Permanent Occupancy | | 7/8/2005 | 7/8/2005 | | DONE |
|
|
|
|
BLD-Final | 5/26/2005 | 5/26/2005 | 5/27/2005 | P | PASS |
Dave Hannah
|
|
|
jeffrey///meet on 19th please; Phone #: ###-#### Internet Inspection Request from: Barbara Moore 18 19 and 20th floors ok for perm occ
|
FIRE-Final Inspection | 5/26/2005 | 5/26/2005 | 5/26/2005 | P | PASS |
Forrest France
|
|
|
20th floor passed inspection. Fire life safety finaled.
|
FIRE-Final Inspection | 5/25/2005 | 5/26/2005 | 5/26/2005 | A | PART |
Forrest France
|
|
|
19th floor passed inspection, 20th floor needs max occupant load sign posted in board room.
|
FIRE-Final Inspection | 3/16/2005 | 3/16/2005 | 3/16/2005 | P | CANC |
Troy Cobbley
|
|
|
danton; Phone #: ###-#### Do not have resubmitted fire sprinkler plans as requested to final fire permits. 3/16/2005 4:53:20 PM
|
BLD-Framing/Rough-in | 1/28/2005 | 1/31/2005 | 1/31/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/28/2005 at 10:48:16 AM. Contact: ###-####. elevator lobby on 19th floor and around stairs from 19 to 20th floor ok to cover 1/31/2005 12:50:02 PM
|
BLD-Framing/Rough-in | 12/29/2004 | 12/29/2004 | 12/29/2004 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/29/2004 at 11:00:37 AM. Contact: ###-####.
|
BLD-Final | 11/24/2004 | 11/29/2004 | 11/29/2004 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/24/2004 at 1:32:12 PM. Contact: ###-####. ok to start moving into offices on 18th floor 11/29/2004 2:06:44 PM
|
FIRE-Final Inspection | 11/29/2004 | 11/29/2004 | 11/29/2004 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/29/2004 at 9:45:52 AM. Contact: ###-####. Phased project - okay on the 18th floor only 11/29/2004 3:51:18 PM
|
BLD-Final | 11/23/2004 | 11/24/2004 | 11/24/2004 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/23/2004 at 3:33:42 PM. Contact: ###-####.
|
FIRE-Final Inspection | 11/23/2004 | 11/24/2004 | 11/24/2004 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/23/2004 at 3:33:00 PM. Contact: ###-####. Glazing at interior stair not installed; delay on lobby doors with mag locks is set at 40 seconds; extinguishers not tagged 11/24/2004 2:20:42 PM
|
FIRE-Final Inspection | 11/23/2004 | 11/23/2004 | 11/23/2004 | P | FAIL |
Rick Jackson
|
|
|
Mag hold opens on lobby doors need 30 second delay; glazing not installed at interior stair; extinguisehr needed in lease space and all extinguishers need annual tags 11/23/2004 2:51:39 PM
|
BLD-Other | 11/16/2004 | 11/17/2004 | 11/17/2004 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/16/2004 at 9:33:43 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/16/2004 | 11/16/2004 | 11/16/2004 | P | PART |
Dave Hannah
|
|
|
Danton; Phone #: ###-#### Internet Inspection Request from: Jan Rice 18th floor ok to cover ceiling grid ok 11/16/2004 3:01:07 PM
|
BLD-Framing/Rough-in | 10/7/2004 | 10/7/2004 | 10/7/2004 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/7/2004 at 8:48:09 AM. Contact: ###-####.restrooms ok to cover 10/8/2004 8:03:41 AM
|
BLD-Framing/Rough-in | 10/4/2004 | 10/5/2004 | 10/5/2004 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/4/2004 at 12:01:29 PM. Contact: ###-####. ok to cover walls on 18th floor allbut for plumbing walls 10/5/2004 12:53:23 PM
|
BLD-Framing/Rough-in | 9/30/2004 | 10/1/2004 | 10/1/2004 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/30/2004 at 8:35:09 AM. Contact: ###-####.ok tocover one side 18th floor 10/1/2004 1:27:14 PM
|
BLD-Conference | 9/21/2004 | 9/22/2004 | 9/22/2004 | P | DONE |
Dave Hannah
|
|
|
danton; Phone #: ###-#### Note: also to attend Rick Jackson for inspection Internet Inspection Request from: Barbara Moore rick jackson and my self walked floors with arct and went over exit signs 9/23/2004 8:00:09 AM
|