BLD-Final | 11/8/2005 | 11/9/2005 | 11/9/2005 | P | PASS |
Jim Sly
|
|
|
Rob; Phone #: ###-#### Internet Inspection Request from: Barbara Moore C/C issued.
|
DOC - Permit Finaled | 11/9/2005 | 11/9/2005 | 11/9/2005 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 7/12/2005 | 7/12/2005 | 7/12/2005 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/12/2005 at 10:33:40 AM.
|
BLD-Framing/Rough-in | 7/11/2005 | 7/12/2005 | 7/12/2005 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/11/2005 at 4:26:03 PM. Contact: ###-####. c/n made ok
|
BLD-Framing/Rough-in | 7/11/2005 | 7/11/2005 | 7/11/2005 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/11/2005 at 8:31:29 AM. Contact: ###-####. c/n posted,, ok to insulate
|
BLD-Framing/Rough-in | 7/8/2005 | 7/8/2005 | 7/8/2005 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/8/2005 at 8:53:40 AM. Contact: ###-####. insulaters were on the job,,, called contractor,, pulled insulaters off job,, c/n posted to call for conf. and to have plans and engineering on job,, to do frame inspection
|
BLD-Framing/Rough-in | 7/7/2005 | 7/7/2005 | 7/8/2005 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/7/2005 at 10:35:27 AM. Contact: ###-####. needs plumbing r/i and seal package installed
|
BLD-Foundation | 5/11/2005 | 5/11/2005 | 5/11/2005 | P | PART |
Tony Young
|
|
|
rob ###-####; Internet Inspection Request from: Letitia Mesa
|
BLD-Footing | 5/10/2005 | 5/10/2005 | 5/10/2005 | P | PART |
Tony Young
|
|
|
###-#### doug
added rebar 5/10/2005 3:17:03 PM
|
BLD-Footing | 5/9/2005 | 5/9/2005 | 5/9/2005 | P | CANC |
Tony Young
|
|
|
###-#### doug - doug cancelled 10:30 am
|
BLD-Footing | 5/5/2005 | 5/6/2005 | 5/6/2005 | A | PART |
Tony Young
|
|
|
chris ###-####
early start,, appears ok 5/6/2005 11:06:56 AM
|