FIRE-Final Inspection | 3/24/2005 | 3/24/2005 | 3/24/2005 | P | PASS |
Troy Cobbley
|
|
|
fire life safety finaled
|
BLD-Final | 3/14/2005 | 3/14/2005 | 3/14/2005 | P | PASS |
Jim Sly
|
|
|
12601 w explorer drive suite 200 for signature card///dave kodanko; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Certificate of Compliance issued. 3/14/2005 3:03:39 PM
|
DOC - Permit Finaled | | | 3/14/2005 | | DONE |
|
|
|
|
BLD-Final | 2/11/2005 | 2/11/2005 | 2/11/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/11/2005 at 8:32:26 AM. Verified Letter of approval from special insp agency and Pinnacle Engineering. Need sign off from Public Works and Code Enf. OK to final when these signed off. 2/11/2005 3:31:11 PM
|
BLD-Final | 1/28/2005 | 1/28/2005 | 1/28/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/28/2005 at 8:13:13 AM. Need fire permit finaled. 1/28/2005 2:00:51 PM
|
BLD-Concrete | 9/29/2004 | 9/29/2004 | 9/29/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/29/2004 at 9:07:24 AM. Contact: ###-####.
|
BLD-Concrete | 8/25/2004 | 8/26/2004 | 8/26/2004 | A | PART |
Jim Sly
|
|
|
dave; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Approx 12 tilt up panels poured......MTI on site....OK pending special insp reports and approvals. 8/26/2004 11:24:35 AM
|
BLD-Concrete | 7/29/2004 | 7/29/2004 | 7/29/2004 | P | PART |
Jim Sly
|
|
|
###-#### David On 7/28 Center footings for columns were poured.....Today slab poured.....MTI is doing special inspections. 7/29/2004 3:21:34 PM
|
BLD-Footing | 7/27/2004 | 7/28/2004 | 7/28/2004 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 7/27/2004 at 4:57:44 PM.
|