Code Occupancy Approval | 5/17/2007 | 5/17/2007 | 5/17/2007 | P | PASS |
Michael Garner
|
|
|
SITE INSPECTION COMPLETE - i REVIEWED THE APPROVED PLANS AND CONDITIONS AND HAVE FOUND THEM TO BE IN SUBSTANTIAL COMPLIANCE: I DID NOTE THE FOLLOWING CHANGES -
1. PLANS CALLED FOR A SOLID PLANTER ON THE MINI-COURTYARD BETWEEN THE CENTER BLDGS - THAT WAS CHANGED TO INDIVIDUAL VASE PLANTERS PER CONSULTATION WITH THE FIRE DEPARTMENT WHO HAD CONCERNS ABOUT ACCESS TO HOSE CONNECTIONS AND INTO THE BLDGS. THEMSELVES
2. PLANS FOR THE CENTER BLDGS CALLED FOR THREE [3] VERTICALLY STACKED WINDOWS MIRRORING THE INTERIOR STAIRWELLS - THAT HAS BEEN CHANGED TO TWO WINDOWS, WITH THE MIDDLE WINDOW REMOVED TO ACCOMODATE A REQUIRED A NECESSARY STRUCTURAL BEAM
3. ORIGINAL PLANS CALLED FOR ROUGH-HEWN [CEDAR?] SHINGLES - BLDR. INSTEAD USED HARDI-PLANK SHINGLES BECAUSE THEY ARE LONGER LASTING, EASIER TO MAINTAIN
4. THE MOST INTERIOR [CLOSEST TO CREEK] BLDGS DO NOT HAVE A STUCCO SKIRT AS THE PLANS CALLED FOR...INSTEAD THEY HAVE A STONE SKIRT WHICH IS IN KEEPING WITH THE STONE SKIRTS ON ALL THE OTHER BLDGS.
THESE CHANGES ARE ACCEPTABLE AND WITHIN THE PARAMETERS OF THE SCOPE AND INTENT OF THE APPROVED PLANS AND CONDITIONS - PASS/CASE CLOSED
|
Permanent Occupancy | | 5/17/2007 | 5/17/2007 | | DONE |
|
|
|
|
BLD-Aging Inspection | 4/20/2007 | 4/20/2007 | 4/27/2007 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 1/10/2007 | 1/10/2007 | 1/11/2007 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 10/31/2006 | 10/31/2006 | 11/3/2006 | | PEND |
Tony Young
|
|
|
|
BLD-Final | 8/30/2006 | 8/31/2006 | 8/31/2006 | A | PASS |
Tony Young
|
|
|
Keil; Phone #: ###-#### ok for c of o pending others
|
BLD-Final | 8/30/2006 | 8/30/2006 | 8/31/2006 | P | CANC |
Tony Young
|
|
|
keil; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
FIRE-Final Inspection | 8/28/2006 | 8/29/2006 | 8/29/2006 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed.
|
BLD-Final | 8/24/2006 | 8/25/2006 | 8/25/2006 | P | CANC |
Tony Young
|
|
|
cancelled - not ready per keil; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Aging Inspection | 7/24/2006 | 7/24/2006 | 7/26/2006 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/4/2006 | 4/4/2006 | 4/4/2006 | | PASS |
Tony Young
|
|
|
work is going to start soon per keil, project super
|
FIRE-Sprinkler Rough-in | 1/30/2006 | 1/30/2006 | 1/30/2006 | P | PART |
Forrest France
|
|
|
Inspection for cold cavity protection of the fire sprinkler lines on the remaining third floor unit of this building is acceptable for cover.
|
BLD-Energy code compliance | 1/17/2006 | 1/17/2006 | 1/17/2006 | P | PART |
Tony Young
|
|
|
keil; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok to cover pending fire sprinkler sign off
|
FIRE-Sprinkler Rough-in | 1/6/2006 | 1/9/2006 | 1/9/2006 | A | PART |
Forrest France
|
|
|
Inspection for tenting at fire sprinklers good for cover at 3rd floor apt. A east only, the remaining 3 units on the floor not complete at this time.
|
BLD-Energy code compliance | 1/4/2006 | 1/5/2006 | 1/5/2006 | A | PART |
Tony Young
|
|
|
partial for garage//keil ###-#### garages ok to cover
|
BLD-Framing/Rough-in | 12/12/2005 | 12/13/2005 | 12/13/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/12/2005 at 12:11:51 PM. Contact: ###-####. ok to cover ext
|
BLD-Framing/Rough-in | 12/5/2005 | 12/5/2005 | 12/5/2005 | P | NR |
Tony Young
|
|
|
air infiltration inspec and framing//keil; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa conf. walk through only,, need to do some pickup items and recall
|
BLD-Framing/Rough-in | 8/17/2005 | 8/17/2005 | 8/17/2005 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/17/2005 at 7:57:10 AM. Contact: ###-####. upper f/walls
|
BLD-Framing/Rough-in | 8/8/2005 | 8/9/2005 | 8/9/2005 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/8/2005 at 4:28:59 PM. Contact: ###-####. upper fire walls.
|
BLD-Conference | 7/19/2005 | 7/19/2005 | 7/19/2005 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/19/2005 at 7:37:45 AM. Contact: ###-####.,,,,,,,,,,,,,,,lower firewalls ok
|
BLD-Framing/Rough-in | 7/15/2005 | 7/18/2005 | 7/18/2005 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/15/2005 at 3:19:31 PM. Contact: ###-####.
|
BLD-Foundation | 4/15/2005 | 4/18/2005 | 4/18/2005 | A | PART |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 4/15/2005 at 11:19:04 AM. Contact: ###-####.
|
BLD-Footing | 4/7/2005 | 4/8/2005 | 4/8/2005 | A | PASS |
Troy James
|
|
|