Permit Information
Permit NumberBLD04-03049
StatusFinaled
Name BENITON CONSTRUCTION
Site Address 111 N AVENUE C
Project NameWolf-Mistry Medical Office
Customer Number 
ePlanReviewNo
Description
Wolf-Mistry Medical Office Building - To construct a 3,287 sq. ft two story Type VB building with a 1, 520 sq. ft. basement. First floor of 1,767 sq. ft. will be used for a medical office with the 1,520 sq. ft. second floor and 1,520 sq. ft. basement used as private residences. Other work includes site demolition, site improvements, paving and landscaping per approved plans and attachements, CVA04-00041, CUP04-00118, DRH04-00041.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/3/200510/4/200510/4/2005APASS
DetailsDave Hannah
russ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok for perm occ
FIRE-Final Inspection9/30/200510/3/200510/3/2005PPASS
DetailsForrest France
Fire life safety passed inspection.
FIRE-Final Inspection9/29/20059/30/20059/30/2005PCANC
DetailsForrest France
Cancel inspection per Russ the general contractor.
FIRE-Final Inspection9/27/20059/29/20059/29/2005ANR
DetailsForrest France
Project is not ready for inspection, contractor to reschedule.
Code Occupancy Approval9/28/20059/28/20059/28/2005PPASS
DetailsWm. Michael Meloy
Permanent Occupancy 9/28/20059/28/2005 DONE
Details
BLD-Other9/8/20059/9/20059/9/2005APART
DetailsDave Hannah
russ Note: ceiling suspended grid; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to drop panels
BLD-Framing/Rough-in9/1/20059/1/20059/2/2005PNR
DetailsDave Hannah
suspended ceiling grid inspection please///russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in8/8/20058/9/20058/9/2005APART
DetailsDave Hannah
Russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok to cover around stairs in basement
BLD-Framing/Rough-in8/5/20058/5/20058/8/2005PPART
DetailsDave Hannah
steel stud ceiling inspection///russ ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ceil in basement ok to cover
BLD-Energy code compliance8/1/20058/2/20058/2/2005APASS
DetailsMike Jordan
russ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Lateral bracing at gable end has been repaired.
BLD-Framing/Rough-in7/27/20057/28/20057/28/2005APART
DetailsMike Jordan
russ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. OK to insulate. Need to rienspect gable ends for proper bracing. Also need to complete fire caulking of penetrations.
BLD-Energy code compliance7/20/20057/21/20057/21/2005PPART
DetailsJim Storey
russ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok to cover basement and first floor.
BLD-Framing/Rough-in7/18/20057/19/20057/19/2005APART
DetailsJim Storey
russ ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie basement and first floor ok to insulate and one side to verify boxes back to back and less than 24 " horizontal spacing as well as hvac shaft interior drywall aplacation.
BLD-Framing/Rough-in7/15/20057/18/20057/18/2005APART
DetailsTony Young
russ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
exterior shear,,, need fix from engineer on strap call-out where cantilever
BLD-Other7/8/20057/11/20057/12/2005PDONE
DetailsDave Hannah
roof sheating inspection//rus; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
BLD-Framing/Rough-in7/5/20057/6/20057/6/2005APART
DetailsDave Hannah
exterior shear nail inspection please////russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore areas that need stone ok to cover
BLD-Framing/Rough-in6/29/20056/30/20056/30/2005PPART
DetailsDave Hannah
russ Note: 2nd floor only; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to cover firts floor ceiling
BLD-Energy code compliance6/22/20056/23/20056/23/2005APART
DetailsDave Hannah
russ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa basement rim ok to cover basement ceiling
BLD-Framing/Rough-in6/21/20056/22/20056/23/2005APART
DetailsDave Hannah
1st floor joist inspection please///russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore basement ceiling ok to insulate rim
BLD-Foundation5/24/20055/25/20055/25/2005APASS
DetailsDave Hannah
russ--for stairwell ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Foundation5/17/20055/18/20055/18/2005PPART
DetailsDave Hannah
russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore rebare ok crew will have spec inspection tomorrow be for pour
BLD-Concrete5/3/20055/4/20055/4/2005APART
DetailsDave Hannah
late am please///russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore mti will also sign off pour
BLD-Footing4/21/20054/22/20054/22/2005PPASS
DetailsTroy James
Scheduled by a contractor via Hello! on 4/21/2005 at 1:09:45 PM. Contact: ###-####.