BLD-Final | 3/5/2008 | 3/5/2008 | 3/5/2008 | P | PASS |
Jim Sly
|
|
|
allen Phone #: ###-#### OK for Perm Occ. :)
|
Code Occupancy Approval | 2/27/2008 | 2/27/2008 | 2/27/2008 | P | PASS |
Carol Montgomery
|
|
|
|
BLD-Conference | 2/21/2008 | 2/22/2008 | 2/22/2008 | A | DONE |
Jim Sly
|
|
|
Phone # ? Go to site and check out. Talked to Alan ###-####. Will proceed to final.
|
BLD-Conference | 2/20/2008 | 2/21/2008 | 2/21/2008 | A | CANC |
Jim Sly
|
|
|
Call sign center and discuss req.for perm Occ.
|
FIRE-Alarm Testing | 12/12/2006 | 12/12/2006 | 12/12/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
FIRE-Final Inspection | 12/1/2006 | 12/4/2006 | 12/4/2006 | A | FAIL |
Troy Cobbley
|
|
|
Need fire alarm and fire sprinkler permits finaled and then life safety will be inspected.
|
BLD-Final | 7/26/2006 | 7/27/2006 | 7/27/2006 | P | PART |
Jim Sly
|
|
|
vern ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley OK for Temp Occ..........OK to Perm, when Fire and Code enforce Perms.
|
FIRE-Final Inspection | 7/26/2006 | 7/27/2006 | 7/27/2006 | A | PASS |
Troy Cobbley
|
|
|
A temporary occupancy was given until the south tenant is complete
|
BLD-Final | 7/24/2006 | 7/25/2006 | 7/25/2006 | P | CANC |
Jim Sly
|
|
|
Vern : ); Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
FIRE-Final Inspection | 7/24/2006 | 7/25/2006 | 7/25/2006 | A | FAIL |
Troy Cobbley
|
|
|
Fire alarm inspection failed
|
FIRE-Final Inspection | 7/21/2006 | 7/21/2006 | 7/21/2006 | P | FAIL |
Troy Cobbley
|
|
|
Still need the fire alarm permit finaled. Life safety for the shell and Sign Company tenant is ok for a temporary occupancy once the fire alarm is a go. The south tenant work is ongoing at this time.
|
BLD-Final | 7/21/2006 | 7/21/2006 | 7/21/2006 | P | CANC |
Jim Sly
|
|
|
vern; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
FIRE-Final Inspection | 7/19/2006 | 7/20/2006 | 7/20/2006 | A | FAIL |
Troy Cobbley
|
|
|
The fire alarm and fire spirnkler permits need t be finaled, exit signs and emergency lights need repaired and approved hardware installed on the second floor restroom doors.
|
FIRE-Conference | 6/28/2006 | 6/29/2006 | 6/29/2006 | A | DONE |
Troy Cobbley
|
|
|
Vern requested occupying the building with the first tenant while finish construction was taking place in the second tenant space. Per Dave Hanniman and I this will be ok as long as the fire sprinklers, fire alarm and fire life safety is complete for the shell and the tenant space that is going to be occupied.
|
BLD-Energy code compliance | 3/23/2006 | 3/24/2006 | 3/24/2006 | A | PASS |
Jim Sly
|
|
|
vern; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 3/22/2006 | 3/22/2006 | 3/22/2006 | P | PASS |
Jim Sly
|
|
|
Vern -- prefer late afternoon; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Footing | 2/7/2006 | 2/7/2006 | 2/7/2006 | P | PART |
Jim Sly
|
|
|
slab and footing re-bar inspection//vern; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
Center (E.-W.) footing OK pending MTI special insp tests and approvals
|
BLD-Footing | 1/30/2006 | 1/31/2006 | 1/31/2006 | A | PART |
Jim Sly
|
|
|
vern nielson; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Int pads at N 1/2 of Bldg
|