BLD-Final | 9/28/2005 | 9/29/2005 | 9/29/2005 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 9/28/2005 at 12:58:22 PM. Contact: ###-####. ok for perm. c of o
|
Permanent Occupancy | | 9/29/2005 | 9/29/2005 | | DONE |
|
|
|
|
BLD-Final | 9/15/2005 | 9/16/2005 | 9/16/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/15/2005 at 3:57:56 PM. Contact: ###-####. pending elec approval
|
FIRE-Final Inspection | 9/14/2005 | 9/15/2005 | 9/15/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
Code Occupancy Approval | 9/15/2005 | 9/15/2005 | 9/15/2005 | A | PASS |
Wm. Michael Meloy
|
|
|
Compliance met.
|
FIRE-Conference | 8/29/2005 | 8/30/2005 | 8/31/2005 | P | DONE |
Forrest France
|
|
|
On site discussion with Tom from CM company regarding fire lane curb painting.
|
BLD-Other | 8/10/2005 | 8/11/2005 | 8/11/2005 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/10/2005 at 5:00:56 PM. Contact: ###-####. ceiling grid ok, pending trades
|
FIRE-Conference | 8/1/2005 | 8/2/2005 | 8/2/2005 | P | DONE |
Troy Cobbley
|
|
|
The exit light out of the west exit door needs to be lowered to be viewabel from below the soffit or an additional exit sign will need to be provided in the lower ceiling.
|
BLD-Framing/Rough-in | 6/29/2005 | 6/30/2005 | 6/30/2005 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/29/2005 at 10:12:51 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 6/24/2005 | 6/24/2005 | 6/27/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/24/2005 at 7:08:58 AM. Contact: ###-####.steel stud framing int ok need to fire stop wood ext walls ok to insulate
|
BLD-Framing/Rough-in | 6/15/2005 | 6/16/2005 | 6/16/2005 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/15/2005 at 10:54:30 AM. Contact: ###-####. roof and exterior shear/brace ok to cover
|
BLD-Concrete | 5/19/2005 | 5/19/2005 | 5/19/2005 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/19/2005 at 9:34:40 AM. Contact: ###-####.
pend s. i. 5/20/2005 9:58:10 AM
|
BLD-Concrete | 5/16/2005 | 5/17/2005 | 5/17/2005 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/16/2005 at 12:51:22 PM.
pending si report 5/17/2005 1:27:56 PM
|
BLD-Footing | 5/9/2005 | 5/10/2005 | 5/10/2005 | A | PART |
Tony Young
|
|
|
tom; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
pend s i 5/10/2005 3:20:47 PM
|
BLD-Footing | 5/5/2005 | 5/6/2005 | 5/6/2005 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/5/2005 at 3:37:17 PM. Contact: ###-####.
portion of west ftg 5/6/2005 10:39:32 AM
|
BLD-Footing | 5/6/2005 | 5/6/2005 | 5/6/2005 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/5/2005 at 3:37:17 PM. Contact: ###-####.
canopy tfgs,, pending s. i. report 5/9/2005 8:10:20 AM
|
BLD-Foundation | 5/2/2005 | 5/3/2005 | 5/3/2005 | A | PART |
Tony Young
|
|
|
tom pallsen; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
pend. si ,,,, point load ftgs,, and part of wall 5/3/2005 10:33:13 AM
|
BLD-Footing | 4/27/2005 | 4/28/2005 | 4/28/2005 | A | PART |
Tony Young
|
|
|
TOM; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
pending s. i. report,,,wip 4/28/2005 12:51:17 PM
|
BLD-Footing | 4/25/2005 | 4/26/2005 | 4/26/2005 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 4/25/2005 at 2:12:18 PM. Contact: ###-####.
east part of ftg,, pending S. I. report 4/26/2005 10:22:59 AM
|