FIRE-Final Inspection | 6/7/2005 | 6/8/2005 | 6/8/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety already finaled
|
BLD-Final | 5/26/2005 | 5/26/2005 | 5/27/2005 | P | PASS |
Jim Sly
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Barbara Moore OK for Perm Occ.
|
FIRE-Final Inspection | 5/25/2005 | 5/26/2005 | 5/26/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
BLD-Final | 5/25/2005 | 5/26/2005 | 5/26/2005 | A | NR |
Jim Sly
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
FIRE-Final Inspection | 5/19/2005 | 5/20/2005 | 5/20/2005 | A | FAIL |
Troy Cobbley
|
|
|
Provide exit discharge lighting (if this is the only item left I can sign a temp per Sam Rogers), repair the two office exit lights, provide manual operation for the smoke vents per IFC 910.3.1
|
FIRE-Conference | 5/16/2005 | 5/17/2005 | 5/17/2005 | A | DONE |
Troy Cobbley
|
|
|
Spoke to Phil about duct smoke detector locations. The north one needs relocated to be ahead of the elbow
|
Code Occupancy Approval | | | 5/10/2005 | | PASS |
|
|
|
FINAL SIGNED OFF.
|
BLD-Concrete | 12/30/2004 | 1/3/2005 | 1/3/2005 | A | PART |
Lane Manuel
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Jan Rice
tilt up panels on north side.
Terracon to provide special insp. 1/3/2005 11:18:15 AM
|
BLD-Concrete | 12/30/2004 | 12/30/2004 | 12/30/2004 | P | PART |
Lane Manuel
|
|
|
Jim; Phone #: 71der/slump test3-2139 Internet Inspection Request from: Jan Rice
5 tilt up panels on south side ok.
Terracon to provide special insp./cylinder/slump tests 12/30/2004 1:27:26 PM
|
BLD-Foundation | 12/21/2004 | 12/22/2004 | 12/22/2004 | P | PART |
Lane Manuel
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
remainder of perimeter footings ok.
terracon on site for special insp./ cylinders, etc. 12/22/2004 1:25:08 PM
|
BLD-Footing | 12/17/2004 | 12/17/2004 | 12/17/2004 | P | PART |
Lane Manuel
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Jan Rice
one half of bldg perimeter footing ok.
Terracon performed special insp., and took cylinder samples 12/17/2004 2:54:48 PM
|
BLD-Foundation | 12/13/2004 | 12/13/2004 | 12/13/2004 | P | PART |
Lane Manuel
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
two tilt up panels ok.
Terracon providing special insp. cylinder tests 12/13/2004 1:50:45 PM
|
BLD-Concrete | 12/6/2004 | 12/8/2004 | 12/8/2004 | P | PART |
Lane Manuel
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Jan Rice
partial ok. see notes from Terracon 12/8/2004 1:37:08 PM
|
BLD-Footing | 11/4/2004 | 11/5/2004 | 11/5/2004 | A | PART |
Jim Sly
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Special insp Req. this Project.....(2) center footing Pads OK pending Terricon special inspections, tests and approvals. 11/5/2004 9:38:35 AM
|