Permit Information
Permit NumberBLD05-00087
StatusExpired
Name VILLA HIGHLAND LLC
Site Address 2291 N 15TH ST
Project NameVilla Highlands
Customer Number 
ePlanReviewNo
Description
Villa Highlands * To construct a new 63,830 sq.ft. three story, independent living facility with 50 dwelling units, There will be a common kitchen, dining room and common multi-purpose area on the first floor for the residence use only. The first floor is 22,758 sq.ft. the second floor is 19,978 sq.ft and the third floor is 20,093 sq.ft. there are 9 - two bedroom, one bath units that are over 800 sq.ft. the remaining units are one bedroom one bath and less than 800 sq.ft. There is a 500 sq.ft. arts and craft room located on the third floor, a 300 sq.ft. excerise room and a 200 sq.ft. projection room on the second floor. NOTE: This structure is fully fire sprinklered per NFPA 13 for area increase. All construction per the approved plans and attached comment list. MJP DRH 04-00138 CUP 04-00046
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection10/15/200710/15/200710/16/2007 PEND
DetailsTony Young
BLD-Aging Inspection6/12/20076/12/20076/14/2007 PEND
DetailsTony Young
Extend Permit 180 days 3/29/20073/29/2007 DONE
BLD-Aging Inspection1/10/20071/10/20071/11/2007 PEND
DetailsTony Young
BLD-Aging Inspection11/7/200611/7/200611/7/2006 PEND
DetailsTony Young
BLD-Conference8/28/20068/29/20069/1/2006ACANC
DetailsTony Young
Discuss engineering and special inspection requirements with general contractor and trades.
BLD-Conference8/31/20069/1/20069/1/2006APASS
DetailsTony Young
meet contractor to verify special inspection needs per Bob A.
met w/ Dave Atwood on site,, said special inspections are being performed about 2 times a day on rebuild of retaining wall
BLD-Conference8/28/20068/28/20068/28/2006APART
DetailsBob Archibald
Received engineering analysis on retaining wall and existing footings. Discussed requirements with Wes and John from Petra and also with crew repairing retaining wall. Repair is to be in reviewed by structural engineer and special inspection also be provided.
BLD-Other6/29/20066/29/20066/29/2006APART
DetailsTony Young
Fire damaged debrie removed from site under permit # BLD06-01649. Structural engineering analysis is required on remaining perimeter footings/foundations that will be used to rebuild structure.
BLD-Framing/Rough-in5/16/20065/19/20065/19/2006PPART
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
ok to cover ceilings in main level great room, offices, kitchen and 3rd floor hallway ceilings
BLD-Framing/Rough-in5/16/20065/18/20065/18/2006PPART
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
ok to insulate ceiling of main level,,, fire-sprayed beams ok pending s. i. report
BLD-Framing/Rough-in5/16/20065/17/20065/17/2006PFAIL
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
c/n posted,, partial frame insp,, need stud bearing for over drilled studs for plumbing,, corridor protection,,
BLD-Framing/Rough-in5/16/20065/16/20065/17/2006PPART
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
conf. walk through on main level
BLD-Framing/Rough-in5/15/20065/15/20065/16/2006PCANC
DetailsTony Young
blake ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
FIRE-Conference5/2/20065/2/20065/2/2006PDONE
DetailsForrest France
On site confrence to discuss emergency lighting requirements for the path of egress as indicated on approved plans.
FIRE-Conference4/28/20065/1/20065/2/2006ADEFR
DetailsForrest France
To be completed 5/2 as discussed.
BLD-Framing/Rough-in4/25/20064/25/20064/25/2006PPART
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
ok to rock ceiling area of hall ways on 2nd and 3rd floor pending trades,, sprinklers
BLD-Framing/Rough-in4/20/20064/20/20064/20/2006PPART
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
elevator shaft ok
BLD-Conference4/11/20064/12/20064/12/2006APART
DetailsTony Young
Blake; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
phone conf. only,, will call in for frame later in week
BLD-Framing/Rough-in4/4/20064/5/20064/5/2006APART
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
ok to cover ceiling in east hall,, 1st floor
FIRE-Final Inspection3/30/20063/31/20063/31/2006ACANC
DetailsTroy Cobbley
to be rescheduled
BLD-Framing/Rough-in3/27/20063/27/20063/27/2006PPART
DetailsTony Young
blake ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
frame conf., and drywall on exterior ok to cover by main stair way entry, north east corner,, will cover w/ felt paper and brick
BLD-Framing/Rough-in3/22/20063/23/20063/23/2006AFAIL
DetailsTony Young
Blake; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
need plumbing rough prior to any cover in corridors
BLD-Framing/Rough-in3/22/20063/22/20063/22/2006PNR
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in3/20/20063/20/20063/20/2006PPART
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
ext. shear ok
BLD-Framing/Rough-in3/16/20063/17/20063/17/2006APART
DetailsTony Young
Blake; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
exterior shear ok on ground level only
BLD-Other3/15/20063/16/20063/16/2006APART
DetailsTony Young
Blake,, shear and roof; Phone #: ###-####
roof area ok to cover,, ext. shear needs to be gone over again and galv. nails in sill plate
BLD-Framing/Rough-in3/14/20063/15/20063/15/2006PPART
DetailsTony Young
Blake; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
big complex to see,, rescheduled for am
BLD-Framing/Rough-in1/20/20061/23/20061/23/2006APART
DetailsTony Young
walk through and shear?,, Blake; Phone #: ###-####
general walk through,,, shear on garage ok
BLD-Framing/Rough-in1/19/20061/20/20061/20/2006ACANC
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in12/7/200512/7/200512/7/2005PPART
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
detatched garage frame ok,, verify draft stop later
BLD-Framing/Rough-in12/6/200512/7/200512/7/2005ANR
DetailsTony Young
Scheduled by a contractor via Hello! on 12/6/2005 at 3:25:11 PM. Contact: ###-####.
BLD-Framing/Rough-in12/5/200512/6/200512/6/2005AFAIL
DetailsDave Hannah
blake; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa c/n items not completed
BLD-Framing/Rough-in12/5/200512/5/200512/5/2005PFAIL
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
need sill bolts, straps on top plates, draft stop, etc,, detatched garages only
BLD-Footing11/16/200511/16/200511/16/2005PPASS
DetailsTom Arcoraci
blake; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles spec insp
BLD-Footing11/2/200511/3/200511/3/2005APART
DetailsTony Young
re-bar for interior footing//blake; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
s. i. on site
BLD-Footing10/26/200510/27/200510/27/2005APART
DetailsTony Young
blake; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
pending s. i. report,, looked at yesterday due to 6:30am pour,, wip
BLD-Footing9/14/20059/14/20059/14/2005PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/14/2005 at 9:48:23 AM. Contact: ###-####. int colunm ftgs ok to pour
BLD-Foundation9/1/20059/2/20059/2/2005PPART
DetailsTony Young
pour at 2:30////blake; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
pend s. i. report,, stem walls on west and north
BLD-Footing8/30/20058/31/20058/31/2005APART
DetailsTony Young
Scheduled by a contractor via Hello! on 8/30/2005 at 11:56:25 AM. Contact: ###-####.
pending s. i. report
BLD-Footing8/26/20058/29/20058/29/2005APART
DetailsTony Young
Scheduled by a contractor via Hello! on 8/26/2005 at 12:24:38 PM. Contact: ###-####.
pending s. i. report
BLD-Footing8/24/20058/25/20058/25/2005PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 8/24/2005 at 1:08:31 PM. Contact: ###-####.
BLD-Footing8/12/20058/15/20058/15/2005PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 8/12/2005 at 2:58:50 PM. Contact: ###-####.
BLD-Foundation8/12/20058/12/20058/12/2005PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 8/12/2005 at 7:53:10 AM. Contact: ###-####.
detached garage walls,, pend. s. i. report
BLD-Footing8/10/20058/10/20058/10/2005PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 8/10/2005 at 11:05:00 AM. Contact: ###-####.
grid line h sect 2,--323 and grid 2.9, c--h ok,, also detached garage, ok,, pend s. i. report
BLD-Foundation7/13/20057/14/20057/14/2005APART
DetailsTony Young
Scheduled by a contractor via Hello! on 7/13/2005 at 4:13:23 PM. Contact: ###-####.
PENDING SPEICIAL INSPECTION
BLD-Footing7/6/20057/6/20057/6/2005PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 7/6/2005 at 8:14:15 AM. Contact: ###-####.
south ftgs,,, pending special inspection report