BLD-Conference | 11/8/2006 | 11/9/2006 | 11/9/2006 | A | DONE |
Jim Sly
|
|
|
Internet Inspection Request from: Patricia Smith
|
BLD-Final | 11/8/2006 | 11/9/2006 | 11/8/2006 | A | PASS |
Jim Sly
|
|
|
blane; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles OK for Perm Occ. :)
|
Code Occupancy Approval | | | 11/8/2006 | | PASS |
|
|
|
|
COD-Stop Work/Reinspection DR | 6/12/2006 | 6/12/2006 | 7/10/2006 | P | DONE |
Carol Montgomery
|
|
|
paid under case # cod06-00918 customer receipt # 3200300000000010018
|
BLD-Final | 6/5/2006 | 6/6/2006 | 6/6/2006 | A | NR |
Jim Sly
|
|
|
Phone #: Blaine ###-#### Talked to Blaine....trying to get a variance landscape rock in leiu of bark.......Need Code enforce final......Blaine said that they didn't do any HVAC and Electrical was existing. They didn't run any new circuits.
|
FIRE-Final Inspection | 6/1/2006 | 6/2/2006 | 6/2/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
FIRE-Final Inspection | 5/31/2006 | 6/1/2006 | 6/1/2006 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 5/31/2006 at 2:30:06 PM. Contact: ###-####. per blaine tanner change time
|
FIRE-Final Inspection | 5/23/2006 | 5/23/2006 | 5/24/2006 | P | FAIL |
Troy Cobbley
|
|
|
don coatworth ; Phone #: ###-#### Two doors have been added that are not shown on the plans. All of the exits require exit discharge lighting and the plans call for the doors that cars come through to have panic hardware but they do not. Contractor is going to resubmit to John Menard with plan review and inspection will be called back in.
|
BLD-Final | 5/15/2006 | 5/16/2006 | 5/16/2006 | A | FAIL |
Dave Hannah
|
|
|
blaine tanner -call 1st before insp; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie needs fire life/safty and code enforcement finals
|
BLD-Framing/Rough-in | 3/27/2006 | 3/27/2006 | 3/27/2006 | P | PASS |
Jim Sly
|
|
|
Blaine Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Energy code compliance | 3/10/2006 | 3/13/2006 | 3/13/2006 | P | PASS |
Tom Arcoraci
|
|
|
Blaine -- insulation and suspended ceiling; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong insul ok
|
BLD-Energy code compliance | 3/7/2006 | 3/8/2006 | 3/8/2006 | A | NR |
Jim Sly
|
|
|
Blaine -- efis stucco insp and insulation; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong Insulaters need to install approved vapor barreir that meets flame and smoke.
|
BLD-Framing/Rough-in | 2/16/2006 | 2/16/2006 | 2/16/2006 | P | PASS |
Jim Sly
|
|
|
Blaine; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong All framing pass
|
BLD-Foundation | 1/24/2006 | 1/25/2006 | 1/25/2006 | A | PART |
Jim Sly
|
|
|
Kenyon; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong Found wall at E. 1/2 of front of bldg OK pend MTI special insp, tests and appr.
|
BLD-Footing | 1/20/2006 | 1/24/2006 | 1/24/2006 | A | PART |
Jim Sly
|
|
|
STS Contractors; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Foot at E. 1/2 of front of Bldg.......OK pending MTI insp, tests, and approvals.
|
BLD-Conference | 1/11/2006 | 1/11/2006 | 1/12/2006 | P | DONE |
Jim Sly
|
|
|
kenyon--; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|