Permit Information
Permit NumberBLD05-00545
StatusFinaled
Name CHRIS PALMER (OWN REP)
Site Address 519 S 8TH ST
Project Name8TH & FULTON BLDG
Customer Number 
ePlanReviewNo
Description
(8TH & FULTON BUILDING - BASEMENT STORAGE) This building is fully fire sprinklered because of low fire-flows and because the basement windows are too small. Fire sprinklers also substitute for the basement enclosure. To create a nonrated corridor within the basement of an existing building. A total of four (4) storage areas will be created. Work is to include interior nonbearing walls and interior doors. All work shall comply with the approved drawings, the plan review report, approved modifications, and all applicable codes. The location of fire sprinkler heads shall comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/1/20065/2/20065/2/2006PPASS
DetailsDave Hannah
chris ###-#### - re-insp--left lighting worksheet calculations in office
DOC - Permit Finaled5/2/20065/2/20065/2/2006PPASS
DetailsDave Hannah
BLD-Final4/26/20064/26/20064/26/2006PFAIL
DetailsJim Storey
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung need wattage calc./ signage and tape on header beam back exit.
FIRE-Final Inspection4/25/20064/26/20064/26/2006APASS
DetailsForrest France
Fire life safety passed inspection.
FIRE-Final Inspection4/20/20064/21/20064/21/2006ACANC
DetailsTroy Cobbley
chris; Phone #: ###-#### Per contractor he was not prepared for the sprinkler inspection and would just reschedule for next week.
BLD-Framing/Rough-in12/14/200512/16/200512/16/2005PPASS
DetailsDave Hannah
chris; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in12/9/200512/12/200512/12/2005ANR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/9/2005 at 3:04:49 PM. Contact: ###-####.
BLD-Conference12/5/200512/7/200512/7/2005APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 12/5/2005 at 11:06:58 AM. Contact: ###-####. work about to start
BLD-Aging Inspection8/30/20058/30/20058/30/2005 PASS
DetailsDave Hannah