BLD-Final | 6/1/2005 | 6/2/2005 | 6/2/2005 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/1/2005 at 8:06:27 AM. Contact: ###-####.ok for perm occ
|
FIRE-Final Inspection | 6/1/2005 | 6/1/2005 | 6/1/2005 | P | FAIL |
Forrest France
|
|
|
Door at east exit to corridor must have code approved hardware. All remaining life safety issues are satisfactory.
|
FIRE-Final Inspection | 6/1/2005 | 6/1/2005 | 6/1/2005 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
Permanent Occupancy | | 6/1/2005 | 6/1/2005 | | DONE |
|
|
|
|
BLD-Final | 4/13/2005 | 4/13/2005 | 4/13/2005 | P | PART |
Dave Hannah
|
|
|
###-#### - paul Note: please call 1/2 hr prior to inspection ok for temp occ needs other trades to go perm and fire safe corr wall above exit door 4/13/2005 2:35:50 PM
|
FIRE-Final Inspection | 4/12/2005 | 4/12/2005 | 4/12/2005 | P | PART |
Forrest France
|
|
|
Temporary occupancy given per Dave Lokker, pending installation and testing of emergency lighting, and verification of door hardware.
|
FIRE-Final Inspection | 4/8/2005 | 4/11/2005 | 4/11/2005 | A | FAIL |
Troy Cobbley
|
|
|
Fail, install and test emergency lights as marked on plans, verify door hardware.
|
BLD-Final | 4/8/2005 | 4/11/2005 | 4/11/2005 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/8/2005 at 4:27:21 PM. Contact: ###-####. needs fire sign off 4/12/2005 8:03:35 AM
|
BLD-Other | 4/1/2005 | 4/4/2005 | 4/4/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/1/2005 at 11:29:27 AM. Contact: ###-####.ceiling grid conf room ok all other grid is exst 4/4/2005 9:48:39 AM
|
BLD-Framing/Rough-in | 3/7/2005 | 3/8/2005 | 3/8/2005 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/7/2005 at 12:47:20 PM. Contact: ###-####.this finishs int wall framing 3/8/2005 9:54:07 AM
|
BLD-Framing/Rough-in | 3/2/2005 | 3/3/2005 | 3/3/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/2/2005 at 1:11:21 PM. Contact: ###-####. 3/3/2005 2:23:11 PM
|