Permit Information
Permit NumberBLD05-00322
StatusFinaled
Name LITZINGER CONSTRUCTION CO
Site Address 1906 S VISTA AVE
Project NameSWANSON OFFICE BLDG
Customer Number 
ePlanReviewNo
Description
Swanson Office Building (Shell & Core) - To construct a new 4320 square foot, one story, wood framed office building on a concrete slab floor. This building will contain a core area consisting of two restrooms, a utility room, an access hallway and a 280 square foot common use conference room. 890 sq. ft., tenant space "A", at the southeast corner of the building, will have a vanilla finish. An MIS permit will be required to approve this space for occupancy. The remainder of the building will be unfinished and will require separate tenant improvement permits to finish for occupancy. No occupancy is approved under this permit. All construction per the approved plans on file. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection2/1/20062/1/20062/1/2006 PASS
DetailsJim Storey
DOC - Permit Finaled2/1/20062/1/20062/1/2006PPASS
DetailsJim Storey
BLD-Final12/2/200512/2/200512/2/2005APASS
DetailsTom Arcoraci
Please call 1/2 hour before inspection...thanks; Phone #: ###-#### Internet Inspection Request from: Ken Litzinger lc issued
Code Occupancy Approval12/1/200512/1/200512/1/2005PPASS
DetailsDena Gambrel
Final signed off.
BLD-Final11/28/200511/29/200511/29/2005ANR
DetailsTom Arcoraci
Please Call 1/2 hour before inspection...thanks; Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
FIRE-Final Inspection11/28/200511/28/200511/28/2005PPASS
DetailsForrest France
Items on correction notice have been resolved, life safety passed inspection.
FIRE-Final Inspection11/21/200511/22/200511/22/2005AFAIL
DetailsForrest France
The exit discharge lights failed to function, provide approved hardware for the pocket doors at the confrence room as required.
FIRE-Final Inspection11/21/200511/21/200511/21/2005PCANC
DetailsTroy Cobbley
No time for inspection
BLD-Final11/14/200511/14/200511/14/2005PNR
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
BLD-Wall cover9/12/20059/12/20059/12/2005PNR
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
BLD-Energy code compliance9/6/20059/7/20059/7/2005APASS
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
BLD-Framing/Rough-in9/6/20059/7/20059/7/2005APASS
DetailsTom Arcoraci
Phone #: ###-#### Internet Inspection Request from: Ken Litzinger
BLD-Framing/Rough-in9/1/20059/1/20059/1/2005APART
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Ken Litzinger pending truss bracing as noted on engineering. ok to insulate.
BLD-Framing/Rough-in8/29/20058/29/20058/29/2005AFAIL
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Ken Litzinger need anchor bolts 36 oc at sheer panels/ block and nail roof to sheer panels with a35s an 2.5 conections ok to insulate will need si for epoxy.
BLD-Aging Inspection8/22/20058/22/20058/22/2005 PASS
DetailsJim Storey
wip
BLD-Foundation6/21/20056/21/20056/21/2005PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 6/21/2005 at 7:34:03 AM. Contact: ###-####.
BLD-Footing6/16/20056/16/20056/16/2005PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 6/16/2005 at 9:31:21 AM. Contact: ###-####.