Permit NumberBLD05-03335
StatusFinaled
Name MCCARTER-MOORHOUSE CO INC
Site Address 10233 W OVERLAND RD
Project NameWalker Dental
Customer Number 
ePlanReviewNo
Description
RCE# FOR MCCARTER-MOORHOUSE CO INC/-Walker Office Building - To construct a 2,765 sq. ft one story type VB office building with a 1,002 sq. ft. basement. Other work includes all site improvements, paving and landscaping per approved plans and attachments, DRH05-00281.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 11/17/200611/17/2006 DONE
Details
BLD-Final11/10/200611/13/200611/13/2006APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 11/10/2006 at 8:31:10 AM. Contact: ###-####. Handrail installed. Gave temp occ. Will be ok for perm occ once code enforcement has finaled.
BLD-Final11/8/200611/9/200611/9/2006PFAIL
DetailsMike Jordan
dana; Phone #: ###-#### Internet Inspection Request from: Patricia Smith. Needs to install additional handrail.
FIRE-Final Inspection11/8/200611/9/200611/9/2006APASS
DetailsForrest France
Fire life safety passed final inspeciton.
Code Occupancy Approval Temp  11/9/2006  
Posted Bond for trash enclosure. Temporary Occ. O.K. ($1,650.00).
FIRE-Final Inspection11/7/200611/8/200611/8/2006AFAIL
DetailsForrest France
Project related fire sprinkler permit failed final inspection.
FIRE-Final Inspection11/7/200611/7/200611/7/2006PFAIL
DetailsForrest France
The project related fire sprinkler permit must be approved and finaled prior to building life safety final.
BLD-Framing/Rough-in9/14/20069/15/20069/15/2006APASS
DetailsMike Jordan
dena Note: fire wall; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Inspected 1hr wall assembly and horizontal wall assembly for stair enclosure.
BLD-Energy code compliance9/1/20069/5/20069/5/2006APASS
DetailsMike Jordan
dana; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley 1hr staairway const. has been addressed. Received RFI from Architect regarding 1hr const. Will inspect stairway when one sided. insul. ok.
BLD-Framing/Rough-in8/29/20068/30/20068/30/2006PFAIL
DetailsMike Jordan
dana ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley. 1hr construction required at stairway enclosure from basement to 1st floor.
BLD-Wall cover6/29/20066/29/20066/29/2006PPASS
DetailsMike Jordan
DANA; Phone #: ###-#### Internet Inspection Request from: Darla Downs. Exterior shear wall nailing.
BLD-Footing5/31/20065/31/20065/31/2006PPART
DetailsMike Jordan
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung perimeter and interior footings. footing backfill with clean drain rock.
BLD-Foundation5/15/20065/15/20065/15/2006PPASS
DetailsMike Jordan
jed; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Basement walls
BLD-Footing5/9/20065/10/20065/10/2006APART
DetailsMike Jordan
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung. wip. Noted no special insp. required for conc. Contractor noted that soils was inspected for bottom of footing for basement walls and will have documentation on next insp.