FIRE-Final Inspection | 11/7/2005 | 11/7/2005 | 11/7/2005 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Final | 11/7/2005 | 11/7/2005 | 11/7/2005 | A | DONE |
Mike Jordan
|
|
|
doug -; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie - ok for perm.
|
BLD-Conference | 7/19/2005 | 7/20/2005 | 7/20/2005 | A | PEND |
Mike Jordan
|
|
|
On site with George Slain regarding handrail issues for temp. occ. As per George Slain, ok to build temp. returns on on side of stairway and make one side of railing continous with a sign noting to use compliant side only.
|
BLD-Conference | 7/19/2005 | 7/20/2005 | 7/20/2005 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 7/20/2005 | 7/20/2005 | 7/20/2005 | P | PART |
Mike Jordan
|
|
|
ok for temp occ.
|
BLD-Final | 7/19/2005 | 7/19/2005 | 7/19/2005 | P | NR |
Tom Arcoraci
|
|
|
doug; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa hand rail issues need to be resolved for temp occ
|
FIRE-Alarm Testing | 7/18/2005 | 7/19/2005 | 7/19/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire alarm permit finaled
|
FIRE-Final Inspection | 7/19/2005 | 7/19/2005 | 7/19/2005 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Renn Ross's permission until all door hardware has been installed and approved and the one hour room for the fire sprinkler riser is complete. Dead bolts need to be removed from the three storage rooms and indicators need to be installed on the balcony doors.
|
BLD-Framing/Rough-in | 7/15/2005 | 7/18/2005 | 7/18/2005 | A | NR |
Mike Jordan
|
|
|
doug; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
FIRE-Final Inspection | 7/15/2005 | 7/15/2005 | 7/15/2005 | P | CANC |
Troy Cobbley
|
|
|
Request for temp; ###-####
|
FIRE-Final Inspection | 7/14/2005 | 7/14/2005 | 7/14/2005 | P | PASS |
Troy Cobbley
|
|
|
Paint curbs per sheet C-2, final fire alarm permit, provide one hour fire rated room per plans.
|
BLD-Conference | 7/13/2005 | 7/14/2005 | 7/14/2005 | A | DONE |
Mike Jordan
|
|
|
doug; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Code Occupancy Approval | | | 7/14/2005 | | PASS |
|
|
|
ALL IN AS REQUIRED FINAL SIGNED OFF.
|
FIRE-Final Inspection | 7/13/2005 | 7/13/2005 | 7/13/2005 | P | FAIL |
Troy Cobbley
|
|
|
Need to provide for fire dept access as discussed, shell drawings don't match what has been built, sprinkler riser room is supposed to be 1 hour rated and is not, provide address on Swordfish side of building, final fire alarm permit, need to test emergency lighting and exit signs and verify door hardware and extinguishers.
|
Code Occupancy Approval | | | 7/11/2005 | | FAIL |
|
|
|
NO HANDICAPPED SIGNS, MISSING SOME LANDSCAPE AND TREES ALONG EMERALD. ISSUED CORRECTION NOTICE
|
BLD-Framing/Rough-in | 6/17/2005 | 6/17/2005 | 6/17/2005 | P | PASS |
Mike Jordan
|
|
|
ceiling grid///doug; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. 2nd floor ok
|
BLD-Conference | 5/3/2005 | 5/4/2005 | 5/4/2005 | A | PART |
Jim Sly
|
|
|
doug; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Talked to Doug... Owners want to open W/O interior doors installed (carpet to be installed 1st) This is on T/I permit...... Need OK from Fire inspector before approving. 5/4/2005 9:54:44 AM 5/4/2005 10:03:18 AM
|
BLD-Other | 7/30/2004 | 8/2/2004 | 8/2/2004 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/30/2004 at 7:52:05 AM. Contact: ###-####. mti on site 8/2/2004 8:58:50 AM
|
BLD-Footing | 6/2/2004 | 6/3/2004 | 6/3/2004 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 6/2/2004 at 5:17:19 PM. Contact: ###-####. 6/3/2004 1:59:14 PM Tilt walls.... MTI special inspection. 6/3/2004 2:02:27 PM
|
BLD-Footing | 5/20/2004 | 5/21/2004 | 5/21/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/20/2004 at 2:52:04 PM. Contact: ###-####. Footings for South and West walls pending MTI special inspections, reports and approvals. 5/21/2004 3:45:51 PM
|
BLD-Footing | 4/29/2004 | 4/30/2004 | 4/30/2004 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/29/2004 at 3:08:23 PM. Contact: ###-####. Met with Stan (job super) and discussed special insp Req Etc.....MTI is the special insp agency.....Soils report OK......Pouring center footing pads and footings for stair towers......OK pending special inspection reports and approvals from MTI. 4/30/2004 11:11:11 AM
|