BLD-Final | 11/21/2006 | 11/21/2006 | 11/21/2006 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 11/21/2006 | 11/21/2006 | 11/21/2006 | P | PASS |
Mike Jordan
|
|
|
Letter og compliance issued for shell and core. PIV valve relocated to outside of bldg, therefore riser room no longer required to be 1 hr const. Also noted fire sprinklers at canopy area, draftstop not required as previously mentioned.
|
Code Occupancy Approval | | | 11/21/2006 | | PASS |
|
|
|
OBTAINED PLANNING APROVALS FOR CHANGES FINAL SIGNED OFF.
|
FIRE-Final Inspection | 11/9/2006 | 11/9/2006 | 11/9/2006 | A | PASS |
Forrest France
|
|
|
Required corrections have been verified for completion, shell fire life safety passed.
|
FIRE-Final Inspection | 11/6/2006 | 11/6/2006 | 11/6/2006 | A | FAIL |
Forrest France
|
|
|
Missing fire dept. access curb lettering, address as posted is missing one number, need to final fire sprinkler permit prior to shell life safety final.
|
COD-Stop Work/Reinspection DR | | 8/18/2006 | 8/18/2006 | | FAIL |
Scott M.Brown
|
|
|
SITE NOT TO APPROVED DR APPROVAL. DRIVEWAY, PARKING LOT, REDUCED PARKING SPACES AND MISSING REQUIRED LANDSCAPE.
|
BLD-Framing/Rough-in | 5/25/2006 | 5/25/2006 | 5/25/2006 | P | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 5/25/2006 at 8:20:43 AM. Contact: ###-####. Mech room is required to be 1hr. const. due to riser. Submit detail for 1hr wall and ceiling assembly.
|
BLD-Energy code compliance | 4/14/2006 | 4/14/2006 | 4/14/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/14/2006 at 9:32:53 AM. Contact: ###-####. Needs to provide fireblocking from toop of cmu wall to underneath side of roof deck at canopy area.
|
BLD-Framing/Rough-in | 3/30/2006 | 3/30/2006 | 3/30/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/30/2006 at 7:07:35 AM. Contact: ###-####.
|
BLD-Other | 3/16/2006 | 3/16/2006 | 3/16/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/16/2006 at 10:37:59 AM. Contact: ###-####. Roof sheating and hardware.
|
BLD-Foundation | 1/25/2006 | 1/26/2006 | 1/26/2006 | A | DONE |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/25/2006 at 3:05:09 PM. Contact: ###-####. Not a foundation insp. Bldg. confrence. Reviewed all special insp reports for compliance on footings foundations and masonry wall constructed to date.
|