FIRE-Final Inspection | 6/6/2008 | 6/9/2008 | 6/10/2008 | A | PASS |
Troy Cobbley
|
|
|
fire life safety passed
|
BLD-Conference | 6/5/2008 | 6/5/2008 | 6/5/2008 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 5/22/2008 | 5/22/2008 | 5/23/2008 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Conference | 4/8/2008 | 4/15/2008 | 4/15/2008 | A | PASS |
Tom Arcoraci
|
|
|
see tom
|
BLD-Conference | 4/8/2008 | 4/8/2008 | 4/8/2008 | P | PASS |
Tom Arcoraci
|
|
|
roof top garden ok to occupy
|
FIRE-Sprinkler Rough-in | 4/4/2008 | 4/7/2008 | 4/7/2008 | A | DONE |
Troy Cobbley
|
|
|
The inspection today was for the roof top garden area. The fire life safety for this area is passed. The smoke detector for the sliding window and the fire alarm as-builts are needed prior to final.
|
BLD-Conference | 4/4/2008 | 4/4/2008 | 4/4/2008 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Sprinkler Rough-in | 4/4/2008 | 4/4/2008 | 4/4/2008 | P | CANC |
Troy Cobbley
|
|
|
carl Phone #: ###-####
|
BLD-Other | 3/25/2008 | 3/25/2008 | 3/25/2008 | P | PASS |
Tom Arcoraci
|
|
|
see Tom
|
BLD-Other | 3/14/2008 | 3/14/2008 | 3/14/2008 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 3/6/2008 | 3/6/2008 | 3/6/2008 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 3/3/2008 | 3/3/2008 | 3/3/2008 | P | PART |
Tom Arcoraci
|
|
|
|
FIRE-Conference | 2/25/2008 | 2/25/2008 | 2/26/2008 | P | CANC |
Troy Cobbley
|
|
|
|
BLD-Conference | 2/12/2008 | 2/13/2008 | 2/13/2008 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Conference | 2/12/2008 | 2/12/2008 | 2/12/2008 | P | CANC |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 2/11/2008 | 2/12/2008 | 2/12/2008 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the 2ND floor south tower at the cafeteria. Two additional emergency lights are required as discussed in the corridor side of the cafeteria east exit
|
FIRE-Final Inspection | 1/16/2008 | 1/17/2008 | 1/18/2008 | P | PART |
Troy Cobbley
|
|
|
Life safety for the 9th floor is passed. The 4th floor garden area is being submitted for plan review comments per tom hayes. Re-inspection of the garden area will be needed when the plans are issued. Also need the 2nd floor cafeteria area/corridors inspected as well.
|
BLD-Final | 1/17/2008 | 1/18/2008 | 1/18/2008 | A | PART |
Tom Arcoraci
|
|
|
ok temp 9 th floor
|
BLD-Conference | 1/14/2008 | 1/16/2008 | 1/16/2008 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 1/11/2008 | 1/11/2008 | 1/14/2008 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 1/9/2008 | 1/10/2008 | 1/11/2008 | A | PART |
Troy Cobbley
|
|
|
The 6th, 7th and 8th floor life safety is complete. The 4th floor garden are needs the emergency light at the stairs repaired and the sprinkler head just inside of the stairway door provided with a canopy and the tape removed. The fire watch can be discontinued as per Dave Hanniman. The 9th floor life safety stills needs to be completed as well as the 2nd, 3rd, 4th and 5th floor tie ins.
|
BLD-Conference | 1/9/2008 | 1/10/2008 | 1/10/2008 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 1/9/2008 | 1/9/2008 | 1/9/2008 | P | CANC |
Troy Cobbley
|
|
|
tom Phone #: ###-####
|
BLD-Conference | 1/8/2008 | 1/9/2008 | 1/9/2008 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 1/2/2008 | 1/2/2008 | 1/2/2008 | P | FAIL |
Troy Cobbley
|
|
|
The inspection was for the life safety on the 8th and 9th floors. The inspection was stopped on the eighth floor due to exit sign locations not matching the city approved plans. Also one exit sign was not working. Tom directed the electrician to install per the plans and per the installation on the 4th and 5th floors.
|
BLD-Wall cover | 12/19/2007 | 12/19/2007 | 12/20/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 12/12/2007 | 12/12/2007 | 12/12/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 11/19/2007 | 11/20/2007 | 11/20/2007 | P | CANC |
Tom Arcoraci
|
|
|
see tom
|
BLD-Final | 11/20/2007 | 11/20/2007 | 11/20/2007 | P | PASS |
Tom Arcoraci
|
|
|
see tom ok temp occ 5 floor
|
FIRE-Final Inspection | 11/8/2007 | 11/9/2007 | 11/9/2007 | A | PART |
Troy Cobbley
|
|
|
The 4th and 5th floors of the central tower are ok to occupy. The interconnections at teh 4th and 5th floors to the north tower are not complete yet and are to be blocked off until work is complete.
|
BLD-Final | 11/8/2007 | 11/9/2007 | 11/9/2007 | P | PART |
Tom Arcoraci
|
|
|
4 and 5 ok for temp occ 4th floor only
|
FIRE-Final Inspection | 11/7/2007 | 11/7/2007 | 11/8/2007 | P | CANC |
Troy Cobbley
|
|
|
tom - fire life safety Phone #: ###-####
|
BLD-Final | 11/7/2007 | 11/8/2007 | 11/8/2007 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 11/2/2007 | 11/2/2007 | 11/2/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Conference | 10/24/2007 | 10/24/2007 | 10/24/2007 | P | PASS |
Tom Arcoraci
|
|
|
temp ok asu ssu 2nd level
|
FIRE-Final Inspection | 10/24/2007 | 10/24/2007 | 10/24/2007 | P | PART |
Troy Cobbley
|
|
|
The ASU SSU portion of the project is ok to occupy.
|
FIRE-Final Inspection | 10/23/2007 | 10/23/2007 | 10/24/2007 | P | CANC |
Troy Cobbley
|
|
|
The project related fire alarm and fire sprinkler permits need finaled first.
|
FIRE-Final Inspection | 10/17/2007 | 10/18/2007 | 10/19/2007 | P | CANC |
Troy Cobbley
|
|
|
Duplicate inspection
|
FIRE-Final Inspection | 10/19/2007 | 10/19/2007 | 10/19/2007 | P | PASS |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave hannimans permission. The temporary occupancy is for only the areas as agreed upon by McCarthy Construction, Boise Fire Dept. and the Building Department. These areas include the basement, 1st floor, 2nd floor, 3rd floor, 6th floor, 7th floor and penthouse. A fire watch is to remain on the 6th and 7th floors.
|
BLD-Final | 10/19/2007 | 10/19/2007 | 10/19/2007 | P | PART |
Tom Arcoraci
|
|
|
basement floor 1 2 3 and pent/house ok for temp occ 6 and 7 ok for shell and core future space
|
BLD-Final | 10/18/2007 | 10/18/2007 | 10/18/2007 | P | DEFR |
Tom Arcoraci
|
|
|
|
BLD-Final | 10/17/2007 | 10/18/2007 | 10/18/2007 | A | DEFR |
Tom Arcoraci
|
|
|
|
BLD-Conference | 10/10/2007 | 10/17/2007 | 10/17/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 10/9/2007 | 10/11/2007 | 10/11/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 10/3/2007 | 10/10/2007 | 10/10/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 10/3/2007 | 10/3/2007 | 10/4/2007 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was to check the operation of the emergency lights and exit signs. We found out that by testing the emergency generator the pharmacy would be shut down which was not going to be acceptable by the st als people so no test was performed.
|
BLD-Wall cover | 10/2/2007 | 10/3/2007 | 10/3/2007 | P | PART |
Tom Arcoraci
|
|
|
wip ok
|
FIRE-Final Inspection | 10/1/2007 | 10/2/2007 | 10/3/2007 | A | CANC |
Troy Cobbley
|
|
|
Overbooked
|
FIRE-Final Inspection | 9/28/2007 | 10/1/2007 | 10/2/2007 | A | FAIL |
Troy Cobbley
|
|
|
I walked through the phase 1 areas with Wayne and looked at the placement of exit signs, fire extinguishers and door hardware only. See the city approved plans for locations of deficiencies. I also noted the lack of emergency lights and exit signs on the roof top which exits people to the stairwells. An emergency generator test of the emergency lighting will need to be scheduled.
|
FIRE-Final Inspection | 9/26/2007 | 9/27/2007 | 10/1/2007 | A | CANC |
Troy Cobbley
|
|
|
Tom; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
FIRE-Final Inspection | 9/25/2007 | 9/26/2007 | 10/1/2007 | A | CANC |
Troy Cobbley
|
|
|
Tom; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
BLD-Conference | 9/26/2007 | 9/26/2007 | 9/26/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 9/24/2007 | 9/25/2007 | 9/25/2007 | A | CANC |
Troy Cobbley
|
|
|
TOM Phone #: ###-####
|
FIRE-Final Inspection | 9/21/2007 | 9/24/2007 | 9/24/2007 | A | CANC |
Troy Cobbley
|
|
|
I need the project related fire sprinkler and fire alarm passed prior to life safety.
|
BLD-Conference | 9/20/2007 | 9/21/2007 | 9/21/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | CANC |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler finaled.
|
FIRE-Final Inspection | 9/19/2007 | 9/19/2007 | 9/19/2007 | P | CANC |
Troy Cobbley
|
|
|
Tom, ###-####
|
FIRE-Final Inspection | 9/18/2007 | 9/18/2007 | 9/18/2007 | P | CANC |
Troy Cobbley
|
|
|
tom Phone #: ###-####
|
BLD-Conference | 9/18/2007 | 9/18/2007 | 9/18/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 9/17/2007 | 9/17/2007 | 9/17/2007 | P | CANC |
Troy Cobbley
|
|
|
The project related fire alarm and fire sprinkler are not passed yet.
|
FIRE-Final Inspection | 9/13/2007 | 9/14/2007 | 9/14/2007 | A | CANC |
Troy Cobbley
|
|
|
wayne - fire life safety Phone #: ###-####
|
FIRE-Final Inspection | 9/12/2007 | 9/13/2007 | 9/13/2007 | A | CANC |
Troy Cobbley
|
|
|
Need the related fire alarm and fire sprinkler passed first
|
FIRE-Final Inspection | 9/12/2007 | 9/12/2007 | 9/12/2007 | P | CANC |
Troy Cobbley
|
|
|
I spoke to wayne by phone and told him that I would not do the life safety inspection until the fire alrm and sprinklers were complete.
|
FIRE-Final Inspection | 9/7/2007 | 9/10/2007 | 9/11/2007 | A | CANC |
Troy Cobbley
|
|
|
tom - fire life safety Phone #: ###-####
|
FIRE-Final Inspection | 9/6/2007 | 9/7/2007 | 9/7/2007 | A | CANC |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler permits finaled first.
|
FIRE-Final Inspection | 9/5/2007 | 9/5/2007 | 9/5/2007 | P | CANC |
Troy Cobbley
|
|
|
As stated in the previous entries no life safety inspection will be performed until the related fire alarm and fire sprinkler permits are finaled. No inspection was performed.
|
FIRE-Final Inspection | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | CANC |
Troy Cobbley
|
|
|
I left a message with Toms secretary that I would not perform the life safety inspection until the alarm and fire sprinkler permits have been completed as was previously stated.
|
BLD-Conference | 8/28/2007 | 8/29/2007 | 8/29/2007 | P | PASS |
Tom Arcoraci
|
|
|
see tom
|
BLD-Wall cover | 8/28/2007 | 8/28/2007 | 8/28/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Other | 8/3/2007 | 8/3/2007 | 8/3/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 8/2/2007 | 8/2/2007 | 8/2/2007 | P | PASS |
Tom Arcoraci
|
|
|
area 1 ok for move in of owner items pending other inspectors
|
BLD-Other | 8/2/2007 | 8/2/2007 | 8/2/2007 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 7/31/2007 | 8/1/2007 | 8/1/2007 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 7/25/2007 | 7/26/2007 | 7/26/2007 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 7/25/2007 | 7/25/2007 | 7/25/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 7/18/2007 | 7/18/2007 | 7/18/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Conference | 7/6/2007 | 7/11/2007 | 7/11/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok 2 3 floor
|
BLD-Wall cover | 7/5/2007 | 7/6/2007 | 7/6/2007 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 7/5/2007 | 7/5/2007 | 7/5/2007 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 6/27/2007 | 6/27/2007 | 6/27/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Other | 6/18/2007 | 6/18/2007 | 6/18/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 6/5/2007 | 6/6/2007 | 6/6/2007 | P | PART |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 5/31/2007 | 5/31/2007 | 5/31/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 5/23/2007 | 5/23/2007 | 5/23/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 5/9/2007 | 5/9/2007 | 5/9/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 5/1/2007 | 5/2/2007 | 5/2/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 4/18/2007 | 4/25/2007 | 4/25/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 4/16/2007 | 4/18/2007 | 4/18/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip
|
BLD-Wall cover | 4/10/2007 | 4/11/2007 | 4/12/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Other | 4/5/2007 | 4/11/2007 | 4/11/2007 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Other | 4/2/2007 | 4/3/2007 | 4/3/2007 | P | PASS |
Tom Arcoraci
|
|
|
ben 2 wip ok
|
BLD-Wall cover | 3/28/2007 | 3/28/2007 | 3/28/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 3/21/2007 | 3/21/2007 | 3/21/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 3/13/2007 | 3/14/2007 | 3/14/2007 | A | PASS |
Tom Arcoraci
|
|
|
see tom wip ok
|
BLD-Wall cover | 3/1/2007 | 3/5/2007 | 3/5/2007 | P | PASS |
Tom Arcoraci
|
|
|
see tom wip ok
|
BLD-Wall cover | 3/1/2007 | 3/1/2007 | 3/1/2007 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 2/5/2007 | 2/14/2007 | 2/14/2007 | P | PASS |
Jim Storey
|
|
|
see tom at 1:30 ###-#### fourth floor verified pipe collors in place at traps.
|
BLD-Wall cover | 1/31/2007 | 2/6/2007 | 2/6/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip
|
BLD-Wall cover | 2/5/2007 | 2/5/2007 | 2/5/2007 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 1/31/2007 | 1/31/2007 | 1/31/2007 | P | PASS |
Tom Arcoraci
|
|
|
see tom
|
BLD-Conference | 1/23/2007 | 1/24/2007 | 1/24/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 1/22/2007 | 1/22/2007 | 1/22/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 1/18/2007 | 1/19/2007 | 1/19/2007 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 1/17/2007 | 1/18/2007 | 1/18/2007 | P | PART |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 1/17/2007 | 1/17/2007 | 1/18/2007 | P | PART |
Tom Arcoraci
|
|
|
wip
|
BLD-Wall cover | 1/9/2007 | 1/10/2007 | 1/10/2007 | P | FAIL |
Tom Arcoraci
|
|
|
eng jud for floor pents not approved
|
BLD-Conference | 1/5/2007 | 1/5/2007 | 1/5/2007 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 12/21/2006 | 12/21/2006 | 12/21/2006 | P | CANC |
Tom Arcoraci
|
|
|
see tom
|
BLD-Other | 12/15/2006 | 12/15/2006 | 12/15/2006 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Other | 12/4/2006 | 12/5/2006 | 12/5/2006 | P | PASS |
Tom Arcoraci
|
|
|
see tom disc on fire stopping
|
BLD-Wall cover | 11/29/2006 | 12/1/2006 | 12/1/2006 | A | NR |
Tom Arcoraci
|
|
|
see tom 8 am
|
BLD-Wall cover | 11/28/2006 | 11/29/2006 | 11/29/2006 | P | PASS |
Tom Arcoraci
|
|
|
tower
|
BLD-Conference | 11/15/2006 | 11/21/2006 | 11/21/2006 | A | PART |
Tom Arcoraci
|
|
|
10:30 tower
|
BLD-Wall cover | 11/14/2006 | 11/15/2006 | 11/15/2006 | P | PASS |
Tom Arcoraci
|
|
|
curtain wall nr
|
BLD-Wall cover | 11/14/2006 | 11/15/2006 | 11/15/2006 | A | PART |
Tom Arcoraci
|
|
|
tower
|
BLD-Final | 11/9/2006 | 11/15/2006 | 11/14/2006 | P | CANC |
Tom Arcoraci
|
|
|
tower insp see tom
|
BLD-Wall cover | 11/14/2006 | 11/14/2006 | 11/14/2006 | P | PART |
Tom Arcoraci
|
|
|
fire joint
|
BLD-Wall cover | 11/1/2006 | 11/8/2006 | 11/8/2006 | P | PASS |
Tom Arcoraci
|
|
|
tower insp wip ok n/ east 2nd floor
|
BLD-Wall cover | 11/1/2006 | 11/8/2006 | 11/8/2006 | A | PASS |
Tom Arcoraci
|
|
|
tower insp wip
|
BLD-Wall cover | 10/25/2006 | 11/1/2006 | 11/1/2006 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 10/24/2006 | 10/25/2006 | 10/25/2006 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Other | 10/12/2006 | 10/18/2006 | 10/18/2006 | P | PASS |
Tom Arcoraci
|
|
|
tower insp wip ok
|
BLD-Wall cover | 10/4/2006 | 10/11/2006 | 10/11/2006 | P | PASS |
Tom Arcoraci
|
|
|
tower insp wip ok
|
BLD-Wall cover | 10/6/2006 | 10/6/2006 | 10/6/2006 | P | PASS |
Tom Arcoraci
|
|
|
conf on smoke partions and barriers
|
BLD-Wall cover | 10/4/2006 | 10/5/2006 | 10/5/2006 | P | PART |
Tom Arcoraci
|
|
|
1:30 pm 3rd floor cover marked on plan 2nd floorcover of ops 1-6 ok except at smoke barrier needs design for gas lines ect in wall
|
BLD-Conference | 9/27/2006 | 10/4/2006 | 10/4/2006 | P | PASS |
Tom Arcoraci
|
|
|
tower insp 2nd floor ops 1-6 ok need to check cont of s/b and f/stop of 6 in pvc drains
|
BLD-Other | 9/19/2006 | 9/27/2006 | 9/27/2006 | P | PASS |
Tom Arcoraci
|
|
|
tower insp 2nd floor ops mock up ok for cover hard lids ok east of ops mok up for cover
|
BLD-Other | 9/19/2006 | 9/19/2006 | 9/19/2006 | P | PASS |
Tom Arcoraci
|
|
|
josh Note: stud wall cover; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles 3rd floor cover
|
FIRE-Final Inspection | 9/15/2006 | 9/15/2006 | 9/15/2006 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given for the basement mech. room. See history for FIR05-00633
|
BLD-Other | 8/3/2006 | 8/3/2006 | 8/3/2006 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/3/2006 at 7:37:27 AM. Contact: ###-####. Partial Framing OK 3rd floor West side highlighted on master plan......few areas above ceiling line that need inspection of continuous gyp and firestopping.....check prior to appr of grid ceiling. Need to verify 1hr walls in basement and firestop penitrations prior to installation of hard lid....(2) selected small rooms.
|
BLD-Energy code compliance | 6/21/2006 | 6/22/2006 | 6/22/2006 | A | PART |
Dave Hannah
|
|
|
tom ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley stage and class room area ground level ext walls ok to cover
|
BLD-Framing/Rough-in | 6/15/2006 | 6/15/2006 | 6/15/2006 | P | PART |
Dave Hannah
|
|
|
Tom Hayes; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt stage and class room area ground level ok to insulate ext wall and one side int walls
|
BLD-Framing/Rough-in | 3/30/2006 | 3/30/2006 | 3/30/2006 | P | PART |
Tom Arcoraci
|
|
|
tom hayes; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa basement walls ok
|
BLD-Framing/Rough-in | 3/20/2006 | 3/20/2006 | 3/20/2006 | P | PART |
Dave Hannah
|
|
|
tom ###-#### - cover up - little stud framing ok to two side area marked on master plan in main office
|
BLD-Framing/Rough-in | 3/13/2006 | 3/13/2006 | 3/13/2006 | P | PART |
Tom Arcoraci
|
|
|
tom ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie OK WIP
|
BLD-Framing/Rough-in | 3/6/2006 | 3/6/2006 | 3/6/2006 | P | PART |
Tom Arcoraci
|
|
|
mccarthy construction- tom hayes; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 1/11/2006 | 1/11/2006 | 1/11/2006 | P | PART |
Tom Arcoraci
|
|
|
tom ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie conf on shaft at north tower area
|
BLD-Aging Inspection | 12/30/2005 | 12/30/2005 | 12/30/2005 | | PASS |
Tom Arcoraci
|
|
|
|