Permit Information
Permit NumberBLD04-02372
StatusFinaled
Name BOISE CITY HOUSING
Site Address 575 S 13TH ST
Project NameCommunity House - temp housing
Customer Number 
ePlanReviewNo
Description
TEMPORARY OCCUPANCY - A permit to install a 26 x 56 2016 sq. ft. modular building to be used as a dormatory for a maximum of 48 occupants for a period of time not to exceed 180 days from final approval. This permit includes the foundation, tie-downs, accessible ramp and stairs, new panic hardware on exit doors, new exit signs, emergency light, fire alarms and smoke detectors per approved plans and attachments, CZC04-00149. State of Idaho Tag # WA-IDI 0320CC. A Temporary Certificate of Occupancy for 180 days is to be issued on final approval. This temporary building has been approved in accordance with IBC Section 107.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/3/200411/4/200411/4/2004PPASS
DetailsBob Archibald
Bill- need sign off for ele & fir...Call before you go out; Phone #: ###-#### Internet Inspection Request from: Jan Rice. Corrections made ok.
FIRE-Final Inspection11/4/200411/4/200411/4/2004APASS
DetailsRick Jackson
Fire/life safety okay 11/4/2004 3:45:25 PM
DOC - Permit Finaled  11/4/2004 DONE
BLD-Other11/2/200411/2/200411/2/2004PPART
DetailsBob Archibald
Corrections being made.
BLD-Conference10/29/200410/29/200410/29/2004PPART
DetailsBob Archibald
CN issued identifying requirements for occupancy.
BLD-Conference10/20/200410/20/200410/20/2004PPART
DetailsBob Archibald
Conference with Bill on stairs located at south end of structure. Lowest riser on eastside and top riser on westside require identification as hazardous. Electrical utility drop to structure installed and approved by Jim Schmer. No other new construction in progress.
BLD-Other10/18/200410/18/200410/18/2004PPASS
DetailsBob Archibald
Remainder of tie downs verified. Stair and ramp construction in progress.
BLD-Conference10/15/200410/15/200410/15/2004PPART
DetailsBob Archibald
Site visit and conference with contractors. Discussed scheduling and verified tie downs on west units, east unit to be left with access for verification. Ramp scheduled for completion on 10/19/04.