Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD05-00946
StatusFinaled
Name GEORGE FISCHER CONSTRUCTION
Site Address 515 S 9TH ST
Project NamePROCLARITY
Customer Number 
ePlanReviewNo
Description
(PROCLARITY) Exterior and interior remodel to an existing 6,497 sq. ft. building per approved plans and CZC05-00071. The building has an existing 2,940 sq. ft. basement that will be sealed off and become crawlspace with crawlspace access only and have no use or storage allowed. Work to include a new exterior accessible ramp and stairway with handrails and guard, some new exterior doors and windows, some exterior stucco work, new skylight/solatube installations, some exterior wall infill, some new interior walls and doors, interior finish, some suspended ceiling work, a new accessible restroom, mechanical work including two new rooftop HVAC units and a new furnace, plumbing work, and electrical work. DEFERRED SUBMITTAL: Please provide structural engineering verification/calculations for the existing roof structure to support the new rooftop HVAC units to the Building Inspector in the field. Also please provide a copy to plan review. A Certificate of Occupancy is to be issued when completed and approved. NOTE: This building is not fire sprinklered. JCB
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/14/20057/15/20057/15/2005APASS
DetailsDave Hannah
larry; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for perm occ
FIRE-Final Inspection7/14/20057/15/20057/15/2005APASS
DetailsForrest France
Fire life safety passed inspection.
BLD-Final7/14/20057/14/20057/15/2005PCANC
DetailsDave Hannah
Permanent Occupancy 7/15/20057/15/2005 DONE
Details
BLD-Final7/13/20057/14/20057/14/2005ANR
DetailsDave Hannah
larry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore needs fire sign off and ada signage on restroom
BLD-Final7/14/20057/14/20057/14/2005ACANC
DetailsDave Hannah
FIRE-Final Inspection7/13/20057/14/20057/14/2005AFAIL
DetailsForrest France
Provide approved remote annunciator for attic HVAC smoke detector, provide the correct sign above main entry/exit, provide current annual inspection tags on fire extinguishers, remove all storage items in the basement- no storage or use of the basement allowed under this permit.
FIRE-Final Inspection7/13/20057/13/20057/13/2005PFAIL
DetailsForrest France
Repair emergency light/exit sign at back door, test HVAC duct smoke detection devices, provide proper verbage on sign above door at main entry/exit, provide annual inspection tags on fire extinguishers, repair two exit signs at main entry, repair main exit discharge light.
BLD-Final7/13/20057/13/20057/13/2005PCANC
DetailsDave Hannah
larry; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa///Cancel per Larry///7/13/05 1:00pm BAS
BLD-Conference6/28/20056/29/20056/29/2005APART
DetailsDave Hannah
LARRY; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles went over what he needs ot doe to get occ
FIRE-Final Inspection6/29/20056/29/20056/29/2005PFAIL
DetailsForrest France
Door hardware not installed yet, exit signs and emergency lights not installed yet, HVAC needs smoke detection, no fire ext. installed yet, manual flush bolts on back exit door are not allowed, no building address posted, additional review needed when ready for inspection.
BLD-Framing/Rough-in6/15/20056/15/20056/16/2005PPASS
DetailsDave Hannah
larry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok to cover walls