BLD-Final | 5/31/2005 | 6/1/2005 | 6/1/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/31/2005 at 4:29:05 PM. OK for Perm Occ. :)
|
Permanent Occupancy | | 6/1/2005 | 6/1/2005 | | DONE |
|
|
|
|
BLD-Final | 5/25/2005 | 5/26/2005 | 5/27/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/25/2005 at 3:51:30 PM. OK for Temp Occ. Landscape Bonded. C/N Obtain all req signatures for Perm Occ within 90 days of this notice.
|
FIRE-Final Inspection | 5/17/2005 | 5/23/2005 | 5/23/2005 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
FIRE-Final Inspection | 5/16/2005 | 5/17/2005 | 5/17/2005 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Sam Rogers permission. Items needing correcting are adding exit discharge lighting outside of the main exit, adding emergency lighting in the main lobby and in the south conference room, and adding a exit sign at the b
|
BLD-Final | 5/17/2005 | 5/17/2005 | 5/17/2005 | P | PART |
Jim Sly
|
|
|
OK for Temp Occ. C/N.... Obtain Perm Occ status within 90 days of this notice
|
Code Occupancy Approval Temp | 5/18/2005 | 5/17/2005 | 5/17/2005 | A | FAIL |
Carol Montgomery
|
|
|
Bond was posted - Temporary Signed. 5/18/2005 9:00:45 AM
|
BLD-Final | 5/13/2005 | 5/16/2005 | 5/16/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/13/2005 at 10:34:10 AM. Contact: ###-####.
|
BLD-Conference | 5/12/2005 | 5/13/2005 | 5/13/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/12/2005 at 4:34:58 PM.
|
BLD-Final | 5/12/2005 | 5/13/2005 | 5/13/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/12/2005 at 4:34:29 PM.
|
BLD-Wall cover | 5/11/2005 | 5/11/2005 | 5/11/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/11/2005 at 8:12:09 AM.
|
BLD-Wall cover | 5/4/2005 | 5/5/2005 | 5/5/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/4/2005 at 1:25:06 PM.
|
BLD-Energy code compliance | 4/19/2005 | 4/19/2005 | 4/19/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/19/2005 at 6:36:30 AM. Pool bldg OK. 4/19/2005 9:41:23 AM
|
BLD-Wall cover | 4/14/2005 | 4/15/2005 | 4/15/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/14/2005 at 4:07:58 PM. Framing at pool cover OK but need to check (2) 4-6' shear panels Ea. side of openig @ East wall (6" oc nailing) 4/15/2005 9:57:48 AM 4/15/2005 9:58:20 AM
|
BLD-Conference | 4/7/2005 | 4/8/2005 | 4/8/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/7/2005 at 4:28:36 PM.
|
BLD-Wall cover | 4/7/2005 | 4/7/2005 | 4/7/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 4/7/2005 at 7:53:28 AM. 2nd 3rd and 4th Flr corridors OK. 4/7/2005 3:27:25 PM
|
BLD-Wall cover | 3/28/2005 | 3/29/2005 | 3/29/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/28/2005 at 5:12:20 PM. Firestop at 1st Flr corridors OK. 3/29/2005 10:54:11 AM
|
BLD-Wall cover | 3/22/2005 | 3/23/2005 | 3/23/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/22/2005 at 2:17:33 PM. Checked firestopping at central lobby common area.....still need to complete. 3/23/2005 10:37:32 AM
|
BLD-Wall cover | 3/22/2005 | 3/23/2005 | 3/23/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/22/2005 at 2:18:39 PM. Main lobby area and Porte Cochere. 3/23/2005 5:21:10 PM
|
BLD-Conference | 3/16/2005 | 3/17/2005 | 3/17/2005 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/16/2005 at 3:41:57 PM. Met with Don to talk about Final inspections. 3/17/2005 12:08:57 PM
|
BLD-Wall cover | 3/9/2005 | 3/11/2005 | 3/11/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/9/2005 at 8:16:42 AM. Checking firestopping at tub valves, spouts, and shower heads 3/11/2005 3:09:55 PM
|
BLD-Energy code compliance | 3/8/2005 | 3/8/2005 | 3/8/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/8/2005 at 9:46:53 AM.
|
BLD-Wall cover | 3/8/2005 | 3/8/2005 | 3/8/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/8/2005 at 9:47:15 AM.
|
BLD-Wall cover | 3/7/2005 | 3/7/2005 | 3/7/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/7/2005 at 7:10:53 AM. Ongoing Misc Insp of Firestopping. 3/7/2005 12:41:59 PM
|
BLD-Wall cover | 3/3/2005 | 3/3/2005 | 3/3/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/3/2005 at 6:14:18 AM. misc walls. 3/3/2005 10:58:33 AM
|
BLD-Wall cover | 3/2/2005 | 3/2/2005 | 3/2/2005 | P | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/2/2005 at 7:00:32 AM.
|
BLD-Footing | 2/25/2005 | 2/25/2005 | 2/25/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/25/2005 at 6:38:51 AM. Pool.....MTI on site. 2/25/2005 12:30:05 PM
|
BLD-Wall cover | 2/25/2005 | 2/25/2005 | 2/25/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/25/2005 at 6:38:24 AM.
|
BLD-Footing | 2/23/2005 | 2/24/2005 | 2/24/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/23/2005 at 9:59:00 AM. Footing Pool area MTI special inspections. 2/24/2005 4:34:02 PM
|
BLD-Footing | 2/23/2005 | 2/24/2005 | 2/24/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/23/2005 at 9:59:38 AM.
|
BLD-Wall cover | 2/23/2005 | 2/24/2005 | 2/24/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/23/2005 at 3:24:02 PM. Exterior walls N of Elevator OK to cover. 2/24/2005 11:34:09 AM
|
BLD-Energy code compliance | 2/23/2005 | 2/23/2005 | 2/23/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/23/2005 at 8:27:45 AM.
|
BLD-Wall cover | 2/17/2005 | 2/22/2005 | 2/22/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/17/2005 at 7:57:21 AM. All drops OK 2nd floor N. end. 2/22/2005 3:35:01 PM
|
BLD-Wall cover | 2/21/2005 | 2/22/2005 | 2/22/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/21/2005 at 8:37:00 AM.
|
BLD-Wall cover | 2/17/2005 | 2/18/2005 | 2/18/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/17/2005 at 3:41:16 PM.
|
BLD-Conference | 2/15/2005 | 2/16/2005 | 2/16/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/15/2005 at 3:13:03 PM. Contact: ###-####. OK to cover...4th floor rooms, 3rd floor rooms and 1st floor rooms (S. 1/2 only) 2/16/2005 9:25:54 AM 2/16/2005 9:27:01 AM
|
BLD-Energy code compliance | 2/15/2005 | 2/16/2005 | 2/16/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/15/2005 at 3:13:54 PM. Contact: ###-####.
|
BLD-Energy code compliance | 2/14/2005 | 2/14/2005 | 2/14/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/14/2005 at 6:16:05 AM.
|
BLD-Wall cover | 2/14/2005 | 2/14/2005 | 2/14/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/14/2005 at 6:15:46 AM.
|
BLD-Wall cover | 2/11/2005 | 2/11/2005 | 2/11/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/11/2005 at 6:39:42 AM.
|
BLD-Wall cover | 2/11/2005 | 2/11/2005 | 2/11/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/11/2005 at 6:40:11 AM. OK to cover drops in rooms....S. 1/2 of bldg. 1st and 2nd floors. 2/11/2005 2:36:04 PM
|
BLD-Wall cover | 2/10/2005 | 2/10/2005 | 2/10/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/10/2005 at 9:19:03 AM. Fix all holes in gyp above all fir downs 1st floor and recall for insp. 2/10/2005 4:27:10 PM
|
BLD-Energy code compliance | 2/7/2005 | 2/7/2005 | 2/7/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/7/2005 at 6:22:22 AM.
|
BLD-Wall cover | 2/7/2005 | 2/7/2005 | 2/7/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/7/2005 at 6:22:00 AM.
|
BLD-Energy code compliance | 2/4/2005 | 2/4/2005 | 2/4/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/4/2005 at 7:20:17 AM.
|
BLD-Wall cover | 2/4/2005 | 2/4/2005 | 2/4/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/4/2005 at 7:19:53 AM. 4th floor firestopping at walls in bathrooms ( S. end) OK 2/4/2005 12:16:00 PM
|
BLD-Energy code compliance | 2/1/2005 | 2/1/2005 | 2/1/2005 | A | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/1/2005 at 6:37:16 AM.
|
BLD-Energy code compliance | 1/28/2005 | 2/1/2005 | 2/1/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/28/2005 at 7:48:47 AM. 2nd floor .....all rooms 2/1/2005 2:08:59 PM
|
BLD-Wall cover | 2/1/2005 | 2/1/2005 | 2/1/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/1/2005 at 6:37:44 AM. 2nd flr all rooms 2/1/2005 2:10:04 PM
|
BLD-Energy code compliance | 1/31/2005 | 1/31/2005 | 1/31/2005 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/31/2005 at 7:03:50 AM.
|
BLD-Wall cover | 1/31/2005 | 1/31/2005 | 1/31/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/31/2005 at 7:03:26 AM.
|
BLD-Wall cover | 1/28/2005 | 1/28/2005 | 1/28/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/28/2005 at 7:49:39 AM. 3rd floor bathrooms OK (S. end) 1st flr S. rooms OK. 1/28/2005 4:22:04 PM
|
BLD-Energy code compliance | 1/27/2005 | 1/27/2005 | 1/27/2005 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/27/2005 at 7:14:48 AM. 1st floor.... S. rooms OK firecaulking and energy code. 1/27/2005 12:04:42 PM
|
BLD-Energy code compliance | 1/27/2005 | 1/27/2005 | 1/27/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/27/2005 at 7:15:12 AM. 2nd floor Bathrooms OK to cover (S. Rooms) 3rd Floor Fir Down Soffits OK to cover (S. Rooms). 1/27/2005 5:07:10 PM
|
BLD-Energy code compliance | 1/25/2005 | 1/26/2005 | 1/26/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/25/2005 at 3:31:25 PM.
|
BLD-Wall cover | 1/25/2005 | 1/26/2005 | 1/26/2005 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/25/2005 at 3:31:01 PM. Complete Firestopping at 2nd to 3rd floor flr/ceiling assembly Rooms S. 1/2 of 2nd flr. 1/26/2005 3:48:38 PM
|
BLD-Energy code compliance | 1/25/2005 | 1/25/2005 | 1/25/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/25/2005 at 9:46:14 AM.
|
BLD-Energy code compliance | 1/24/2005 | 1/24/2005 | 1/24/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/24/2005 at 7:51:12 AM.
|
BLD-Wall cover | 1/24/2005 | 1/24/2005 | 1/24/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/24/2005 at 7:51:40 AM. All Fire stopping OK in all rooms ..... S. 1/2 of Bldg 1st Flr. 1/24/2005 3:10:38 PM
|
BLD-Conference | 1/21/2005 | 1/21/2005 | 1/21/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/21/2005 at 10:23:03 AM. Contact: ###-####.
|
BLD-Energy code compliance | 1/19/2005 | 1/21/2005 | 1/21/2005 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/19/2005 at 9:04:50 AM.
|
BLD-Framing/Rough-in | 1/20/2005 | 1/20/2005 | 1/20/2005 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/20/2005 at 8:56:55 AM.
|
BLD-Framing/Rough-in | 1/18/2005 | 1/18/2005 | 1/18/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/18/2005 at 6:55:43 AM.
|
BLD-Wall cover | 1/17/2005 | 1/18/2005 | 1/18/2005 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/17/2005 at 7:36:09 AM. Complete Firestopping of penitrations thru top plates and gyp ceiling membranes at dropped soffit areas.....1st flr Ext walls and 2nd flr rooms (S 1/2) 1/18/2005 10:27:08 AM
|
BLD-Framing/Rough-in | 1/14/2005 | 1/14/2005 | 1/14/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/14/2005 at 6:24:14 AM. Elevator shaft OK to rock..... Corridor 2nd floor N. end OK to cover.
1/14/2005 10:54:05 AM 1/14/2005 10:55:07 AM
|
BLD-Energy code compliance | 1/12/2005 | 1/13/2005 | 1/13/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/12/2005 at 5:21:50 PM. S. 1/2 of 2nd and 3rd floor OK. 1/13/2005 11:44:47 AM
|
BLD-Wall cover | 1/12/2005 | 1/13/2005 | 1/13/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/12/2005 at 5:22:26 PM.
|
BLD-Framing/Rough-in | 1/11/2005 | 1/12/2005 | 1/12/2005 | A | PASS |
Jim Sly
|
|
|
ok to cover --tim- ###-#### cell ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie OK to cover S 1/2 of 2nd floor. 1/12/2005 3:49:09 PM
|
BLD-Framing/Rough-in | 1/11/2005 | 1/12/2005 | 1/12/2005 | A | CANC |
Jim Sly
|
|
|
ok to cover --tim- ###-#### cell ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Wall cover | 1/10/2005 | 1/11/2005 | 1/11/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/10/2005 at 3:51:36 PM.
|
BLD-Wall cover | 1/11/2005 | 1/11/2005 | 1/11/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/11/2005 at 9:26:12 AM. OK to cover corridors.... 2nd 3rd floors. 1/11/2005 4:04:06 PM
|
BLD-Wall cover | 1/10/2005 | 1/10/2005 | 1/10/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/10/2005 at 6:54:14 AM. OK to rock selected walls in Electr rm and boiler rm 1st flr. 1/10/2005 2:26:06 PM
|
BLD-Energy code compliance | 1/7/2005 | 1/7/2005 | 1/7/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/7/2005 at 6:22:09 AM. S. 1/2 of 2nd floor. 1/7/2005 12:20:09 PM
|
BLD-Energy code compliance | 1/5/2005 | 1/6/2005 | 1/6/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/5/2005 at 2:38:14 PM. Few units done..... 1/6/2005 12:35:28 PM
|
BLD-Wall cover | 1/5/2005 | 1/5/2005 | 1/5/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/5/2005 at 6:21:40 AM. Still insulating. 1/5/2005 2:57:45 PM
|
BLD-Wall cover | 1/5/2005 | 1/5/2005 | 1/5/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/5/2005 at 6:22:17 AM. S 1/2 of 2nd flr 1/5/2005 4:43:25 PM
|
BLD-Wall cover | 12/31/2004 | 1/3/2005 | 1/3/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/31/2004 at 1:33:22 PM. Framing OK S. 1/2 of 2nd floor. 1/3/2005 4:49:46 PM
|
BLD-Wall cover | 12/28/2004 | 12/29/2004 | 12/29/2004 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/28/2004 at 2:30:14 PM.
|
BLD-Conference | 12/28/2004 | 12/28/2004 | 12/28/2004 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/28/2004 at 7:48:34 AM.
|
BLD-Conference | 12/23/2004 | 12/23/2004 | 12/23/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/23/2004 at 7:38:44 AM. Contact: ###-####. Architect to approve Electricians Method of firestopping and fireblocking penitrations thru plates. 12/23/2004 4:39:17 PM
|
BLD-Conference | 12/21/2004 | 12/22/2004 | 12/22/2004 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/21/2004 at 4:37:45 PM. Need to review Legacy report on foam seal used in leiu of firecaulk for (metal) Electr penitrating items....for fireblock in walls. . 12/22/2004 11:45:41 AM 12/22/2004 11:48:18 AM
|
BLD-Framing/Rough-in | 12/21/2004 | 12/22/2004 | 12/22/2004 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/21/2004 at 4:38:19 PM.
|
FIRE-Conference | 12/21/2004 | 12/21/2004 | 12/21/2004 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/21/2004 at 10:34:24 AM. Contact: ###-####. Dave Miller approved the relocation of the roof access to above stair door - there is no equipment on the roof that will need access; will require structural review also 12/21/2004 4:03:22 PM
|
BLD-Framing/Rough-in | 12/20/2004 | 12/20/2004 | 12/20/2004 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/20/2004 at 10:37:09 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 12/16/2004 | 12/17/2004 | 12/17/2004 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/16/2004 at 3:11:33 PM. 2nd floor.......Need to install all holdowns, complete double top plates at plumbing walls, complete firecaulking. 12/17/2004 11:01:47 AM
|
BLD-Wall cover | 12/14/2004 | 12/14/2004 | 12/14/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/14/2004 at 8:59:46 AM. Contact: ###-####. OK to prerock lid on Corridors pending fire sprinkler insp. and appr. 12/14/2004 4:31:01 PM
|
BLD-Other | 12/6/2004 | 12/7/2004 | 12/7/2004 | A | PART |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 12/6/2004 at 8:03:37 AM. Contact: ###-####.
|
BLD-Other | 12/6/2004 | 12/7/2004 | 12/7/2004 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/6/2004 at 8:03:37 AM. Contact: ###-####. Partial Roof nailing S 1/2 OK 12/7/2004 3:25:27 PM 12/7/2004 3:26:07 PM
|
BLD-Conference | 12/1/2004 | 12/2/2004 | 12/2/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/1/2004 at 1:29:21 PM. Contact: ###-####.
|
BLD-Conference | 11/30/2004 | 12/1/2004 | 12/1/2004 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/30/2004 at 2:18:18 PM. Contact: ###-####.
|
BLD-Conference | 11/18/2004 | 11/19/2004 | 11/19/2004 | A | PART |
Jim Sly
|
|
|
Pre-rock and block at Tubs per appr plan, or Architect to supply new Detail. 11/19/2004 2:10:56 PM
|
BLD-Conference | 11/17/2004 | 11/18/2004 | 11/18/2004 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/17/2004 at 4:13:47 PM. Contact: ###-####.
|
BLD-Conference | 11/16/2004 | 11/16/2004 | 11/16/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/16/2004 at 6:59:00 AM. Contact: ###-####. Met with Plumber ans Don to discuss Shower valve in 1hr wall. 11/16/2004 5:13:28 PM
|
BLD-Conference | 11/3/2004 | 11/4/2004 | 11/4/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/3/2004 at 2:13:11 PM. Contact: ###-####. Moving swimming pool....Contact planning and Zoning. 11/4/2004 3:50:24 PM
|
BLD-Conference | 11/2/2004 | 11/2/2004 | 11/2/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/2/2004 at 8:35:03 AM. Contact: ###-####. Talked about extending rated wall at stairtower (2hr) across double wall ...
Double wall consists of Ext wall and wall Next to it by stairway. 11/2/2004 3:56:48 PM 11/2/2004 3:59:04 PM
|
BLD-Conference | 10/27/2004 | 10/28/2004 | 10/28/2004 | A | NR |
Jim Sly
|
|
|
|
BLD-Conference | 10/28/2004 | 10/28/2004 | 10/28/2004 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/28/2004 at 6:42:27 AM. Contact: ###-####. C/N Architect to resubmit for approval..... Details for protection of penitrating items through rated walls and floor/ceiling assembly, and Misc framing corrections. Corr notice on site. 10/28/2004 4:49:16 PM
|
BLD-Conference | 10/27/2004 | 10/27/2004 | 10/27/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/27/2004 at 6:51:18 AM. Contact: ###-####. Met with Tim (foreman) and went over Framing issues. 10/27/2004 6:09:30 PM
|
BLD-Conference | 10/26/2004 | 10/26/2004 | 10/26/2004 | P | PART |
Jim Sly
|
|
|
Don; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner Met with Tom, Dave and Jim Storey......Checked plans and jobsite. 10/26/2004 5:01:24 PM
|
BLD-Conference | 10/26/2004 | 10/26/2004 | 10/26/2004 | P | PASS |
Tom Arcoraci
|
|
|
Don; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner
|
BLD-Conference | 10/21/2004 | 10/21/2004 | 10/21/2004 | P | DONE |
Troy Cobbley
|
|
|
Per IFC 1009 exception #1 the windows can have stops in them 10/21/2004 4:18:12 PM
|
BLD-Framing/Rough-in | 9/29/2004 | 9/30/2004 | 9/30/2004 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/29/2004 at 3:11:07 PM. Contact: ###-####. 1st flr shear walls and holdowns.... Most done and OK @ South 1/2 of bldg. 9/30/2004 11:08:53 AM
|
BLD-Conference | 9/28/2004 | 9/29/2004 | 9/29/2004 | P | CANC |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/28/2004 at 1:48:38 PM. Contact: ###-####.
|
BLD-Foundation | 9/22/2004 | 9/23/2004 | 9/23/2004 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/22/2004 at 1:49:12 PM. Contact: ###-####. rebar and insulation for slab on grade north end mti will also be on site to check final and test concrete 9/23/2004 4:33:45 PM
|
BLD-Conference | 9/22/2004 | 9/22/2004 | 9/22/2004 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/22/2004 at 10:15:27 AM. Contact: ###-####. Met with Framing super...... Bob... Need continuous rock at 2hr wall ... uninterupted by studs at perpendicular walls. 9/22/2004 3:15:57 PM
|
BLD-Concrete | 9/9/2004 | 9/10/2004 | 9/10/2004 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 9/9/2004 at 1:42:18 PM. Contact: ###-####.
partial found/slab ok.
see MTI notes for notation details, location of approval for this date 9/10/2004 12:46:36 PM
|
BLD-Other | 9/9/2004 | 9/10/2004 | 9/10/2004 | P | DONE |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 9/9/2004 at 1:41:26 PM. Contact: ###-####.
|
BLD-Energy code compliance | 9/8/2004 | 9/8/2004 | 9/8/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/8/2004 at 7:27:11 AM. Foundation insul. 9/8/2004 3:53:32 PM
|
BLD-Foundation | 9/2/2004 | 9/3/2004 | 9/3/2004 | A | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 9/2/2004 at 12:55:33 PM.
rigid insul. @ stemwalls ok. need to reinspect 2 ft insulation return @ slab once backfilled and prep'd. 9/3/2004 9:13:02 AM
|
BLD-Conference | 9/1/2004 | 9/2/2004 | 9/2/2004 | A | PART |
Jim Sly
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Don has been calling in for inspections for concrete, ...but entering wrong permit #....... Went through more details on plans with Ferguson. 9/2/2004 12:46:16 PM
|
BLD-Conference | 8/16/2004 | 8/19/2004 | 8/19/2004 | P | PASS |
Jim Sly
|
|
|
sandy; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles !st Pre Constr Conf...Met with Project Mngr (Greg) Job Super (Don) and job Foreman (Tim) . All People associated with ground work and Utilities there. MTI is special insp Agency. Went over plans with Don. 8/19/2004 4:18:09 PM
|
BLD-Conference | 8/19/2004 | 8/19/2004 | 8/19/2004 | P | PASS |
Jim Sly
|
|
|
don; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|