BLD-Final | 4/25/2005 | 4/25/2005 | 4/25/2005 | P | PASS |
Dave Hannah
|
|
|
Don, ###-#### needs elec hook ups and dissconnections
|
Permanent Occupancy | | 4/25/2005 | 4/25/2005 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/21/2005 | 4/22/2005 | 4/22/2005 | A | PASS |
Troy Cobbley
|
|
|
fire life finaled
|
BLD-Final | 4/20/2005 | 4/21/2005 | 4/21/2005 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/20/2005 at 11:08:13 AM. Contact: ###-####. needs fire life safty sign off and change locks front and back exit doors 4/21/2005 2:19:27 PM
|
FIRE-Final Inspection | 4/21/2005 | 4/21/2005 | 4/21/2005 | A | FAIL |
Forrest France
|
|
|
Keyed hardware only allowed on one exterior door. Remaining doors in main entry/exit must have approved hardware. Pocket door on work room must have approved hardware. Approved hardware req. on teller gate.
|
FIRE-Final Inspection | 4/15/2005 | 4/18/2005 | 4/18/2005 | A | FAIL |
Forrest France
|
|
|
Fail inspection. Keyed hardware is only allowed on one door. Main entry/exit has three. See building review note #14 and fire review note #6. Remove manual flush bolts from conference room doors, see bld. review note #15. Duct detectors are mounted o
|
FIRE-Sprinkler Rough-in | 4/14/2005 | 4/15/2005 | 4/15/2005 | A | PASS |
Troy Cobbley
|
|
|
Ceilings and pendant sprinklers added in the three rooms that previously did not have ceilings. Sprinklers in these rooms ok to cover
|
BLD-Other | 3/31/2005 | 4/1/2005 | 4/1/2005 | P | PART |
Dave Hannah
|
|
|
Don, ###-#### would like a ceiling inspectionok to cover front lobby area 4/1/2005 1:20:18 PM
|
BLD-Framing/Rough-in | 2/17/2005 | 2/18/2005 | 2/18/2005 | A | PASS |
Dave Hannah
|
|
|
Don, ###-####
|