(TITLE ONE)(FOREST RIVER VIII-2ND FLR-SUITE #200) Remodel for a new 11,566 sq. ft. expansion to an existing 2,780 sq. ft. office tenant on the second floor of an existing building per approved plans on file. The new tenant total will be 14,346 sq. ft. and the tenant will now occupy the entire second floor. Existing one-hour rated exit corridor on the floor is being downgraded to a non-rated corridor under this permit. Work to include miscellaneous interior demolition work, some new interior walls, some new interior doors, interior finish, fire sprinkler work including new quick-response heads throughout the entire floor, mechanical work, plumbing work, and electrical work. Accessible upgrade work will include providing an accessible stall in the Men's restroom and providing accessible door hardware throughout the whole floor. A new Certificate of Occupancy is to be issued when completed and approved. Original tenant permit was done under BLD02-02842. NOTE: This building is fully fire sprinklered for one-hour substitution. (PC#0634-03) JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/20/20045/20/20045/20/2004PPASS
DetailsDave Hannah
Don, ###-#### ok for perm occ 5/20/2004 2:21:46 PM
Permanent Occupancy 5/20/20045/20/2004 DONE
Details
BLD-Final5/17/20045/18/20045/18/2004AFAIL
DetailsDave Hannah
Don, ###-#### needs grab bars in ada stall and t/p desp 7-9 inches from front of bowl 5/18/2004 8:49:41 AM
BLD-Final3/25/20043/26/20043/26/2004PFAIL
DetailsDave Hannah
Don, ###-#### needs to finish ada mens restroom and ada signage at stair towers 3/26/2004 3:12:14 PM
FIRE-Final Inspection3/25/20043/25/20043/25/2004PPASS
DetailsRick Jackson
BLD-Framing/Rough-in2/23/20042/24/20042/24/2004PPART
DetailsDave Hannah
Don, ###-#### ph 3 infill walls ok to cover after elec r/i 2/24/2004 3:23:43 PM
BLD-Framing/Rough-in2/3/20042/3/20042/3/2004PPART
DetailsDave Hannah
Don, ###-#### ok to cover office in back 2/3/2004 4:15:53 PM
FIRE-Sprinkler Rough-in1/28/20041/29/20041/29/2004APART
DetailsRick Jackson
Don, ###-#### Not a sprinkler r/i inspection; This is a phased project - okay to occupy the south half - exits to be maintained 1/29/2004 9:25:20 AM
BLD-Conference1/27/20041/28/20041/28/2004ADONE
DetailsDave Hannah
phase one ok ok to move staff in to this area 1/28/2004 9:08:08 AM
BLD-Final1/27/20041/27/20041/27/2004PNR
DetailsDave Hannah
Don, ###-####
BLD-Conference12/3/200312/4/200312/4/2003APART
DetailsDave Hannah
###-#### don no mec permit needed super said they will only be moveing defuserers and duct detector can be innstalled under fire alem permit 12/4/2003 10:00:10 AM
FIRE-Conference12/3/200312/4/200312/4/2003APART
DetailsRick Jackson
don; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Met with Don and reviewed fire code notes. The alarm panel monitors trouble and alarm only and will require supervisory signal for the sprinkler monitoring; the panel will require a smoke detector above the panel and will need to monitor duct detectors for AHU shutdown; it is unclear if the alarm system is monitoring the 3 story elevator recall for primary and alternate floor 12/4/2003 8:33:30 AM
BLD-Framing/Rough-in11/26/200312/1/200312/1/2003APART
DetailsDave Hannah
Don, ###-#### 12/1/2003 11:18:03 AM west half infill walls ok to cover after elec r/i 12/1/2003 12:59:54 PM