BLD-Final | 5/10/2006 | 5/10/2006 | 5/10/2006 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/10/2006 at 8:14:37 AM. Contact: ###-####. C/C issued
|
DOC - Permit Finaled | 5/10/2006 | 5/10/2006 | 5/10/2006 | P | PASS |
Jim Sly
|
|
|
|
Permanent Occupancy | | 5/10/2006 | 5/10/2006 | | DONE |
|
|
|
|
Permanent Occupancy | | 5/10/2006 | 5/10/2006 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 5/10/2006 | | |
|
|
|
|
FIRE-Final Inspection | 1/12/2006 | 1/13/2006 | 1/13/2006 | A | PASS |
Troy Cobbley
|
|
|
life safety finaled
|
BLD-Final | 12/30/2005 | 1/3/2006 | 1/3/2006 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/30/2005 at 1:10:02 PM. Contact: ###-####. OK for Temp Occ..........OK for Perm Occ when Fire Perms.
|
FIRE-Final Inspection | 12/30/2005 | 12/30/2005 | 12/30/2005 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Hanneman's permission. Items needing addressing are syncing of the horns, mount map at facp, reverify signals (zone 10), and get the resubmitted plans approved.
|
FIRE-Final Inspection | 12/29/2005 | 12/29/2005 | 12/29/2005 | P | FAIL |
Troy Cobbley
|
|
|
Plug sprinkler heads mounted horizontally in the T.I. space. Reinstall the ball drip at the FDC. Certify the backflow preventor. Relocate the bell to the FDC. Provide above ground hydro test papers. Resubmit fire alarm plans showing the flow switch and tamper switch. Test all of the a/v's. Test all of the elevator functions/recall. Test the access controlled egress doors. Provide map at the FACP. Provide printout of the fire alarm signals. Provide minimum 8.3 AH batteries for the FACP. Life safety is ok to final when all of this is done.
|
BLD-Other | 12/2/2005 | 12/2/2005 | 12/2/2005 | P | PASS |
Jim Sly
|
|
|
mike Note: ceiling grid; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Grid ok
|
BLD-Framing/Rough-in | 10/11/2005 | 10/11/2005 | 10/11/2005 | P | PASS |
Mike Jordan
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|