Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD04-00300
StatusFinaled
Name VIDEO EYE CORP
Site Address 9465 W EMERALD ST
Project NameVideo Eye Bldg
Customer Number 
ePlanReviewNo
Description
Video Eye Corporation (Shell & Core) - To construct a new 37,750 square foot, two story, concrete tilt-up office/warehouse shell and core building and related site improvements. All construction per the approved plans and attached comment list. The core work includes the stairways, elevator and second floor restrooms and corridor. This building will be fully fire sprinklered. This is a shell and core permit only. No occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. PC#094-04/DRH03-00167 Mod. #1/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection11/7/200511/7/200511/7/2005PPASS
DetailsTroy Cobbley
Life safety finaled
BLD-Final11/7/200511/7/200511/7/2005ADONE
DetailsMike Jordan
doug -; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie - ok for perm.
BLD-Conference7/19/20057/20/20057/20/2005APEND
DetailsMike Jordan
On site with George Slain regarding handrail issues for temp. occ. As per George Slain, ok to build temp. returns on on side of stairway and make one side of railing continous with a sign noting to use compliant side only.
BLD-Conference7/19/20057/20/20057/20/2005APASS
DetailsTom Arcoraci
BLD-Final7/20/20057/20/20057/20/2005PPART
DetailsMike Jordan
ok for temp occ.
BLD-Final7/19/20057/19/20057/19/2005PNR
DetailsTom Arcoraci
doug; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa hand rail issues need to be resolved for temp occ
FIRE-Alarm Testing7/18/20057/19/20057/19/2005APASS
DetailsTroy Cobbley
Fire alarm permit finaled
FIRE-Final Inspection7/19/20057/19/20057/19/2005PPART
DetailsTroy Cobbley
A temporary occupancy was given with Renn Ross's permission until all door hardware has been installed and approved and the one hour room for the fire sprinkler riser is complete. Dead bolts need to be removed from the three storage rooms and indicators need to be installed on the balcony doors.
BLD-Framing/Rough-in7/15/20057/18/20057/18/2005ANR
DetailsMike Jordan
doug; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
FIRE-Final Inspection7/15/20057/15/20057/15/2005PCANC
DetailsTroy Cobbley
Request for temp; ###-####
FIRE-Final Inspection7/14/20057/14/20057/14/2005PPASS
DetailsTroy Cobbley
Paint curbs per sheet C-2, final fire alarm permit, provide one hour fire rated room per plans.
BLD-Conference7/13/20057/14/20057/14/2005ADONE
DetailsMike Jordan
doug; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Code Occupancy Approval  7/14/2005 PASS
ALL IN AS REQUIRED FINAL SIGNED OFF.
FIRE-Final Inspection7/13/20057/13/20057/13/2005PFAIL
DetailsTroy Cobbley
Need to provide for fire dept access as discussed, shell drawings don't match what has been built, sprinkler riser room is supposed to be 1 hour rated and is not, provide address on Swordfish side of building, final fire alarm permit, need to test emergency lighting and exit signs and verify door hardware and extinguishers.
Code Occupancy Approval  7/11/2005 FAIL
NO HANDICAPPED SIGNS, MISSING SOME LANDSCAPE AND TREES ALONG EMERALD. ISSUED CORRECTION NOTICE
BLD-Framing/Rough-in6/17/20056/17/20056/17/2005PPASS
DetailsMike Jordan
ceiling grid///doug; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. 2nd floor ok
BLD-Conference5/3/20055/4/20055/4/2005APART
DetailsJim Sly
doug; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Talked to Doug... Owners want to open W/O interior doors installed (carpet to be installed 1st) This is on T/I permit...... Need OK from Fire inspector before approving. 5/4/2005 9:54:44 AM 5/4/2005 10:03:18 AM
BLD-Other7/30/20048/2/20048/2/2004APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 7/30/2004 at 7:52:05 AM. Contact: ###-####. mti on site 8/2/2004 8:58:50 AM
BLD-Footing6/2/20046/3/20046/3/2004APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 6/2/2004 at 5:17:19 PM. Contact: ###-####. 6/3/2004 1:59:14 PM Tilt walls.... MTI special inspection. 6/3/2004 2:02:27 PM
BLD-Footing5/20/20045/21/20045/21/2004PPART
DetailsJim Sly
Scheduled by a contractor via Hello! on 5/20/2004 at 2:52:04 PM. Contact: ###-####. Footings for South and West walls pending MTI special inspections, reports and approvals. 5/21/2004 3:45:51 PM
BLD-Footing4/29/20044/30/20044/30/2004APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 4/29/2004 at 3:08:23 PM. Contact: ###-####. Met with Stan (job super) and discussed special insp Req Etc.....MTI is the special insp agency.....Soils report OK......Pouring center footing pads and footings for stair towers......OK pending special inspection reports and approvals from MTI. 4/30/2004 11:11:11 AM