BLD-Conference | 5/23/2006 | 5/24/2006 | 5/24/2006 | A | PASS |
Tony Young
|
|
|
verify for plumbing if final is done this should have all been passed before,, ok
|
DOC - Permit Finaled | 5/24/2006 | 5/24/2006 | 5/24/2006 | P | PASS |
Tony Young
|
|
|
done
|
BLD-Final | 6/6/2005 | 6/7/2005 | 6/8/2005 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/6/2005 at 4:20:25 PM. Contact: ###-####.
|
BLD-Conference | 6/1/2005 | 6/2/2005 | 6/2/2005 | P | PASS |
Tony Young
|
|
|
please call 30 min prior to meet///chris; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa reciever coach,,, GO B S U !!!!!,,, CONF ON FINAL
|
BLD-Energy code compliance | 2/23/2005 | 2/24/2005 | 2/24/2005 | A | CANC |
Troy James
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Energy code compliance | 2/24/2005 | 2/24/2005 | 2/24/2005 | P | PASS |
Troy James
|
|
|
|
BLD-Framing/Rough-in | 2/23/2005 | 2/24/2005 | 2/24/2005 | P | PASS |
Troy James
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Energy code compliance | 2/21/2005 | 2/22/2005 | 2/22/2005 | A | CANC |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 2/21/2005 at 12:16:47 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/21/2005 | 2/22/2005 | 2/22/2005 | A | FAIL |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 2/21/2005 at 12:16:10 PM. Contact: ###-####. c/n posted 2/22/2005 11:33:59 AM
|
BLD-Foundation | 12/17/2004 | 12/20/2004 | 12/20/2004 | A | PASS |
Troy James
|
|
|
Gordon - late morning; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
BLD-Footing | 12/17/2004 | 12/17/2004 | 12/17/2004 | P | PART |
Troy James
|
|
|
gordon; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
wip setbacks ok rebar laying in forms 12/17/2004 1:20:17 PM
|
BLD-Grading Inspection | 12/16/2004 | 12/16/2004 | 12/16/2004 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engineer
|
BLD-Grading Inspection | 6/7/2005 | 6/7/2005 | | | |
|
|
|
Final grading and drainage approved. However when the storm drain connection was checked it took nearly 35 minutes for the water to make it to the street storm drain. Advised Chris Lombardo that this indicates there may be a problem
|