Code Occupancy Approval | 5/17/2007 | 5/17/2007 | 5/17/2007 | P | PASS |
Michael Garner
|
|
|
SITE INSPECTION COMPLETE - i REVIEWED THE APPROVED PLANS AND CONDITIONS AND HAVE FOUND THEM TO BE IN SUBSTANTIAL COMPLIANCE: I DID NOTE THE FOLLOWING CHANGES -
1. PLANS CALLED FOR A SOLID PLANTER ON THE MINI-COURTYARD BETWEEN THE CENTER BLDGS - THAT WAS CHANGED TO INDIVIDUAL VASE PLANTERS PER CONSULTATION WITH THE FIRE DEPARTMENT WHO HAD CONCERNS ABOUT ACCESS TO HOSE CONNECTIONS AND INTO THE BLDGS. THEMSELVES
2. PLANS FOR THE CENTER BLDGS CALLED FOR THREE [3] VERTICALLY STACKED WINDOWS MIRRORING THE INTERIOR STAIRWELLS - THAT HAS BEEN CHANGED TO TWO WINDOWS, WITH THE MIDDLE WINDOW REMOVED TO ACCOMODATE A REQUIRED A NECESSARY STRUCTURAL BEAM
3. ORIGINAL PLANS CALLED FOR ROUGH-HEWN [CEDAR?] SHINGLES - BLDR. INSTEAD USED HARDI-PLANK SHINGLES BECAUSE THEY ARE LONGER LASTING, EASIER TO MAINTAIN
4. THE MOST INTERIOR [CLOSEST TO CREEK] BLDGS DO NOT HAVE A STUCCO SKIRT AS THE PLANS CALLED FOR...INSTEAD THEY HAVE A STONE SKIRT WHICH IS IN KEEPING WITH THE STONE SKIRTS ON ALL THE OTHER BLDGS.
THESE CHANGES ARE ACCEPTABLE AND WITHIN THE PARAMETERS OF THE SCOPE AND INTENT OF THE APPROVED PLANS AND CONDITIONS - PASS/CASE CLOSED
|
BLD-Final | 11/22/2005 | 11/23/2005 | 11/23/2005 | A | PASS |
Tony Young
|
|
|
keil ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
DOC - Permit Finaled | 11/23/2005 | 11/23/2005 | 11/23/2005 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 11/18/2005 | 11/21/2005 | 11/21/2005 | P | NH |
Tony Young
|
|
|
Steve, ###-####
|
BLD-Final | 11/8/2005 | 11/8/2005 | 11/8/2005 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/8/2005 at 8:11:13 AM. Contact: ###-####. hand rail/all others signed off
|
BLD-Energy code compliance | 6/24/2005 | 6/24/2005 | 6/24/2005 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 6/23/2005 | 6/24/2005 | 6/24/2005 | A | NR |
Dave Hannah
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 6/21/2005 | 6/22/2005 | 6/22/2005 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/21/2005 at 3:42:44 PM. Contact: ###-####.ok to insulate after fixing minor issues,, need letter from arch. on venting issues, and access issues
|
BLD-Framing/Rough-in | 6/8/2005 | 6/8/2005 | 6/9/2005 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/8/2005 at 8:51:19 AM. Contact: ###-####. ext. shear ok
|
BLD-Framing/Rough-in | 6/6/2005 | 6/6/2005 | 6/6/2005 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/6/2005 at 7:36:50 AM. Contact: ###-####. nail shear per plan
|
BLD-Framing/Rough-in | 4/29/2005 | 5/2/2005 | 5/2/2005 | P | PART |
Tony Young
|
|
|
jim ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
435 looked at lower,,, upper fire wall ok to stand 5/2/2005 1:22:06 PM
|
BLD-Foundation | 3/22/2005 | 3/22/2005 | 3/22/2005 | P | PASS |
Troy James
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Footing | 3/17/2005 | 3/18/2005 | 3/18/2005 | A | PASS |
Troy James
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|