BLD-Final | 6/30/2005 | 7/1/2005 | 7/1/2005 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/30/2005 at 3:46:30 PM. Contact: ###-####. OK for Perm Occ ():
|
Code Occupancy Approval | 6/30/2005 | 6/30/2005 | 6/30/2005 | P | PASS |
Scott M.Brown
|
|
|
OK FINAL SIGNED OFF
|
FIRE-Final Inspection | 6/29/2005 | 6/30/2005 | 6/30/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
Permanent Occupancy | | 6/30/2005 | 6/30/2005 | | DONE |
|
|
|
|
BLD-Energy code compliance | 4/26/2005 | 4/27/2005 | 4/27/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/26/2005 at 2:01:54 PM. Contact: ###-####.
|
BLD-Energy code compliance | 4/25/2005 | 4/26/2005 | 4/26/2005 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/25/2005 at 11:53:47 AM. Contact: ###-####. C/N on Misc Energy Code. 4/26/2005 10:52:16 AM
|
BLD-Framing/Rough-in | 4/21/2005 | 4/22/2005 | 4/22/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/21/2005 at 3:22:33 PM. Contact: ###-####. All framing pass. 4/22/2005 12:36:43 PM
|
BLD-Conference | 4/5/2005 | 4/6/2005 | 4/6/2005 | A | PART |
Jim Sly
|
|
|
roger; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Top layer of rock on tunnelized corridor OK. Framing for deck platform OK. 4/6/2005 10:18:55 AM
|
BLD-Framing/Rough-in | 3/15/2005 | 3/16/2005 | 3/16/2005 | A | PART |
Jim Sly
|
|
|
Roger; Phone #: ###-#### Internet Inspection Request from: Jan Rice Roof nailing and shear nailing OK. 3/16/2005 9:08:47 AM
|
BLD-Footing | 2/7/2005 | 2/7/2005 | 2/7/2005 | P | PART |
Jim Sly
|
|
|
ed; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Setbacks and reinforcing OK.......Need Special insp (3500psi) or Stamped letter from Engineer specifying concrete design strength 2500 or less. 2/7/2005 3:47:15 PM
|