Code Occupancy Approval | 4/28/2008 | 3/28/2008 | 4/28/2008 | P | PASS |
Carol Montgomery
|
|
|
Everything has been completed per the plans signed and approved and on site. Compliance Met. Closed.
|
FIRE-Conference | 4/25/2008 | 4/25/2008 | 4/25/2008 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 4/2/2008 | 4/3/2008 | 4/3/2008 | P | PASS |
Jim Sly
|
|
|
mike Phone #: ###-#### OK for Perm Occ.
|
BLD-Final | 3/24/2008 | 3/25/2008 | 3/25/2008 | P | NR |
Jim Sly
|
|
|
jade - ###-#### Talked to Jade......Can't final until plumb finals. ACHD?
|
FIRE-Final Inspection | 3/24/2008 | 3/24/2008 | 3/24/2008 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given, with dave hannimans permission, until the fire lane to the northwest has been completed. All other items are passed.
|
Code Occupancy Approval Temp | | | 3/14/2008 | | DONE |
|
|
|
Bond has been received and in place on CUP04-00137. Temporary signed.
|
BLD-Conference | 3/11/2008 | 3/12/2008 | 3/12/2008 | A | DONE |
Jim Sly
|
|
|
mike Note: also with George please Phone #: ###-#### C/N Do not proceed with any work that is not contained within a set of approved plans located at jobsite......Changes and addendums to the original approved plans to be included as a complete set of drawings of what is built.
|
BLD-Conference | 3/11/2008 | 3/11/2008 | 3/11/2008 | P | PASS |
Jim Sly
|
|
|
Set up meeting 3/12/08.....
|
BLD-Conference | 3/10/2008 | 3/10/2008 | 3/10/2008 | P | CANC |
Jim Sly
|
|
|
mike Phone #: ###-####
|
Code Occupancy Approval Temp | 3/6/2008 | 3/6/2008 | 3/6/2008 | P | CANC |
Carol Montgomery
|
|
|
N/R - need to post bond $69,000.00+ for temporary. Called Cathy and gave her information for bonding
|
BLD-Energy code compliance | 12/31/2007 | 1/2/2008 | 1/2/2008 | P | PASS |
Jim Sly
|
|
|
mike Phone #: ###-####
|
BLD-Framing/Rough-in | 12/19/2007 | 12/20/2007 | 12/20/2007 | A | PASS |
Jim Sly
|
|
|
for cover please-Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 11/20/2007 | 11/21/2007 | 11/21/2007 | A | PASS |
Jim Sly
|
|
|
mike - exterior part 2 of 2 Phone #: ###-####
|
BLD-Other | 11/7/2007 | 11/7/2007 | 11/7/2007 | P | PART |
Jim Sly
|
|
|
Exterior for cover for part 1 of 2--Mike; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt S and E walls OK
|
BLD-Other | 11/1/2007 | 11/2/2007 | 11/2/2007 | A | FAIL |
Mike Jordan
|
|
|
mike Note: cover on the admin bld Phone #: ###-####. On site to inspect soffitt, noted type 2b const. Contractor has placed non fire rated osb behind soffitt. No combustibles allowed. Did note that plans on site called for osb, but were not the approved set. will reshedule for Monday and have approved set of drawings.
|
BLD-Framing/Rough-in | 10/25/2007 | 10/26/2007 | 10/26/2007 | A | PART |
Jim Sly
|
|
|
mike - metal steel - interior and exterior Phone #: ###-#### Talked to Mike about 3 studs required at all roof joist point loads ( 1 area ) and 1 area with studs offset at point load......will address with Engineer. After Engineer and STRATA ok..........OK to cover exterior.
|
BLD-Concrete | 9/24/2007 | 9/24/2007 | 9/24/2007 | P | PASS |
Jim Sly
|
|
|
craig Note: late afternoon please for inspection Phone #: ###-#### Remainder of CMU....trash and radius walls....OK
|
BLD-Concrete | 9/20/2007 | 9/21/2007 | 9/21/2007 | P | PART |
Jim Sly
|
|
|
Greg Phone #: ###-#### CMU wall at radius wall and walls for trash enclosures appear OK up to 4' high......
|
BLD-Wall cover | 7/17/2007 | 7/18/2007 | 7/18/2007 | P | PART |
Jim Sly
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang Wall and interior column pads OK pending special insp, and tests by STRATA
|
BLD-Footing | 7/11/2007 | 7/11/2007 | 7/11/2007 | P | PART |
Jim Sly
|
|
|
mike - rebar Phone #: 308- South and part of E wall......2nd 5' lift......OK pend special insp (strata) tests and approvals.
|
BLD-Footing | 7/5/2007 | 7/6/2007 | 7/6/2007 | A | PART |
Jim Sly
|
|
|
mike - rebar Phone #: ###-#### Rebar at tower columns and walls OK pending special insp/ Rick Cummings and Tests and approvals from STRATA.
|
BLD-Footing | 6/29/2007 | 6/29/2007 | 6/29/2007 | P | PART |
Jim Sly
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang Select footings and wall (5' lift)........OK pending special insp..........and testing by STRATA.
|
BLD-Other | 6/26/2007 | 6/26/2007 | 6/26/2007 | P | PART |
Jim Sly
|
|
|
mike Note: rebar Phone #: ###-#### Footing OK for Observation tower pending rebar insp by Rick Cummings (Certified reinforced concrete special insp) and tests and approvals from STRATA .
|
BLD-Footing | 6/20/2007 | 6/20/2007 | 6/20/2007 | P | PART |
Jim Sly
|
|
|
dave - ###-#### OK pending special inspection by Rick Cummings.
|
BLD-Aging Inspection | 11/30/2006 | 11/30/2006 | 11/30/2006 | | PEND |
Jim Sly
|
|
|
Talked to architect........still out for bid.
|