BLD-Final | 10/25/2006 | 10/26/2006 | 10/26/2006 | A | PASS |
Jim Sly
|
|
|
jim ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith OK for Perm Occ. :)
|
Permanent Occupancy | | 10/26/2006 | 10/26/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/24/2006 | 10/25/2006 | 10/25/2006 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled. THe correct door hardware has been installed.
|
BLD-Final | 10/10/2006 | 10/11/2006 | 10/11/2006 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Temp occ granted. All life/safety issues have been resolved. Waiting for ada counter tops and additional door hardware.
|
BLD-Final | 10/3/2006 | 10/4/2006 | 10/4/2006 | A | FAIL |
Mike Jordan
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. No handrails installed at ramp or stairs at front enterance. Riser height on conc. stairs at front enetrance exceed the max 7 inch allowable. Handrail not continous at new stairway. Needs to have ada accessible counters at cashier and service counter.
|
FIRE-Final Inspection | 9/27/2006 | 9/28/2006 | 9/28/2006 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Hanniman's permission until the two man doors on the east side of the showroom have been provided with approved door hardware.
|
Code Occupancy Approval | | | 9/27/2006 | | PASS |
|
|
|
FINAL SIGNED OFF
|
BLD-Framing/Rough-in | 8/25/2006 | 8/25/2006 | 8/25/2006 | P | PASS |
Mike Jordan
|
|
|
charlie - ceiling grid; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. Remainder of show room.
|
FIRE-Conference | 7/17/2006 | 7/17/2006 | 7/17/2006 | P | DONE |
Troy Cobbley
|
|
|
Dan and I went over inspection procedure for the sprinkler system above the special ceiling.
|
BLD-Conference | 7/17/2006 | 7/17/2006 | 7/17/2006 | P | PART |
Mike Jordan
|
|
|
dan -call 1st before insp ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. ceiling grid. reviewed submittals. west half of showroom. Due to differnt type of system ele. and mech. has agreed to insp aftewr first half is complete.
|
BLD-Framing/Rough-in | 7/10/2006 | 7/10/2006 | 7/10/2006 | P | PASS |
Mike Jordan
|
|
|
charlie; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. mezz. framing in existing bldg.
|
BLD-Framing/Rough-in | 5/3/2006 | 5/3/2006 | 5/3/2006 | P | PASS |
Mike Jordan
|
|
|
charlie; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Final | 4/12/2006 | 4/13/2006 | 4/13/2006 | P | CANC |
Mike Jordan
|
|
|
Rom; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Framing/Rough-in | 4/13/2006 | 4/13/2006 | 4/13/2006 | P | PART |
Mike Jordan
|
|
|
Rom; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. Contractor to fax special inspection report to structural engineer for approval of changes. Also need to add the hilti pins along back wall. Area of inspection is mezz.
|
BLD-Other | 3/29/2006 | 3/30/2006 | 3/30/2006 | A | PASS |
Mike Jordan
|
|
|
tom Note: structural steel columns - joyces; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Reveiwed special insp. reports and performed a partial insp. on welded connections.
|
BLD-Foundation | 2/24/2006 | 2/24/2006 | 2/24/2006 | P | PART |
Mike Jordan
|
|
|
re-bar and masonary grout insp//grouting at 1pm//tom; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. West wall, top of wall. Also reveiwed special inspection reports.
|
BLD-Foundation | 2/21/2006 | 2/21/2006 | 2/21/2006 | P | DEFR |
Mike Jordan
|
|
|
masonary wall, grout and re-bar insp//grouting at 1pm// tom; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Wall inspected by special inspector.
|
BLD-Concrete | 2/16/2006 | 2/16/2006 | 2/16/2006 | P | DEFR |
Mike Jordan
|
|
|
rebar for concrete Tom ###-####
|
BLD-Other | 2/14/2006 | 2/14/2006 | 2/14/2006 | P | PART |
Mike Jordan
|
|
|
re-bar and grout inspection//tom; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Footing | 2/9/2006 | 2/9/2006 | 2/9/2006 | P | PASS |
Mike Jordan
|
|
|
Tom -- for slab; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Foundation | 1/19/2006 | 1/19/2006 | 1/19/2006 | P | PASS |
Mike Jordan
|
|
|
tom; Phone #: ###-#### Note: before 3:00 conrete pour Internet Inspection Request from: Cathy Chiles. Perimeter stemwalls.
|
BLD-Footing | 1/17/2006 | 1/17/2006 | 1/17/2006 | P | PART |
Mike Jordan
|
|
|
tom ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Conc placed when on site. Noted that contractor had special insp.
|
BLD-Footing | 1/12/2006 | 1/12/2006 | 1/12/2006 | P | PART |
Mike Jordan
|
|
|
tom; Phone #: ###-#### Internet Inspection Request from: Barbara Moore. east west and south perimeter footings. wip
|