Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD04-00958
StatusFinaled
Name BRIGHTON CORPORATION
Site Address 12754 W LASALLE ST
Project NameLASALLE BLDG
Customer Number 
ePlanReviewNo
Description
LaSalle Boise Research Center (Shell Office Building) - To construct a new 16,940 square foot, one story, concrete tilt-up offiice shell building and related site improvement. This is a shell building permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. This building is fully fire sprinklered. The sprinklers are used for area increase. All construction per the approved plans and attached comment list. DRH04-52/#04-280/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection3/24/20053/24/20053/24/2005PPASS
DetailsTroy Cobbley
fire life safety finaled
BLD-Final3/14/20053/14/20053/14/2005PPASS
DetailsJim Sly
12601 w explorer drive suite 200 for signature card///dave kodanko; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Certificate of Compliance issued. 3/14/2005 3:03:39 PM
DOC - Permit Finaled  3/14/2005 DONE
BLD-Final2/11/20052/11/20052/11/2005PNR
DetailsJim Sly
Scheduled by a contractor via Hello! on 2/11/2005 at 8:32:26 AM. Verified Letter of approval from special insp agency and Pinnacle Engineering. Need sign off from Public Works and Code Enf. OK to final when these signed off. 2/11/2005 3:31:11 PM
BLD-Final1/28/20051/28/20051/28/2005PNR
DetailsJim Sly
Scheduled by a contractor via Hello! on 1/28/2005 at 8:13:13 AM. Need fire permit finaled. 1/28/2005 2:00:51 PM
BLD-Concrete9/29/20049/29/20049/29/2004PPART
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/29/2004 at 9:07:24 AM. Contact: ###-####.
BLD-Concrete8/25/20048/26/20048/26/2004APART
DetailsJim Sly
dave; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Approx 12 tilt up panels poured......MTI on site....OK pending special insp reports and approvals. 8/26/2004 11:24:35 AM
BLD-Concrete7/29/20047/29/20047/29/2004PPART
DetailsJim Sly
###-#### David On 7/28 Center footings for columns were poured.....Today slab poured.....MTI is doing special inspections. 7/29/2004 3:21:34 PM
BLD-Footing7/27/20047/28/20047/28/2004APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 7/27/2004 at 4:57:44 PM.