BLD-Aging Inspection | 8/3/2006 | 8/3/2006 | 8/3/2006 | | CANC |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 8/3/2006 | 8/3/2006 | 8/3/2006 | A | PASS |
Mike Jordan
|
|
|
ok for perm occ.
|
BLD-Aging Inspection | 5/12/2006 | 5/12/2006 | 5/16/2006 | | PASS |
Troy Cobbley
|
|
|
Fire life safety ok to final. Fire alarm permit has been finaled.
|
Permanent Occupancy | | 11/30/2005 | 11/30/2005 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/20/2005 | 10/28/2005 | 10/28/2005 | A | FAIL |
Troy Cobbley
|
|
|
Fire alarm was not ready
|
FIRE-Conference | 10/20/2005 | 10/21/2005 | 10/23/2005 | P | NR |
Troy Cobbley
|
|
|
Fire alarm permit needs finaled. Per Ralph with Alarmco the work will be done next week and the inspection called in.
|
BLD-Final | 8/29/2005 | 8/29/2005 | 8/29/2005 | P | PART |
Jim Sly
|
|
|
bob-- cell ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie OK for Temp......OK to final for Perm when Fire finals for Perm. C/N Obtain Perm Occ status within 90 days of this notice.
|
BLD-Final | 8/26/2005 | 8/26/2005 | 8/29/2005 | P | NR |
Jim Sly
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
FIRE-Final Inspection | 8/26/2005 | 8/26/2005 | 8/26/2005 | P | PART |
Forrest France
|
|
|
Temporary occupancy approved with Sam Rogers permission pending the installation of HVAC duct smoke detectors.
|
BLD-Final | 8/25/2005 | 8/26/2005 | 8/26/2005 | A | NR |
Jim Sly
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Need Fire
|
FIRE-Final Inspection | 8/24/2005 | 8/25/2005 | 8/25/2005 | P | FAIL |
Forrest France
|
|
|
Need to repair emergency discharge light at back exit, need to mount the two fire extinguishers provided for the sales floor, need to install remaining ceiling tile and sprinkler escutcheons, provide fire alarm permit and duct smoke detectors.
|
FIRE-Final Inspection | 8/16/2005 | 8/17/2005 | 8/17/2005 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for insulation being re-attached to the deck since it was previously laying on the sprinkler piping. The insulation over the sales floor has been repaired but over the restrooms and offices there are still problems. Ceiling is ok to be installed but office area/restroom will need to be spot checked at the building final.
|
BLD-Framing/Rough-in | 8/16/2005 | 8/17/2005 | 8/17/2005 | A | PART |
Jim Sly
|
|
|
ceiling grid///tom; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Footing | 8/2/2005 | 8/3/2005 | 8/3/2005 | A | PART |
Jim Sly
|
|
|
tom; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa 2 footings at N wall OK......Talked with Eng..... Greg No special insp req.
|
BLD-Framing/Rough-in | 7/25/2005 | 7/26/2005 | 7/26/2005 | A | PART |
Mike Jordan
|
|
|
###-#### Tom \\metal framing insp.
|