BLD-Final | 4/12/2005 | 4/12/2005 | 4/12/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/12/2005 at 9:51:52 AM. Contact: ###-####. ok for perm 4/12/2005 3:50:58 PM
|
FIRE-Final Inspection | 4/5/2005 | 4/6/2005 | 4/6/2005 | A | PASS |
Forrest France
|
|
|
Fire life safety finaled
|
FIRE-Final Inspection | 4/1/2005 | 4/4/2005 | 4/4/2005 | A | FAIL |
Troy Cobbley
|
|
|
Provide as-builts for the fire alarm system and straighten sprig ups in Fast Glass
|
BLD-Final | 4/1/2005 | 4/4/2005 | 4/4/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/1/2005 at 4:12:49 PM. Contact: ###-####. temp occ due to plunbing 4/4/2005 10:14:29 AM
|
BLD-Framing/Rough-in | 2/28/2005 | 2/28/2005 | 2/28/2005 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 2/28/2005 at 8:24:41 AM. Contact: ###-####.
shell framing ok 2/28/2005 4:25:57 PM
|
BLD-Framing/Rough-in | 2/23/2005 | 2/23/2005 | 2/23/2005 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 2/23/2005 at 8:54:47 AM. Contact: ###-####.
interior shearwall nailing ok 2/23/2005 3:18:44 PM
|
BLD-Framing/Rough-in | 2/11/2005 | 2/11/2005 | 2/11/2005 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 2/11/2005 at 8:21:10 AM. Contact: ###-####.
roof nailing ok 2/11/2005 3:18:52 PM
|
BLD-Footing | 11/9/2004 | 11/10/2004 | 11/10/2004 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/9/2004 at 3:33:06 PM. Contact: ###-####. north west corner and wall at same ok 11/10/2004 9:37:26 AM
|
BLD-Foundation | 11/9/2004 | 11/10/2004 | 11/10/2004 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/9/2004 at 3:33:59 PM. Contact: ###-####. wall at n/w corner ok 11/10/2004 10:28:44 AM
|
BLD-Footing | 11/5/2004 | 11/8/2004 | 11/8/2004 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 11/5/2004 at 2:35:23 PM. Contact: ###-####.
footings ok @ loading dock area. stemwall from line "c" thru "j" 11/8/2004 12:41:45 PM
|
BLD-Footing | 11/4/2004 | 11/5/2004 | 11/5/2004 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/4/2004 at 2:30:40 PM. Contact: ###-####.
|
BLD-Foundation | 11/4/2004 | 11/5/2004 | 11/5/2004 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/4/2004 at 2:29:28 PM. Contact: ###-####. wall at south and west ok 11/5/2004 8:54:25 AM
|
BLD-Footing | 11/1/2004 | 11/2/2004 | 11/2/2004 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/1/2004 at 4:15:06 PM. Contact: ###-####. Most of west wall, all of S. wall, and 1/2 of E. wall OK....2500 PSI Soils test... Drain rock max 6" . 11/2/2004 9:22:32 AM 11/2/2004 9:23:06 AM
|