remove hose on from hose stations; clarify east exit door; repair draft stops 3/29/2004 9:23:29 AM
|
BLD-Other | 3/25/2004 | 3/26/2004 | 3/26/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/25/2004 at 3:47:41 PM. Contact: ###-####. min 6 inches support of mains/hvac support/insulate soffit and rim joist. 3/26/2004 4:31:23 PM
|
BLD-Framing/Rough-in | 3/2/2004 | 3/3/2004 | 3/3/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 3/2/2004 at 2:02:19 PM. Contact: ###-####. interior framing ok for cover. 3/3/2004 3:41:30 PM
|
BLD-Framing/Rough-in | 2/26/2004 | 2/26/2004 | 2/26/2004 | P | CANC |
Jim Storey
|
|
|
Brandon, ###-#### rolled per requist. 2/26/2004 11:37:04 AM
|
BLD-Framing/Rough-in | 2/26/2004 | 2/26/2004 | 2/26/2004 | P | PART |
Troy James
|
|
|
Brandon, ###-####
ok to sheetrock structural walls. Need solid risers to new stair and pony wall under stair. Need positive connection at wall plates to beam and beam to beam connection. 2/26/2004 1:08:44 PM
|
BLD-Framing/Rough-in | 2/24/2004 | 2/25/2004 | 2/25/2004 | A | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 2/24/2004 at 9:55:04 AM. Contact: ###-####.
|
BLD-Footing | 2/2/2004 | 2/3/2004 | 2/3/2004 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 2/2/2004 at 3:53:50 PM. Contact: ###-####.
|