Information based on query as of Monday, July 8, 2024.
Permit Information
Permit NumberBLD05-02919
StatusFinaled
Name HOBBS ENTERPRISES LLC
Site Address 11031 W GREYLING DR
Project Name 
Customer Number 
ePlanReviewNo
Description
Early start approved per Steve Monroe///11/10/05 BAS - To construct a 4237sq.ft. Two story single family dwelling (2581sq.ft. Main floor / 1656sq.ft. Upper floor) with a 174sq.ft. Covered front porch, and a 1104sq.ft. Attached three car side load garage per approved plans, all red-lining, and Plan review report. THE PERMIT HOLDER is responsible to comply with current wall bracing requirements adopted by the city of Boise. R-1C zoning/setbacks as per Evelyn Grimes with Planning and Zoning. (SRZ)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/27/20064/28/20064/28/2006PPASS
DetailsMike Jordan
final inspection requested; Phone #: ###-#### Internet Inspection Request from: larry hobbs
DOC - Permit Finaled4/28/20064/28/20064/28/2006PPASS
DetailsMike Jordan
BLD-Wall cover2/8/20062/9/20062/9/2006PPASS
DetailsMike Jordan
this is a request for a insulation inspection after 12 p.m.thanks Internet Inspection Request from: larry hobbs. All framing issues have been repaired. ok to cover.
BLD-Framing/Rough-in2/2/20062/3/20062/3/2006AFAIL
DetailsMike Jordan
request framing inspection; Phone #: ###-#### Internet Inspection Request from: larry hobbs. Complete lateral bracing on C01 truss. Additional studs required at the 3 11 7/8 ML. Truss engineering shows continous bearing at D01 truss. Additional blocking required under floor at bearing points. c/n posted.
BLD-Foundation11/17/200511/18/200511/18/2005APART
DetailsMike Jordan
larry hobbs ###-####
BLD-Footing11/14/200511/14/200511/14/2005PPART
DetailsMike Jordan
###-#### larry