Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD03-03027
StatusFinaled
Name BENCHMARK CONSTRUCTION
Site Address 3430 N MAPLE GROVE RD
Project NameKing of Glory Lutheran Church
Customer Number 
ePlanReviewNo
Description
King of Glory Lutheran Church (Addition) -To construct a 6,028 s.f. one story, Type VB, fully fire sprinklered classroom addition and interior/exterior remodel to existing church structure per the approved plans and attachments. CUP03-00098 Fire sprinklers used for area.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/10/20053/11/20053/11/2005APASS
DetailsJim Sly
kerry ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie OK for Perm Occ. :) 3/11/2005 8:53:57 AM
Permanent Occupancy 3/11/20053/11/2005 DONE
Details
BLD-Conference3/7/20053/8/20053/8/2005ACANC
DetailsJim Sly
Terry; Phone #: ###-#### Internet Inspection Request from: Jan Rice
BLD-Final2/10/20052/11/20052/11/2005PNR
DetailsJim Sly
terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore OK for Perm Occ. when Code Enforce sign off for Perm. 2/11/2005 4:17:24 PM
FIRE-Final Inspection2/10/20052/11/20052/11/2005APASS
DetailsTroy Cobbley
Fire life safety finaled 2/11/2005 8:43:36 AM
FIRE-Final Inspection2/4/20052/4/20052/4/2005AFAIL
DetailsTroy Cobbley
Paint curgbing for fire dept access as discussed and marked on approved drawings. Repair the two existing exit signs in the assembly hall. Provide occupant load signs for both assembly areas.
BLD-Framing/Rough-in1/27/20051/27/20051/27/2005PPASS
DetailsJim Sly
ceiling grid-- terry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in1/24/20051/25/20051/25/2005APASS
DetailsJim Sly
cieling grid inspection please///terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in1/20/20051/21/20051/21/2005PNR
DetailsJim Sly
Terry-ceiling grid; Phone #: ###-#### Internet Inspection Request from: Jan Rice
BLD-Framing/Rough-in1/7/20051/10/20051/10/2005APART
DetailsJim Sly
Terry; Phone #: ###-#### Internet Inspection Request from: Jan Rice Library and ajacent rooms. 1/10/2005 9:37:00 AM
BLD-Framing/Rough-in12/10/200412/13/200412/13/2004APART
DetailsJim Sly
Terry; Phone #: ###-#### Internet Inspection Request from: Jan Rice Soffits/ceiling framing at main hallway OK. Sprinkler inspection...OK. 12/13/2004 10:54:20 AM
BLD-Framing/Rough-in11/18/200411/19/200411/19/2004APART
DetailsJim Sly
ceiling grid inspection please////terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore 4 conditional use rooms OK for grid. 11/19/2004 11:44:29 AM
BLD-Conference10/27/200410/28/200410/28/2004APASS
DetailsJim Sly
terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Need Fire Guru blessing for partial Occ. on new and old areas befor finals. 10/28/2004 3:44:15 PM
FIRE-Conference10/28/200410/28/200410/28/2004PDONE
DetailsTroy Cobbley
Contractor wants to move people out of four existing offices into four new offices. Per Dave Miller Benchmark Construction needs to submit a letter to him stating what they want to do, why they can't get fire alarm and fire sprinkler systems operational at the time they do this and a time line on when work will be completed or else they will need to vacate. 10/28/2004 4:14:10 PM
BLD-Energy code compliance9/20/20049/20/20049/20/2004APASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/20/2004 at 7:05:09 AM. Contact: ###-####. Frame pass. 9/20/2004 12:15:30 PM
BLD-Framing/Rough-in9/13/20049/14/20049/14/2004PPART
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/13/2004 at 2:24:42 PM. Contact: ###-####. All OK except Need to check shear wall W of restrooms at energy code insp. 9/14/2004 1:53:33 PM
BLD-Framing/Rough-in9/8/20049/10/20049/10/2004PPART
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/8/2004 at 7:40:43 AM. Need straps at micros to wall, complete shear wall W.of restrms. OK to insulate.

9/10/2004 3:37:17 PM 9/10/2004 3:37:42 PM
BLD-Framing/Rough-in8/30/20048/31/20048/31/2004AFAIL
DetailsJim Sly
Scheduled by a contractor via Hello! on 8/30/2004 at 1:39:09 PM. Contact: ###-####. C/N mRemove all kraft facing from existing insul....OR protect. Framing OK. 8/31/2004 10:15:07 AM
BLD-Framing/Rough-in8/26/20048/27/20048/27/2004PPART
DetailsJim Sly
Scheduled by a contractor via Hello! on 8/26/2004 at 10:40:39 AM. Contact: ###-####. Framing in existing Bldg at daycare area...OK Note: Need to remove kraft paper on existing ceiling insulation. Foot and wall OK at front entry columns....N. wall. 8/27/2004 3:44:14 PM
BLD-Other8/24/20048/25/20048/25/2004PPART
DetailsJim Sly
terry - plywood inspect for new roof job; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles 8/25/2004 3:03:12 PM Roof OK. 8/25/2004 3:49:58 PM
BLD-Framing/Rough-in8/16/20048/18/20048/18/2004APART
DetailsLane Manuel
TERRY SHEAR WALL; Phone #: ###-#### Internet Inspection Request from: Annette Moore
Exter. shear nailing ok. LM 8/18/2004 11:05:22 AM
BLD-Foundation7/19/20047/20/20047/20/2004APART
DetailsTony Young
Scheduled by a contractor via Hello! on 7/19/2004 at 1:19:28 PM. Contact: ###-####.
c/n posted on changes and fix for rebar,, ok to pour if needed 7/20/2004 11:05:25 AM
BLD-Footing7/14/20047/15/20047/15/2004APASS
DetailsTroy James
Scheduled by a contractor via Hello! on 7/14/2004 at 3:53:15 PM. Contact: ###-####.