BLD-Final | 11/23/2004 | 11/24/2004 | 11/24/2004 | P | PASS |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 11/23/2004 at 4:06:18 PM. Contact: ###-####.
perm. c of o ok 11/24/2004 2:29:53 PM
|
FIRE-Final Inspection | 11/23/2004 | 11/24/2004 | 11/24/2004 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled. Engineer, Steve Howard ###-####, to supply revised air balance report to me by email 11/24/2004 1:53:12 PM
|
Permanent Occupancy | | 11/23/2004 | 11/23/2004 | | DONE |
|
|
|
|
BLD-Final | 11/19/2004 | 11/22/2004 | 11/22/2004 | P | CANC |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 11/19/2004 at 7:07:01 AM. Contact: ###-####.
11/22/2004 12:52:33 PM need final insp's. by others prior to bldg. final 11/22/2004 12:54:30 PM
|
Code Occupancy Approval Temp | 11/22/2004 | 11/22/2004 | 11/22/2004 | A | DONE |
Scott M.Brown
|
|
|
TEMP SIGNED OFF, NEW LANDSCAPE NEEDS BARK GROUND COVER THE REST MAY REMAIN ROCK, TOLD THIS WOULD BE DONE IN JUST A FEW DAYS.. 11/22/2004 11:02:44 AM 11/22/2004 11:03:23 AM
|
FIRE-Final Inspection | 11/19/2004 | 11/22/2004 | 11/22/2004 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/19/2004 at 7:09:33 AM. Contact: ###-####. Repair exit signs; post occupant load sign; deep fat fryers need to be no more than 16 inches from nozzles; need air balance report; hang extinguishers 11/22/2004 3:52:36 PM
|
BLD-Other | 11/18/2004 | 11/19/2004 | 11/19/2004 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/18/2004 at 11:54:45 AM. need vapor berrior 11/19/2004 10:34:34 AM
|
BLD-Other | 11/19/2004 | 11/19/2004 | 11/19/2004 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 11/19/2004 at 7:06:13 AM. Contact: ###-####.
recheck additional support wires @ ceiling grid for ceiling accessory supports. 11/19/2004 2:51:48 PM
|
FIRE-Conference | 11/17/2004 | 11/18/2004 | 11/18/2004 | A | DONE |
Troy Cobbley
|
|
|
Spoke to Pete about the fire life safety review notes and requirements. 11/18/2004 10:35:17 AM
|
BLD-Other | 11/17/2004 | 11/17/2004 | 11/17/2004 | A | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 11/17/2004 at 7:24:32 AM. Contact: ###-####.
t-bar in back "galley" section ok 11/17/2004 12:02:40 PM
|
BLD-Framing/Rough-in | 11/1/2004 | 11/1/2004 | 11/1/2004 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/1/2004 at 7:20:44 AM. fire blocking above fire place ok to cover 11/1/2004 9:30:47 AM
|
BLD-Energy code compliance | 10/20/2004 | 10/22/2004 | 10/22/2004 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/20/2004 at 10:37:29 AM. Contact: ###-####. Frame and Energy OK. 10/22/2004 11:59:18 AM
|
BLD-Framing/Rough-in | 10/20/2004 | 10/21/2004 | 10/21/2004 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/20/2004 at 10:30:32 AM.
|
BLD-Framing/Rough-in | 10/20/2004 | 10/20/2004 | 10/20/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/20/2004 at 10:36:43 AM. Contact: ###-####. Framing OK at Ext. walls of Kitch and lobby Pend Electr approval. Told Contr to Fireblock F/P chase 10' OC 10/20/2004 3:19:26 PM
|
BLD-Framing/Rough-in | 10/14/2004 | 10/15/2004 | 10/15/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/14/2004 at 2:46:13 PM. Contact: ###-####. Shear nailing at E. 1/2 of N. and S. walls.......and E. wall (except for F/P pop out) OK. 10/15/2004 3:21:43 PM
|
BLD-Framing/Rough-in | 10/13/2004 | 10/14/2004 | 10/14/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/13/2004 at 5:08:04 PM. Contact: ###-####. roof ok a35 in place through out roof. 10/14/2004 2:26:34 PM
|
BLD-Framing/Rough-in | 10/8/2004 | 10/11/2004 | 10/11/2004 | A | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 10/8/2004 at 12:46:55 PM. Contact: ###-####.
rough frame @ roof for new cricket, west end OK. 10/11/2004 8:50:57 AM
|
BLD-Footing | 10/5/2004 | 10/6/2004 | 10/6/2004 | P | CANC |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 10/5/2004 at 11:02:53 AM. Contact: ###-####.
|
BLD-Footing | 10/5/2004 | 10/5/2004 | 10/5/2004 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 10/5/2004 at 9:48:20 AM. Contact: ###-####.
to be inspected by special inspector. (Strata) 10/5/2004 1:24:36 PM
|