BLD-Aging Inspection | 10/24/2008 | 10/24/2008 | 10/31/2008 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 10/31/2008 | 10/31/2008 | 10/31/2008 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 8/15/2008 | 8/15/2008 | 8/15/2008 | P | PASS |
Dave Hannah
|
|
|
randy Phone #: ###-#### ok for cert of comp
|
BLD-Aging Inspection | 8/14/2008 | 8/14/2008 | 8/15/2008 | | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 2/26/2008 | 2/27/2008 | 2/28/2008 | P | PART |
Forrest France
|
|
|
Corrections verified for completion, fire life safety inspection passed.
|
BLD-Aging Inspection | 2/4/2008 | 2/4/2008 | 2/12/2008 | P | DEFR |
Forrest France
|
|
|
Provide functional EM lighting at all stairways, some need repaired as previously noted.
|
BLD-Aging Inspection | 2/4/2008 | 2/4/2008 | 2/4/2008 | | DEFR |
Dave Hannah
|
|
|
sent to fire
|
FIRE-Final Inspection | 11/30/2007 | 11/30/2007 | 12/4/2007 | P | FAIL |
Forrest France
|
|
|
Need to verify functional EM lighting at all three stairways, provide signage at the gates to the basement level in the stariways, remove covering at a fire sprinkler head in the south stairway 1st floor exit discharge.
|
BLD-Aging Inspection | 9/12/2007 | 9/12/2007 | 9/20/2007 | | FAIL |
Dave Hannah
|
|
|
needs fire signoffs walked project with owner
|
BLD-Final | 4/11/2006 | 4/12/2006 | 4/17/2006 | A | DONE |
Forrest France
|
|
|
wip, pending alarm and sprinkler permit finals.
|
BLD-Conference | 6/22/2005 | 6/23/2005 | 6/23/2005 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/22/2005 at 1:01:13 PM. Contact: ###-####. fire protection on 3rd floor ceiling ok to start covering
|
BLD-Other | 5/16/2005 | 5/17/2005 | 5/17/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/16/2005 at 12:00:21 PM. Contact: ###-####. ok to insulate
|
BLD-Framing/Rough-in | 4/20/2005 | 4/20/2005 | 4/20/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/20/2005 at 11:06:02 AM. Contact: ###-####. soffit in basement lobby area ok to cover 4/20/2005 2:22:08 PM
|
BLD-Conference | 4/5/2005 | 4/5/2005 | 4/5/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/5/2005 at 10:22:19 AM. Contact: ###-####. smoke dams 4/5/2005 3:17:22 PM
|
BLD-Conference | 3/30/2005 | 3/31/2005 | 3/31/2005 | A | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/30/2005 at 1:16:35 PM. Contact: ###-####.
|
BLD-Conference | 3/29/2005 | 3/30/2005 | 3/30/2005 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/29/2005 at 2:36:11 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/28/2005 | 3/29/2005 | 3/29/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/28/2005 at 1:38:50 PM. Contact: ###-####. needs to check floor pens in restrooms sec thru fifth 3/29/2005 9:55:56 AM
|
BLD-Conference | 3/22/2005 | 3/23/2005 | 3/23/2005 | A | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/22/2005 at 2:57:43 PM. Contact: ###-####.
|
BLD-Final | 3/23/2005 | 3/23/2005 | 3/23/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/22/2005 at 2:57:43 PM. Contact: ###-####. ok for temp occ 3/24/2005 12:00:00 PM
|
FIRE-Conference | 3/1/2005 | 3/1/2005 | 3/1/2005 | P | DONE |
Troy Cobbley
|
|
|
For temporary occupancy for the 6th floor I need a letter stating full functionability of the emergency lighting system, two emergency lights added on the sixth floor, signage in the stairs, a barrier at ground level landing to keep people from continuing to the basement, fire extinguisher for the first floor main lobby and sprinkler protection in the mechanical closet on the first floor.
|
BLD-Final | 2/24/2005 | 2/25/2005 | 2/25/2005 | A | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/24/2005 at 1:14:56 PM. Contact: ###-####.
|
BLD-Aging Inspection | 12/22/2004 | 12/22/2004 | 12/22/2004 | | PART |
Dave Hannah
|
|
|
wip 12/22/2004 10:09:30 AM
|