BLD-Final | 10/3/2005 | 10/4/2005 | 10/4/2005 | A | PASS |
Dave Hannah
|
|
|
russ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok for perm occ
|
FIRE-Final Inspection | 9/30/2005 | 10/3/2005 | 10/3/2005 | P | PASS |
Forrest France
|
|
|
Fire life safety passed inspection.
|
FIRE-Final Inspection | 9/29/2005 | 9/30/2005 | 9/30/2005 | P | CANC |
Forrest France
|
|
|
Cancel inspection per Russ the general contractor.
|
FIRE-Final Inspection | 9/27/2005 | 9/29/2005 | 9/29/2005 | A | NR |
Forrest France
|
|
|
Project is not ready for inspection, contractor to reschedule.
|
Code Occupancy Approval | 9/28/2005 | 9/28/2005 | 9/28/2005 | P | PASS |
Wm. Michael Meloy
|
|
|
|
Permanent Occupancy | | 9/28/2005 | 9/28/2005 | | DONE |
|
|
|
|
BLD-Other | 9/8/2005 | 9/9/2005 | 9/9/2005 | A | PART |
Dave Hannah
|
|
|
russ Note: ceiling suspended grid; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to drop panels
|
BLD-Framing/Rough-in | 9/1/2005 | 9/1/2005 | 9/2/2005 | P | NR |
Dave Hannah
|
|
|
suspended ceiling grid inspection please///russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 8/8/2005 | 8/9/2005 | 8/9/2005 | A | PART |
Dave Hannah
|
|
|
Russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok to cover around stairs in basement
|
BLD-Framing/Rough-in | 8/5/2005 | 8/5/2005 | 8/8/2005 | P | PART |
Dave Hannah
|
|
|
steel stud ceiling inspection///russ ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ceil in basement ok to cover
|
BLD-Energy code compliance | 8/1/2005 | 8/2/2005 | 8/2/2005 | A | PASS |
Mike Jordan
|
|
|
russ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Lateral bracing at gable end has been repaired.
|
BLD-Framing/Rough-in | 7/27/2005 | 7/28/2005 | 7/28/2005 | A | PART |
Mike Jordan
|
|
|
russ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. OK to insulate. Need to rienspect gable ends for proper bracing. Also need to complete fire caulking of penetrations.
|
BLD-Energy code compliance | 7/20/2005 | 7/21/2005 | 7/21/2005 | P | PART |
Jim Storey
|
|
|
russ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok to cover basement and first floor.
|
BLD-Framing/Rough-in | 7/18/2005 | 7/19/2005 | 7/19/2005 | A | PART |
Jim Storey
|
|
|
russ ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie basement and first floor ok to insulate and one side to verify boxes back to back and less than 24 " horizontal spacing as well as hvac shaft interior drywall aplacation.
|
BLD-Framing/Rough-in | 7/15/2005 | 7/18/2005 | 7/18/2005 | A | PART |
Tony Young
|
|
|
russ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa exterior shear,,, need fix from engineer on strap call-out where cantilever
|
BLD-Other | 7/8/2005 | 7/11/2005 | 7/12/2005 | P | DONE |
Dave Hannah
|
|
|
roof sheating inspection//rus; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 7/5/2005 | 7/6/2005 | 7/6/2005 | A | PART |
Dave Hannah
|
|
|
exterior shear nail inspection please////russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore areas that need stone ok to cover
|
BLD-Framing/Rough-in | 6/29/2005 | 6/30/2005 | 6/30/2005 | P | PART |
Dave Hannah
|
|
|
russ Note: 2nd floor only; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to cover firts floor ceiling
|
BLD-Energy code compliance | 6/22/2005 | 6/23/2005 | 6/23/2005 | A | PART |
Dave Hannah
|
|
|
russ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa basement rim ok to cover basement ceiling
|
BLD-Framing/Rough-in | 6/21/2005 | 6/22/2005 | 6/23/2005 | A | PART |
Dave Hannah
|
|
|
1st floor joist inspection please///russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore basement ceiling ok to insulate rim
|
BLD-Foundation | 5/24/2005 | 5/25/2005 | 5/25/2005 | A | PASS |
Dave Hannah
|
|
|
russ--for stairwell ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Foundation | 5/17/2005 | 5/18/2005 | 5/18/2005 | P | PART |
Dave Hannah
|
|
|
russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore rebare ok crew will have spec inspection tomorrow be for pour
|
BLD-Concrete | 5/3/2005 | 5/4/2005 | 5/4/2005 | A | PART |
Dave Hannah
|
|
|
late am please///russ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore mti will also sign off pour
|
BLD-Footing | 4/21/2005 | 4/22/2005 | 4/22/2005 | P | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 4/21/2005 at 1:09:45 PM. Contact: ###-####.
|