BLD-Final | 2/16/2006 | 2/16/2006 | 2/16/2006 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/16/2006 at 7:50:37 AM. Contact: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 2/15/2006 | 2/15/2006 | 2/15/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
FIRE-Alarm Testing | 2/6/2006 | 2/6/2006 | 2/6/2006 | P | PASS |
Troy Cobbley
|
|
|
fire alarm permit passed
|
FIRE-Final Inspection | 2/6/2006 | 2/6/2006 | 2/6/2006 | P | FAIL |
Troy Cobbley
|
|
|
provide occupancy load signs
|
BLD-Other | 2/1/2006 | 2/1/2006 | 2/1/2006 | A | DONE |
Mike Jordan
|
|
|
Informed bldg occupant has 24hrs to remove temp. structure at south exit of main bldg.
|
Permanent Occupancy | | 2/1/2006 | 2/1/2006 | | DONE |
|
|
|
|
BLD-Other | 1/11/2006 | 1/11/2006 | 1/11/2006 | A | DONE |
Mike Jordan
|
|
|
Plastic has been removed from outside of sanctuary addition. 180 day temp use granted for tent. Noted that plans are being redrawn for tent removal and addition of walls. Contractor to reschedule fire inspections, contractor says repairs have been made.
|
BLD-Other | 11/4/2005 | 11/4/2005 | 11/4/2005 | P | FAIL |
Tom Arcoraci
|
|
|
cn issued no occupancy until final
|
FIRE-Final Inspection | 11/2/2005 | 11/3/2005 | 11/3/2005 | A | FAIL |
Troy Cobbley
|
|
|
No inspection done due to the fire alarm being failed and building issues noted. The building issues noted include tenting/canopy materials enclosing the south canopy. This area is shown on the building plans as being enclosed with walls. A permit is needed for the canopy and the two heaters, bbq and the space LP tanks removed. Plans need to be resubmitted to show this work removed or the work needs to be completed. A ceiling needs to be installed in the fire sprinkler riser room to cover the exposed cpvc sprinkler piping. The accelerator on the dry pipe valve has a sign stating the it does not work and the trim valves to it are closed. This device needs to be repaired.
|
BLD-Final | 11/2/2005 | 11/3/2005 | 11/3/2005 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/2/2005 at 3:14:43 PM. Contact: ###-####.
|
BLD-Aging Inspection | 10/13/2005 | 10/13/2005 | 10/13/2005 | | NR |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 8/5/2005 | 8/8/2005 | 8/8/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/5/2005 at 2:28:39 PM. Contact: ###-####.
|
BLD-Footing | 6/14/2005 | 6/17/2005 | 6/17/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 6/14/2005 at 3:25:21 PM. Contact: ###-####. spec insp on site
|