FIRE-Final Inspection | 4/12/2006 | 4/13/2006 | 4/13/2006 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
Permanent Occupancy | | 4/13/2006 | 4/13/2006 | | DONE |
|
|
|
|
BLD-Final | 1/20/2006 | 1/20/2006 | 1/20/2006 | P | PASS |
Mike Jordan
|
|
|
late pm please//bruce; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Ok for perm occ once elec., and fire alarm/life/safety have been finaled.
|
BLD-Final | 1/20/2006 | 1/20/2006 | 1/20/2006 | P | CANC |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 1/20/2006 | 1/20/2006 | 1/20/2006 | P | PART |
Forrest France
|
|
|
Per S. Rogers a temporary occupancy was granted. Final pending two issues associated with the related alarm permit.
|
BLD-Final | 1/19/2006 | 1/20/2006 | 1/20/2006 | A | CANC |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 1/19/2006 | 1/19/2006 | 1/19/2006 | P | FAIL |
Troy Cobbley
|
|
|
Per Sam Rogers a temporary occupancy can be given if the elevators get signed off by the state elevator inspectors. This temporary occupancy is good for the fire alarm permit as well.
|
BLD-Final | 1/19/2006 | 1/19/2006 | 1/19/2006 | P | NR |
Mike Jordan
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 1/3/2006 | 1/3/2006 | 1/3/2006 | P | PASS |
Mike Jordan
|
|
|
suspended ceiling grid//bruce; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. ceiling grid ok.
|
BLD-Framing/Rough-in | 12/29/2005 | 12/30/2005 | 12/30/2005 | P | FAIL |
Mike Jordan
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Ceiling grid in basement.
|
BLD-Framing/Rough-in | 12/28/2005 | 12/28/2005 | 12/28/2005 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/28/2005 at 7:57:37 AM. Contact: ###-####. Checked all remaining penetrations at one hour lid in basement. Also inspected ceiling grid, not yet complete. Did partial walk thru.
|
BLD-Aging Inspection | 11/1/2005 | 11/1/2005 | 11/1/2005 | | PASS |
Tom Arcoraci
|
|
|
wip
|
BLD-Framing/Rough-in | 9/1/2005 | 9/1/2005 | 9/1/2005 | P | PASS |
Tom Arcoraci
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa fire stop at hard lid in basement ok
|
BLD-Framing/Rough-in | 7/19/2005 | 7/20/2005 | 7/20/2005 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 7/19/2005 | 7/19/2005 | 7/19/2005 | P | CANC |
Tom Arcoraci
|
|
|
bruck; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa re sched for 7-20 in am out of time
|
BLD-Framing/Rough-in | 6/14/2005 | 6/14/2005 | 6/14/2005 | P | PART |
Tom Arcoraci
|
|
|
basement//bruce; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok lid
|
BLD-Energy code compliance | 5/31/2005 | 5/31/2005 | 5/31/2005 | P | PASS |
Jim Sly
|
|
|
bruce ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Insulation on 1st floor OK.
|
BLD-Framing/Rough-in | 5/24/2005 | 5/24/2005 | 5/24/2005 | P | PASS |
Tom Arcoraci
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles 1st floor
|
BLD-Framing/Rough-in | 5/20/2005 | 5/20/2005 | 5/20/2005 | P | PASS |
Tom Arcoraci
|
|
|
fire caulking//bruce; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Energy code compliance | 5/9/2005 | 5/10/2005 | 5/10/2005 | A | PART |
Tom Arcoraci
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa 2nd floor
|
BLD-Framing/Rough-in | 5/5/2005 | 5/5/2005 | 5/5/2005 | P | PART |
Tom Arcoraci
|
|
|
fire caulking inspection please///bruce; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok 408
|
BLD-Framing/Rough-in | 5/2/2005 | 5/2/2005 | 5/2/2005 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 5/2/2005 at 8:16:04 AM. Contact: ###-####. 2nd floor ok
|
BLD-Framing/Rough-in | 4/27/2005 | 4/27/2005 | 4/27/2005 | P | PART |
Tom Arcoraci
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa 2nd floor cor ok to rock ok to insulate floor on 2nd floor rooms
|
BLD-Energy code compliance | 4/18/2005 | 4/18/2005 | 4/18/2005 | P | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Barbara Moore 3rd floor OK 4/18/2005 2:56:21 PM
|
BLD-Framing/Rough-in | 4/11/2005 | 4/11/2005 | 4/11/2005 | P | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Barbara Moore 3rd Flr OK to Cover except (2) Electrical rooms. 4/11/2005 4:25:50 PM
|
BLD-Energy code compliance | 3/29/2005 | 3/29/2005 | 3/29/2005 | P | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Frame and Energy OK 4th Flr only. 3/29/2005 5:43:02 PM
|
BLD-Framing/Rough-in | 3/23/2005 | 3/24/2005 | 3/24/2005 | A | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Walked 4th floor to inspect firestopping....Need UL assembly for 4" PVC.... Need more firecaulking at annulus at 1 1/2 and 2" PVC at top plate penitrations. OK'd to start insulation Ext and Party walls... will call for re-insp Mon. 3/24/2005 1:48:29 PM
|
BLD-Framing/Rough-in | 3/23/2005 | 3/23/2005 | 3/23/2005 | P | NR |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Conference | 3/10/2005 | 3/11/2005 | 3/11/2005 | A | PART |
Jim Sly
|
|
|
Bruce; Phone #: ###-#### Jim & Tom both to insp. Internet Inspection Request from: Jan Rice Walk thru with Tom A. and Bruce. 3/11/2005 10:43:56 AM
|
BLD-Conference | 3/10/2005 | 3/11/2005 | 3/11/2005 | A | PASS |
Tom Arcoraci
|
|
|
Bruce; Phone #: ###-#### Jim & Tom both to insp. Internet Inspection Request from: Jan Rice
|
BLD-Framing/Rough-in | 3/10/2005 | 3/10/2005 | 3/10/2005 | P | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Talked to Bruce about all sub contractors to submit listed assemblies for penitrations thru rated walls/floors etc. 3/10/2005 4:56:11 PM
|
BLD-Framing/Rough-in | 3/9/2005 | 3/9/2005 | 3/9/2005 | P | FAIL |
Jim Sly
|
|
|
for fire shaft-- bruce; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Need to complete fire taping in shafts...... 3/9/2005 5:27:55 PM
|
BLD-Framing/Rough-in | 2/22/2005 | 2/22/2005 | 2/22/2005 | P | PART |
Lane Manuel
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
truss/ roof framing @ main bldg structure ok 2/22/2005 4:14:03 PM
|
BLD-Framing/Rough-in | 2/15/2005 | 2/15/2005 | 2/15/2005 | P | CANC |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 2/15/2005 at 9:04:35 AM.
need to recheck truss calc's/ web bracing. Bracing missed, contr. to reschedule. 2/15/2005 4:35:18 PM
|
BLD-Framing/Rough-in | 2/7/2005 | 2/7/2005 | 2/7/2005 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 2/7/2005 at 7:39:49 AM. Contact: ###-####.
north and south lower roofs- nailing ok, including shear nailing in these areas only. 2/7/2005 1:55:15 PM
|
BLD-Framing/Rough-in | 2/3/2005 | 2/4/2005 | 2/4/2005 | P | PART |
Lane Manuel
|
|
|
roof nailing bruce sleep ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
center/upper portion (only) of roof nailing ok 2/4/2005 3:14:58 PM
|
BLD-Other | 10/28/2004 | 10/29/2004 | 10/29/2004 | P | DONE |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 10/28/2004 at 10:38:58 AM. Contact: ###-####. verified 6 mil vapor barrier at slab on grade portion of hotel. 10/29/2004 2:04:38 PM
|
BLD-Other | 10/14/2004 | 10/15/2004 | 10/15/2004 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/14/2004 at 1:23:30 PM. Contact: ###-####. Remainder of vapor barrier under slab....OK. 10/15/2004 9:57:16 AM
|
BLD-Other | 10/13/2004 | 10/14/2004 | 10/14/2004 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/13/2004 at 3:32:43 PM. Contact: ###-####. Inspection of 6 mil vapor barrier under Basement slab...gridline 10 to 16 OK . Sewell and Assoc Engineers OK'd Pool in close proximity to Basement wall provided that pool rebar is tied into slab ( located between pool and Bsmnt wall). Rebar ties from pool to slab verified and OK'd...... Pool rebar OK'd. 10/14/2004 9:31:32 AM 10/14/2004 9:35:59 AM
|
BLD-Foundation | 8/6/2004 | 8/6/2004 | 8/6/2004 | P | NR |
Lane Manuel
|
|
|
JACK; Phone #: ###-#### Internet Inspection Request from: Annette Moore spec insp required mti 8/6/2004 4:16:59 PM
|
BLD-Footing | 8/4/2004 | 8/5/2004 | 8/5/2004 | P | NR |
Tom Arcoraci
|
|
|
would like inspection in afternoon, please call if needs to be earlier than that. ; Phone #: ###-#### Internet Inspection Request from: Robynn Sleep
|