Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD04-02003
StatusFinaled
Name QUALITY QUARTZ ENGINEERING
Site Address 11566 W PRESIDENT DR
Project NameBENTE BLDG
Customer Number 
ePlanReviewNo
Description
(QUALITY QUARTZ ENGINEERING)(BENTE BLDG) A "Certificate of Occupancy is required. The building is fully sprinklered. To remodel and finish a 6,000 sq.ft. area on the west side of the building for a fabrication facility for glass products per approved plans. Work includes construction & finish of interior walls to create stock, packaging, cleaning and hot fabrication areas with access doors between areas; to remove portion of storefront glazing and enlarge opening per attached engineering detail, installing C10x15.3 steel channel as structural reinforcing support above opening with 3/4" threaded support rods W/ Hilti Hit HY-150 adhesive anchor (ER-5193), layout as shown, for new overhead door; to install cylinder 6-pack's of Hydrogen & Oxygen with process piping, process piping and non-combustible barrier between H2 & O2 cylinders, all per hazardous materials technical report attached to plans; to install or modify electrical, mechanical, plumbing, fire sprinkler & alarm systems to meet tenant needs and comply with adopted codes & ordinances.Use of hazardous materials within this tenant space are within allowable limits per code based on hazardous materials inventory provided by approved haz mat technical report attached. PC04-563/drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/16/200412/16/200412/16/2004PPASS
DetailsLane Manuel
Scheduled by a contractor via Hello! on 12/16/2004 at 9:47:23 AM.
permanent c of o ok 12/16/2004 3:03:55 PM
Permanent Occupancy 12/16/200412/16/2004 DONE
Details
BLD-Final12/15/200412/15/200412/15/2004PCANC
DetailsLane Manuel
Scheduled by a contractor via Hello! on 12/15/2004 at 10:31:33 AM. Contact: ###-####.
still needs plumbing final. 12/15/2004 2:13:27 PM
BLD-Final12/13/200412/13/200412/13/2004PPART
DetailsLane Manuel
signed for temp. c of o.
need to install emergency illumination @ exterior of bldg
BLD-Final12/9/200412/10/200412/10/2004PFAIL
DetailsLane Manuel
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
c/n left on site. No temp c of o. 12/10/2004 2:25:51 PM
FIRE-Final Inspection12/9/200412/10/200412/10/2004APASS
DetailsTroy Cobbley
Fire life safety finaled 12/10/2004 9:10:18 AM
FIRE-Final Inspection12/6/200412/6/200412/6/2004PFAIL
DetailsTroy Cobbley
Provide correct hardware on two of the west facing exit doors. Provide correct light level on face of exit sign or provide another type of approved exit sign at south (west facing) exit
BLD-Framing/Rough-in9/21/20049/22/20049/22/2004PPART
DetailsLane Manuel
Scheduled by a contractor via Hello! on 9/21/2004 at 2:20:22 PM. Contact: ###-####.
6" walls ok for cover @ inter. portion of project 9/22/2004 3:11:35 PM