FIRE-Final Inspection | 6/14/2006 | 6/14/2006 | 6/14/2006 | | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Final | 5/30/2006 | 5/30/2006 | 5/30/2006 | P | PASS |
Jim Sly
|
|
|
Anna, : ); Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
DOC - Permit Finaled | 5/30/2006 | 5/30/2006 | 5/30/2006 | P | PASS |
Jim Sly
|
|
|
|
Permanent Occupancy | | 5/30/2006 | 5/30/2006 | | DONE |
|
|
|
|
BLD-Final | 12/15/2005 | 12/15/2005 | 12/15/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/15/2005 at 9:47:10 AM. Contact: ###-####. OK for Temp Occ. OK to Perm when Fire Perms. ():
|
FIRE-Final Inspection | 12/15/2005 | 12/15/2005 | 12/15/2005 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Hannimen's permission until the fire alarm permit is finaled. The exit sign on the second floor at the top of the west stairs needs repaired and the emergency light on the first floor east exit needs repaired.
|
BLD-Conference | 12/12/2005 | 12/13/2005 | 12/13/2005 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/12/2005 at 12:30:09 PM. Contact: ###-####. Reviewed letter from Architect justifying and approving 12ga wire at 7' 6" supporting cold rolled steel carrying 2nd floor ceiling.
|
BLD-Framing/Rough-in | 12/8/2005 | 12/9/2005 | 12/9/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/8/2005 at 12:44:16 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 12/7/2005 | 12/7/2005 | 12/7/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/7/2005 at 9:14:48 AM. Contact: ###-####. need to complete Firestopping at walls above F R ceiling 2nd Flr.
|
BLD-Framing/Rough-in | 11/28/2005 | 11/28/2005 | 11/28/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/28/2005 at 8:34:57 AM. Contact: ###-####. 1st layer (shaft bd) at 1hr wall 2nd floor near ceiling OK OK to install 2nd layer ....(5/8 rock)
|
BLD-Framing/Rough-in | 11/22/2005 | 11/23/2005 | 11/23/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/22/2005 at 3:27:52 PM. Contact: ###-####. Insp of 1st layer shaft wall 2nd flr.....Need to firestop and re-inspect.
|
BLD-Framing/Rough-in | 11/10/2005 | 11/14/2005 | 11/14/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/10/2005 at 12:53:58 PM. Contact: ###-####. Need UL design from Arch for N. wall 2nd floor.
|
BLD-Framing/Rough-in | 11/2/2005 | 11/3/2005 | 11/3/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/2/2005 at 3:43:31 PM. Contact: ###-####.
|
BLD-Conference | 11/2/2005 | 11/2/2005 | 11/2/2005 | P | DONE |
Jim Sly
|
|
|
per your request Internet Inspection Request from: Letitia Mesa Talked to Dan about Stamped letters and details fro Architect for any changes made on the approved plan.
|
BLD-Framing/Rough-in | 10/27/2005 | 10/28/2005 | 10/28/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/27/2005 at 10:11:48 AM. Contact: ###-####. Framing around all beams 1st floor OK
|
BLD-Framing/Rough-in | 10/17/2005 | 10/18/2005 | 10/18/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/17/2005 at 1:38:57 PM. Contact: ###-####. Framing around small beams to allow for 2 5/8 rock. OK
|
BLD-Concrete | 10/11/2005 | 10/12/2005 | 10/12/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/11/2005 at 11:36:20 AM. Contact: ###-####. Dan talked with Engineer.....No special insp req at concrete floor deck.
|
BLD-Conference | 9/22/2005 | 9/22/2005 | 9/22/2005 | P | PART |
Jim Sly
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Need some one to approve modified listed tested assembly for protection of columns..... referred Architect to Plan check and George Slane.
|
BLD-Footing | 8/31/2005 | 8/31/2005 | 8/31/2005 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/31/2005 at 9:28:15 AM. Contact: ###-####. Talked to Dan..... 3000 psi conc Req. special insp.....Or letter from Eng of record to reduce design strength to 2500
|