Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD04-01700
StatusFinaled
Name DOUG STOREY
Site Address 360 E MALLARD DR Unit: 100
Project NameLAKEPOINTE CENTRE II
Customer Number 
ePlanReviewNo
Description
(HOLLINGSHEAD EYE CENTER)(LAKEPOINTE CENTRE II-STE 100) Remodel and new 3,076 sq. ft. expansion to an existing 4,011 sq. ft. outpatient eye clinic and office on first floor of existing building per approved plans on file and CZC04-00129. New tenant space total will be 7,087 sq. ft. Work to include miscellaneous interior demolition work, new accessible parking spaces and curb ramp, new exterior accessible ramp with handrails, new exterior canopy at entrance, new interior walls and doors, some new interior windows, two new accessible restrooms, interior finish, suspended ceiling work, new counters/cabinets, new sinks, fire sprinkler work, mechanical work, plumbing work, and electrical work. (Additional area reduces the adjacent space and a separate permit under BLD04-01699 will be attached to the same plans.) A Certificate of Occupancy is to be issued when completed and approved. NOTE: This building is fully fire sprinklered for area increase. (PC#0477-04) JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 5/25/20055/25/2005 DONE
Details
Code Occupancy Approval  5/25/2005 PASS
OK PER PLANNING APPROVAL FINAL SIGNED OFF.
BLD-Final5/4/20055/6/20055/6/2005PPASS
DetailsJim Storey
please call 15 min prior///doug; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok pending p/z sign off.
FIRE-Final Inspection5/6/20055/6/20055/6/2005PPASS
DetailsForrest France
Fire life safety finaled.
FIRE-Final Inspection5/4/20055/5/20055/5/2005PPART
DetailsForrest France
Final pending correct verbage on sign at main entry, see IFC 1008.1.8.3 #2.2 2003 ed.
FIRE-Conference4/22/20054/25/20054/25/2005ADONE
DetailsForrest France
Meeting with Doug to clarify requirements for inspection compliance on project.
BLD-Final4/20/20054/21/20054/21/2005PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/20/2005 at 10:05:13 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Apr 21 2005 11:27AM.
FIRE-Final Inspection4/20/20054/20/20054/20/2005PFAIL
DetailsForrest France
Two exit signs at main entrance do not operate under emergency power supply. Test and verify exit disharge lighting and outdoor listing. Provide "when building is occupied" sign and remove thumb turn from main dbl. doors. Fire ext. in billing dept. is mou
BLD-Framing/Rough-in1/25/20051/25/20051/25/2005PPASS
DetailsJim Storey
doug; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Final12/28/200412/29/200412/29/2004APART
DetailsJim Storey
Dave- Suite 100; Phone #: ###-#### Internet Inspection Request from: Jan Rice first phase ok. 12/29/2004 10:07:28 AM
FIRE-Final Inspection12/28/200412/29/200412/29/2004AFAIL
DetailsRick Jackson
Dave- Suite 100; Phone #: ###-#### Internet Inspection Request from: Jan Rice Need fire code review notes; install exit sign at vestibule per plans; need to verify exit/emergency lights on battery; provide extinguishers; install sprinkler escutcheons; provide sprinkler resubmittals; exit sign at lobby area - remove arrow; duct detectors may be required will verify with plan review notes - no mechanical plans 12/29/2004 8:47:02 AM
BLD-Framing/Rough-in11/9/200411/10/200411/10/2004APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/9/2004 at 4:00:04 PM. Contact: ###-####. pending ele approval. 11/10/2004 9:57:50 AM
BLD-Conference10/20/200410/20/200410/20/2004PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/20/2004 at 11:09:34 AM. Contact: ###-####.