Code Occupancy Approval | 4/3/2006 | 4/3/2006 | 4/3/2006 | P | PASS |
Scott M.Brown
|
|
|
FINAL OK ALSO OK TO RELASE BOND.
|
BLD-Final | 11/28/2005 | 11/29/2005 | 11/29/2005 | A | PEND |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/28/2005 at 3:17:41 PM. Contact: ###-####. Will be ok for temp. occ once code enforcement has been finaled.
|
BLD-Final | 11/28/2005 | 11/28/2005 | 11/28/2005 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/28/2005 at 8:23:25 AM. Contact: ###-####. Still needs to post bond.
|
FIRE-Final Inspection | 11/23/2005 | 11/25/2005 | 11/25/2005 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
Code Occupancy Approval Temp | 11/23/2005 | 11/23/2005 | 11/23/2005 | P | FAIL |
Scott M.Brown
|
|
|
need to bond $51,000 for landscape, curbing, paint, parking lot stripping.
|
FIRE-Final Inspection | 11/22/2005 | 11/23/2005 | 11/23/2005 | P | CANC |
Troy Cobbley
|
|
|
No time for inspection
|
BLD-Final | 11/23/2005 | 11/23/2005 | 11/23/2005 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/23/2005 at 9:23:09 AM. Contact: ###-####. Need Code enforce, Fire and...........finals
|
FIRE-Final Inspection | 11/21/2005 | 11/21/2005 | 11/21/2005 | P | CANC |
Troy Cobbley
|
|
|
No time for inspection but I talked to Bob with Lea Electric about the correct remote annunciators for the duct smoke detectors. What they had was wrong per Bob.
|
BLD-Framing/Rough-in | 11/10/2005 | 11/14/2005 | 11/14/2005 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/10/2005 at 4:08:20 PM. Contact: ###-####. Hangars were nailed off. Reviewed RFI From engineer detailing welded connection at column to beam connection.
|
BLD-Framing/Rough-in | 10/18/2005 | 10/18/2005 | 10/18/2005 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/18/2005 at 7:04:32 AM. Contact: ###-####.nail hip hangers/weld colm. to post.
|
BLD-Energy code compliance | 10/14/2005 | 10/14/2005 | 10/14/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/14/2005 at 7:26:55 AM. Contact: ###-####.ok to cover walls / pending hip ridge hanger nailling and vapor barrior at overbuilds can check no ceilling .
|
BLD-Framing/Rough-in | 10/10/2005 | 10/10/2005 | 10/10/2005 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/10/2005 at 8:00:45 AM. Contact: ###-####.c/n posted/ok to insulate.
|
BLD-Framing/Rough-in | 9/30/2005 | 9/30/2005 | 9/30/2005 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 9/30/2005 at 7:38:09 AM. Contact: ###-####. roof and wall sheer nailling ok.
|
BLD-Other | 9/28/2005 | 9/28/2005 | 9/29/2005 | P | NR |
Jim Storey
|
|
|
steve Note: shear and/or roof; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Aging Inspection | 9/27/2005 | 9/27/2005 | 9/27/2005 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Foundation | 7/26/2005 | 7/27/2005 | 7/27/2005 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/26/2005 at 11:05:20 AM.
|
BLD-Footing | 7/20/2005 | 7/22/2005 | 7/22/2005 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/20/2005 at 2:59:20 PM.
|