Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD04-02971
StatusFinaled
Name VAN AUKER CONSTRUCTION
Site Address 12450 W EXECUTIVE DR
Project NameVAN AUKER CLOVERDALE #10
Customer Number 
ePlanReviewNo
Description
(MIDWEST FLOOR COVERING)(VAN AUKER CLOVERDALE #10 BLDG) New tenant to occupy entire 26,400 sq. ft. vacant shell building for warehouse use and constructing a new 1,660 sq. ft. accessory office area with light storage mezzanine above and a small 144 sq. ft. H-3 occupancy flammable liquid storage room all per approved plans and engineering. Work to include two new interior square pad footings, new steel column and girder, new wood column, new floor joists and sheathing, new stairway with handrails and guard, new guard at light storage mezzanine, new one-hour rated fire barrier walls with 3/4 hour rated doors and one-hour rated floor-ceiling assembly at H-3 occupancy, some new interior walls and doors, new interior finish, new suspended ceiling, two new accessible restrooms, fire sprinkler work, new mechanical work including a new furnace, new plumbing, and new electrical work. Special Inspection is required for steel construction (fabrication/welding), fabrication process of wood structural elements on premises of fabricator's shop, soils, and epoxy/adhesive anchor installations. Deferred submittal for compliance with the IFC for the H-3 flammable liquid storage room will be submitted into the office for approval prior to installation. Racking in the warehouse will be done under a separate permit. A Certificate of Occupancy is to be issued when completed and approved. NOTE: This building is fully fire sprinklered. JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/28/20054/29/20054/29/2005APASS
DetailsJim Sly
per your request Internet Inspection Request from: Barbara Moore OK for Perm Occ :) 4/29/2005 10:33:51 AM
Permanent Occupancy 4/29/20054/29/2005 DONE
Details
FIRE-Final Inspection4/22/20054/25/20054/25/2005APASS
DetailsTroy Cobbley
Fire life safety finaled
FIRE-Final Inspection4/20/20054/21/20054/21/2005AFAIL
DetailsForrest France
Remove thumbturn from main office exit door. Flammable liquid storage room needs doors installed for hardware verification.
BLD-Framing/Rough-in4/12/20054/13/20054/13/2005APART
DetailsJim Sly
jim Note: ceiling; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Grid OK. 4/13/2005 9:16:47 AM
BLD-Energy code compliance3/18/20053/18/20053/18/2005PPASS
DetailsDave Hannah
jim; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in3/17/20053/17/20053/17/2005PPART
DetailsDave Hannah
jim; Phone #: ###-#### Internet Inspection Request from: Barbara Moore int walls ok to insulate shear on ext walls on office ok to cover ok to insulate office area 3/17/2005 5:20:09 PM
BLD-Framing/Rough-in3/8/20053/8/20053/8/2005PFAIL
DetailsJim Sly
jim; Phone #: ###-#### Internet Inspection Request from: Barbara Moore C/N Eng to approve Simpson LBV316 joist hangers with 8 nails only ..... Complete shear walls and recall. Check sill fastening (8" oc) 3/8/2005 4:22:18 PM
BLD-Concrete2/28/20052/28/20052/28/2005PPART
DetailsLane Manuel
Jim; Phone #: ###-#### Internet Inspection Request from: Jan Rice
2 interior piers ok 2/28/2005 3:04:10 PM